| Requirement 1) | |||||
| (A) | (B) | (C ) | (D )=(C )/(B) | ||
| Subunit X | Actual Result | Flexible Budget | Flexible Budget Variance(F )/(U) | % of variance (F )/(U) | |
| Direct Material | $ 28,900.00 | $ 26,800.00 | $ 2,100.00 | (U) | 7.84% |
| Direct Labor | $ 13,900.00 | $ 14,600.00 | $ 700.00 | (F) | 4.79% |
| Indirect Labor | $ 26,000.00 | $ 22,900.00 | $ 3,100.00 | (U) | 13.54% |
| Utilities | $ 12,000.00 | $ 11,200.00 | $ 800.00 | (U) | 7.14% |
| Depreciation | $ 27,000.00 | $ 27,000.00 | $ - | 0.00% | |
| Repair & Maintenance | $ 4,700.00 | $ 5,700.00 | $ 1,000.00 | (F) | 17.54% |
| $ 1,12,500.00 | $ 1,08,200.00 | $ 4,300.00 | (U) | 3.97% | |
| Requirement 2) | |||||
| This performance report includes only cost data ,therfore Subunit is a cost centre. | |||||
| Requirement 3) | |||||
| Management first investigate all unfavorable variances. | |||||
| 1) Indirect Labor | |||||
| 2) Direct Material | |||||
| 3) Utilities | |||||
| Requirement 4) | |||||
| No,Favorable variance should be investigated. | |||||
Requirement 1. Complete the performance evaluation report for this subunit Enter the variance percent as a...
Requirements 1. Complete the performance evaluation report for this subunit. 2. Based on the data presented, what type of responsibility center is the subunit? 3. Which items should be investigated if part of management's decision criteria is to investigate all variances exceeding $ 2 comma 800 or 12 % question mark 4. Should only unfavorable variances be investigated? Explain. Requirement 1. Complete the performance evaluation report for this subunit. (Enter the variances as positive numbers. Round the variance percentages to...
Please open enlarge and view. The blue box data table is
included.
Options for requirement 3 are Depreciation, direct labor, direct
materials, indirect labor, repairs and maintenance, utilities
Options for req 4 Yes or no And (never need to be
investigated because they increase net income, should be
investigated to make sure the variance does not happen again,
should be investigated to make sure they are not hurting the
business in the long run.
Х Data Table Flexible Budget Variance...
One subunit of Pike Sports Company had the following financial results last month: Pike-Subunit X Actual Results Flexible Budget Flexible Budget Variance (F or U) % Variance (F or U) Direct Materials $28,800 $27,000 Direct Labor 13,400 14,200 Indirect Labor 26,100 23,000 Utilities 12,200 11,300 Depreciation 29,000 29,000 Repairs and Maintenance 4,800 5,700 Total $114,300 $110,200 Requirements: 1. Complete the performance evaluation report for this subunit. Enter the variance percent as a percentage of the budgeted amount rounded to two...
.
One subunit of Extreme Sports Company had the following financial results last month: (Click the icon to view the financial results.) Read the requirements Requirement 1. Complete the performance evaluation report for this subunit. Enter the variance percent as a percentage of the budgeted amount rounded to two places. (Enter a variance for each account as a positive number, and select whether the variance is favorable [F] or unfavorable [U]. For any zero variances, enter a 0 in the...
%E24-22 (similar to) One subunit of Extreme Sports Company had the following financial results last month: ES: (Click the icon to view the financial results.) Read the requirements Requirement 1. Complete the performance evaluation report for this subunit. Enter the variance percent as a percentage of the b places. (Enter a variance for each account as a positive number and select whether the variance is favorable [F] or unfavorable in the variance column and then leave the For U box...
all information is shown
One subunit of Winter Sports Manufacturing Company had the following financial results last month HE (Click the icon to view the financial results) Requirements 1. Complete the performance evaluation report for this subunit. 2. Based on the data presented, what type of responsibility center is the subunt? 1. Which items should be investigated if part of management's decision criteria is to investigate al variancesceng $3,200 of 10%? 4. Should only unfavorable variances be investigated? Explain Requirement...
One subunit of All Season Sports Manufacturing Company had the following financial results last month: Click the icon to view the financial results.) Requirements 1. Complete the performance evaluation report for this subunit. 2. Based on the data presented, what type of responsibility center is the subunit? 3. Which items should be investigated if part of management's decision criteria is to investigate all variances exceeding $3,200 or 11.5%? 4. Should only unfavorable variances be investigated? Explain. Requirement 1. Complete the...
E24-22 (similar to) One subunit of Extreme Sports Company had the following financial results last month: (Click the icon to view the financial results.) Read the requirements Requirement 1. Complete the performance evaluation report for this subunit. Enter the variance percent as a percentage of for each account as a positive number, and select whether the variance is favorable [F] or unfavorable [U]. For any zero van U box blank. Enter the variance percent as a percentage rounded to two...
One subunit of Winter Sports Manufacturing Company had the following financial results last month: : (Click the icon to view the financial results.) Requirements 1. Complete the performance evaluation report for this subunit. 2. Based on the data presented, what type of responsibility center is the subunit? 3. Which items should be investigated if part of management's decision criteria is to investigate all variances exceeding $3,100 or 13%? 4. Should only unfavorable variances be investigated? Explain. X Reqi varia Data...
Tully Company's production performance report for
April includes the information shown below.
LOADING...
Requirement
Prepare a flexible budget for the items shown and compute the
flexible budget cost variances and planning cost variances for each
item. Indicate whether the variances are favorable or unfavorable
for each item.
Begin with the master budget, then complete the flexible budget
columns and the actual results columns. Label each variance as
favorable (F) or unfavorable (U). (For variances with a $0
balance, make sure...