Panamint Systems Corporation is estimating activity costs associated with producing disk drives, tapes drives, and wire drives. The indirect labor can be traced to four separate activity pools. The budgeted activity cost and activity base data by product are provided below.
Activity Cost |
Activity Base |
||
Procurement | $371,200 | Number of purchase orders | |
Scheduling | 234,000 | Number of production orders | |
Materials handling | 486,400 | Number of moves | |
Product development | 744,600 | Number of engineering changes | |
Production | 1,479,200 | Machine hours |
Number of Purchase Orders |
Number of Production Orders |
Number of Moves |
Number of Engineering Changes |
Machine Hours |
Number of Units |
|
Disk drives | 4,020 | 260 | 1,440 | 12 | 1,500 | 2,300 |
Tape drives | 2,200 | 245 | 700 | 8 | 8,600 | 4,000 |
Wire drives | 11,500 | 780 | 3,500 | 20 | 10,300 | 2,800 |
The activity-based cost for each wire drive unit is
a.$20.95
b.$644.27
c.$255.61
d.$230.89
The correct answer is b. $ 644.27
Notes:
Number of Purchase Orders | Number of Production orders | Number of Moves | Number of Engineering Changes | Machine Hours | |
Disk drives | 4020 | 260 | 1,440 | 12 | 1,500 |
Tape drives | 2200 | 245 | 700 | 8 | 8,600 |
Wire drives | 11500 | 780 | 3,500 | 20 | 10,300 |
Total Activity | 17720 | 1285 | 5640 | 40 | 20400 |
Activity Cost | Activity Base | Total Activity | Activity Rate ( Activity Cost / Total Activity) | |
Procurement | 371200 | Number of purchase orders | 17720 | 20.94808126410840 |
Scheduling | 2,34,000 | Number of production orders | 1285 | 182.10116731517500 |
Materials handling | 4,86,400 | Number of moves | 5640 | 86.24113475177300 |
Product development | 7,44,600 | Number of engineering changes | 40 | 18,615.00 |
Production | 14,79,200 | Machine hours | 20400 | 72.50980392156860 |
Wire drives | |||
Activity Rate ( Activity Cost / Total Activity) | Activity | Cost ( Activity Rate * Activity) | |
Procurement | 20.94808126 | 11500 | 240902.9345 |
Scheduling | 182.1011673 | 780 | 142038.9105 |
Materials handling | 86.24113475 | 3500 | 301843.9716 |
Product development | 18615 | 20 | 372300 |
Production | 72.50980392 | 10300 | 746850.9804 |
Total Cost | 1803936.797 | ||
Units | 2800 | ||
Per Unit Cost ( Total Cost /Units) | 644.2631418 |
Panamint Systems Corporation is estimating activity costs associated with producing disk drives, tapes drives, and wire...
Panamint Systems Corporation is estimating activity costs associated with producing disk drives, tapes drives, and wire drives. The indirect labor can be traced to four separate activity pools. The budgeted activity cost and activity base data by product are provided below. Activity Cost Activity Base Procurement $374,100 Number of purchase orders Scheduling $208,600 Number of production orders Materials handling $478,000 Number of moves Product development $798,000 Number of engineering changes Production $1,461,200 Machine hours Number of Purchase Orders Number of...
Panamint Systems Corporation is estimating activity costs associated with producing disk drives, tapes drives, and wire drives. The indirect labor can be traced to four separate activity pools. The budgeted activity cost and activity base data by product are provided below. Procurement Scheduling Materials handling Product development Production Activity Cost Activity Base $347,800 Number of purchase orders 205,800 Number of production orders 491,900 Number of moves 779,400 Number of engineering changes 1,418,700 Machine hours Number of Engineering Machine Changes Hours...
Panamint Systems Corporation is estimating activity costs associated with producing disk drives, tapes drives, and wire drives. The indirect labor can be traced to four separate activity pools. The budgeted activity cost and activity base data by product are provided below. Procurement Scheduling Materials handling Product development Activity Cost Activity Base $366,100 Number of purchase orders 244,900 Number of production orders 414,000 Number of moves 720,800 Number of engineering changes 1,584,700 Machine hours Production Number of Engineering Changes Number ol...
Panamint Systems Corporation is estimating activity costs associated with producing disk drives, tapes drives, and wire drives. The indirect labor can be traced to four separate activity pools. The budgeted activity cost and activity base data by product are provided below. Activity Cost Activity Base Procurement $329,900 Number of purchase orders Scheduling 223,700 Number of production orders Materials handling 426,300 Number of moves Product development 762,500 Number of engineering changes Production 1,434,200 Machine hours Number of Purchase Orders Number of...
Panamint Systems Corporation is estimating activity costs associated with producing disk drives, tapes drives, and wire drives. The indirect labor can be traced to four separate activity pools The budgeted activity cost and activity base data by product are provided below Activity Cost Activity Base Number of purchase orders Number of production orders Number of moves Procurement333,500 Scheduling $245,900 Materials handling Product development Production ,513,200 $424,700 $743,700 Number of engineering changes Machine hours Number Number of Number Number of Number...
Panamint Systems Corporation is estimating activity costs associated with producing disk drives, tapes drives, and wire drives. The indirect labor can be traced to four separate activity pools. The budgeted activity cost and activity base data by product are provided below. Activity Cost Activity Base Procurement $368,300 Number of purchase orders Scheduling 205,300 Number of production orders Materials handling 463,200 Number of moves Product development 755,700 Number of engineering changes Production 1,427,300 Machine hours Number of Purchase Orders Number of...
Panamint Systems Corporation is estimating activity costs associated with producing disk drives, tapes drives, and wire drives. The indirect labor can be traced to four separate activity pools. The budgeted activity cost and activity base data by product are provided below. Activity Cost Activity Base Procurement $355,800 Number of purchase orders Scheduling $219,600 Number of production orders Materials handling $486,900 Number of moves Product development $756,500 Number of engineering changes Production $1,495,300 Machine hours Number of Purchase Orders Number of...
Panamint Systems Corporation is estimating activity costs associated with producing disk drives, tapes drives, and wire drives. The indirect labor can be traced to four separate activity pools. The budgeted activity cost and activity base data by product are provided below. Activity Cost Activity Base Procurement $345,800 Number of purchase orders Scheduling $231,000 Number of production orders Materials handling $490,100 Number of moves Product development $785,000 Number of engineering changes Production $1,537,000 Machine hours Number of Purchase Orders Number of...
Panamint Systems Corporation is estimating activity costs associated with producing disk drives, tapes drives, and wire drives. The indirect labor can be traced to four separate activity pools. The budgeted activity cost and activity base data by product are provided below. Procurement Scheduling Materials handling Product development Production Activity Cost Activity Base $302,500 Number of purchase orders 248,300 Number of production orders 496,300 Number of moves 772,900 Number of engineering changes 1,560,800 Machine hours Number of Engineering Changes 10 Number...
Panamint Systems Corporation is estimating activity costs associated with producing disk drives, tapes drives, and wire drives. The indirect labor can be traced to four separate activity pools. The budgeted activity cost and activity base data by product are provided below. Procurement Scheduling Materials handling Product development Production Activity Cost Activity Base $335,300 Number of purchase orders 218,700 Number of production orders 460,700 Number of moves 732,900 Number of engineering changes 1,413,300 Machine hours Number of Purchase Orders Number of...