| 1-a. | ||
| Predetermined overhead rate = Estimated total manufacturing overhead / Estimated total direct labor hours = 1967840 / 100400 | 19.60 | per DLH |
| 1-b. | ||
| Xactive | Pathbreaker | |
| Overhead applied [ Predetermined overhead rate * Direct labor hours ] | 576240 | 1391600 |
| (/) Estimated annual production | 21000 | 71000 |
| Overhead cost per unit | 27.44 | 19.60 |
| Xactive | Pathbreaker | |
| Direct materials per unit | 64.40 | 50.60 |
| Direct labor cost per unit | 17.80 | 12.60 |
| Overhead cost per unit | 27.44 | 19.60 |
| Unit product cost | 109.64 | 82.80 |
| 2. | ||
| Activity cost pools | Activity rate [ Estimated overhead cost / Expected total activity ] | |
| Supporting direct labor | 7.05 | per DLH |
| Batch setup | 1500 | per setup |
| Product sustaining | 327580 | per product |
| General factory | 7.05 | per MHR |
| 3. | ||
| Xactive | Pathbreaker | |
| Overhead alloction : [ Activity rate * Expected activity ] | ||
| Supporting direct labor | 207270 | 500550 |
| Batch setup | 345000 | 195000 |
| Product sustaining | 327580 | 327580 |
| General factory | 14805 | 50055 |
| Total overhead allocated | 894655 | 1073185 |
| (/) Estimated annual production | 21000 | 71000 |
| Overhead cost per unit | 42.60 | 15.12 |
| Xactive | Pathbreaker | |
| Direct materials per unit | 64.40 | 50.60 |
| Direct labor cost per unit | 17.80 | 12.60 |
| Overhead cost per unit | 42.60 | 15.12 |
| Unit product cost | 124.80 | 78.32 |
Direct materials per unit Direct labor cost per unit Direct labor-hours per unit Estimated annual production...
Direct materials per unit Direct labor cont per unit Direct labor-hours per unit Estimated annual production and sales Xactive $ 64.00 $ 17.40 1.4 DLHS 17,000 units $ $ Pathbreaker 50.20 12.20 1 DLHS 67,000 units The company has a conventional costing system in which manufacturing overhead is applied to units based on direct labor-hours. Data concerning manufacturing overhead and direct labor-hours for the upcoming year appear below: Estimated total manufacturing overhead Estimated total direct labor-hours $1,743,360 90,800 DLHS Required:...
y
Rocky Mountain Corporation makes two types of hiking boots-Xactive and Pathbreaker. Data concerning these two product lines appear below: Direct materials per unit Direct labor cost per unit Direct labor. hours per unit Estimated annual production and sales Xactive $ 64.40 $ 17.30 1.4 LHS 21,000 units Pathbreaker $50.60 $12.60 1 DHS 71,000 units The company has a conventional costing system in which manufacturing overhead is applied to units based on direct labor hours. Data concerning manufacturing overhead and...
Rocky Mountain Corporation makes two types of hiking boots-Xactive and Pathbreaker. Data concerning these two product lines appear below: Direct materials per unit Direct labor cost per unit Direct labor-hours per unit Estimated annual production and sales Xactive $ 64.40 $ 17.80 1.4 DLHS 21,000 units Pathbreaker $ 50.60 $ 12.60 1 DLHS 71,000 units The company has a conventional costing system in which manufacturing overhead is applied to units based on direct labor-hours. Data concerning manufacturing overhead and direct...
ter 4 Rocky Mountain Corporation makes two types of hiking boots-Xactive and Pathbreaker. Data concerning these two product lines appear below: $ $ Xactive 63.80 17.20 1.4 DLHS 15,000 units Direct materials per unit Direct labor cost per unit Direct labor-hours per unit Estimated annual production and sales $ $ Pathbreaker 50.00 12.00 1 DLHS 65,000 units The company has a conventional costing system in which manufacturing overhead is applied to units based on direct labor-hours. Data concerning manufacturing overhead...
Rocky Mountain Corporation makes two types of hiking boots-Xactive and Pathbreaker. Data concerning these two product line appear below: Direct materials per unit Direct labor cost per unit Direct labor-hours per unit Estimated annual production and sales $ $ Xactive 65.10 18.5e 1.4 LHS 28,000 units $ $ Pathbreaker 51.30 13.30 1 DLHS 78,000 units The company has a conventional costing system in which manufacturing overhead is applied to units based on direct labor-hours. Data concerning manufacturing overhead and direct...
Rocky Mountain Corporation makes two types of hiking boots-Xactive and Pathbreaker. Data concerning these two product lines appear below: $ $ Direct materials per unit Direct labor cost per unit Direct labor-hours per unit Estimated annual production and sales Xactive 64.20 17.60 1.4 DLHS 19,000 units Pathbreaker 50.40 12.40 1 DLHS 69,000 units The company has a conventional costing system in which manufacturing overhead is applied to units based on direct labor-hours. Data concerning manufacturing overhead and direct labor-hours for...
Rocky Mountain Corporation makes two types of hiking boots-Xactive and Pathbreaker. Data concerning these two product lines appear below: $ $ Direct materials per unit Direct labor cost per unit Direct labor-hours per unit Estimated annual production and sales Xactive Pathbreaker 65.20 $ $1.40 18.60 $ 13.40 1.4 DLHS 1 DLA 29,000 units79,000 units The company has a conventional costing system in which manufacturing overhead is applied to units based on direct labor hours. Data concerning manufacturing overhead and direct...
Rocky Mountain Corporation makes two types of hiking boots-Xactive and Pathbreaker. Data concerning these two product line appear below: Direct materials per unit Direct labor cost per unit Direct labor-hours per unit Estimated annual production and sales Xactive $ 65.70 $ 19.10 1.4 DLHS 34,000 units Pathbreaker $ 51.90 $ 13.90 1 DLHS 84,000 units The company has a conventional costing system in which manufacturing overhead is applied to units based on direct labor-hours Data concerning manufacturing overhead and direct...
Rocky Mountain corporation
Rocky Mountain Corporation makes two types of hiking boots-Xactive and Pathbreaker. Data concerning these two product line appear below: Direct materials per unit Direct labor cost per unit Direct labor-hours per unit Estimated annual production and sales Xactive $65.20 $ 18.60 1.4 DLHS 29,000 units Pathbreaker $ 51.40 $ 13.40 1 DLHS 79,000 units The company has a conventional costing system in which manufacturing overhead is applied to units based on direct labor-hours Data concerning manufacturing overhead...
Check my work Rocky Mountain Corporation makes two types of hiking boots-Xactive and Pathbreaker. Data concerning these two product lines appear below: Direct materials per unit Direct labor cost per unit Direct labor-hours per unit Estimated annual production and sales Xactive $ 64.70 $ 18.10 1.4 DLHS 24,000 units Pathbreaker $ 50.90 $ 12.90 1 DLHS 74,000 units The company has a conventional costing system in which manufacturing overhead is applied to units based on direct labor-hours. Data concerning manufacturing...