Need some assistance with this question, please show work if applicable. Thank you!

A quality analyst wants to construct a control chart for controlling the variability of a packaging process. Each day last we

0 0
Add a comment Improve this question Transcribed image text
Answer #1

The problem is you need to use tables for the 3-sigma chart. If you do not share the version of the table you are using in your class, then I will use mine, and then the final answer may change a bit in decimal places.

--------------------

Sample size (n) = 4
Coefficient (A2) = 0.729 (from the table, in your table, it maybe 0.73 or 0.728 and so on)

Day P1 P2 P3 P4 Average Range
Mon 23 22 23 24 23 2
Tue 23 21 19 21 21 4
Wed 20 19 20 21 20 2
Thu 18 19 20 19 19 2
Fri 18 20 22 20 20 4
Avg. 20.6 2.8
X_double-bar R-bar

So,

Upper Control Limit for the range chart, UCL_R = D4 * R-bar = 2.282*2.8 = 6.39

Add a comment
Know the answer?
Add Answer to:
Need some assistance with this question, please show work if applicable. Thank you! A quality analyst...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • > Moving to the next question prevents changes d el 1 points Save Ans Question 16...

    > Moving to the next question prevents changes d el 1 points Save Ans Question 16 Use this information to answer this question: A Quality Analyst wants to construct a sample mean chart for controlling a packaging process. He knows from past experience that whenever this process is under control package weight is normally distributed with a mean of twenty ounces and a standard deviation of two ounces. Each day last week, he randomly selected four packages and weighed each:...

  • Travel Data 10. Using your travel data: a. Develop a 95% confidence interval for your mean...

    Travel Data 10. Using your travel data: a. Develop a 95% confidence interval for your mean time to work (lunch) using time in minutes. b. What assumption is necessary for you to complete part (a)? Do you feel this assumption is valid? 119 B C A 1 TO WORK Time in Day of Week Minutes 2 Date Ce 2-Sep Monday 3-Sep Tuesday 4-Sep Wednesday 5-Sep Thursday 6-Sep Friday 9-Sep Monday 10-Sep Tuesday 11-Sep Wednesday 12-Sep Thursday 13-Sep Friday 16-Sep Monday...

  • ) A cable operator’ quality analyst is monitoring calls from hundred customers randomly on a daily...

    ) A cable operator’ quality analyst is monitoring calls from hundred customers randomly on a daily basis. She notes down instances of incorrect information being passed on to customers; the data collected over five days is given below. Day Monday Tuesday Wednesday Thursday Friday Number of instances of incorrect information 5 10 23 20 15 a) Calculate the upper and lower control limits for her c-chart. 4) The specification for a Lyn's stainless steel chimney liner requires a thickness of...

  • Need some assistance with this question, please show work if applicable. Thank you! A department chair...

    Need some assistance with this question, please show work if applicable. Thank you! A department chair wants to monitor the percentage of failing students in classes in her department. Each class had an enrollment of 50 students last spring. The number of failing students in the 10 classes offered that term were 1, 4, 2, 0, 0, 0, 0, 0, 0, and 3, respectively. Compute the 3-sigma control limits for an appropriate control chart. What is the upper control limit?...

  • VII. Samples of 10 taken in 1985 and 1995 revealed the average time people Data set for those usi...

    VII. Samples of 10 taken in 1985 and 1995 revealed the average time people Data set for those using statistics spend grocery shopping decreased from 18 minutes to 14 minutes. Respective standard deviations were 5 minutes and 4 minutes. Test at the .10 level of significance whether there has been a change in shopping time variability. software Shopping Time 1985 19 17 18 16 18 1995 10 17 20 16 13 18 15 14 23 28 18 VIII. Test at...

  • PHP code for a calendar using  control structures Design Overview and Requirements As part of the...

    PHP code for a calendar using  control structures Design Overview and Requirements As part of the first submission point, you should generate a static calendar for the current month. The current month used for the header and display can be determined in your code by using the date () function. To be eligible for grading you should construct the calendar using one or more control structures nested inside a calendar php script file. An example of how the calendar may...

  • A quality analyst wants to construct a control chart for determining whether three machines, all producing...

    A quality analyst wants to construct a control chart for determining whether three machines, all producing the same product, are in control with regard to a particular quality variable. Accordingly, he sampled four units of output from each machine, with the following results: Machine Measurements #1 17 15 15 17 #2 16 25 18 25 #3 23 24 23 22 What is the estimate of the mean of the sampling distribution for the sample mean? O 20 16 FOOOOO 23...

  • Question 4 options: FC.73 Ties at BYU-Idaho have become very popular since Tie the Knot, an...

    Question 4 options: FC.73 Ties at BYU-Idaho have become very popular since Tie the Knot, an IBC company, has started operations this semester. Sales have consistently increased during the weeks and the company wants to forecast future daily sales using the following data: Day Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Monday 32 29 37 32 35 28 36 Tuesday 22 22 26 30 21 31 30 Wednesday 17 19 21 23 20...

  • Will give positive rating! AM/PM Method Assignment # 03: Calculate the early and late dates for the following activiti...

    Will give positive rating! AM/PM Method Assignment # 03: Calculate the early and late dates for the following activities, and create a bar chart. Assuming a Monday to Friday working week and the first activity starting on Dec 01 20XX. 1-Dec Activity A Activity B Activi Activity F Activity G 2 days da 3 da da 2 da Activity C Activity E 3 da 3 da SUNDAY MONDAY TUESDAY WEDNESDAY THURSDAY FRIDAY SATURDAY 2 4 Fulil Mocn NW 10 12...

  • Need some assistance with this problem, please show work if applicable. Thank you! A small grocery...

    Need some assistance with this problem, please show work if applicable. Thank you! A small grocery store sells fresh produce, which it obtains from a local farmer. During the strawberry season, demand for fresh strawberries can be reasonably approximated using a Normal distribution with a mean of 40 quarts per day and a standard deviation of 6 quarts per day. Excess costs run $0.39 per quart. The grocer orders 49 quarts per day. What is the implied cost of shortage...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT