The following data are given for Stringer Company:
| Budgeted production | 909 units |
| Actual production | 1,036 units |
| Materials: | |
| Standard price per ounce | $1.82 |
| Standard ounces per completed unit | 12 |
| Actual ounces purchased and used in production | 12,805 |
| Actual price paid for materials | $26,250 |
| Labor: | |
| Standard hourly labor rate | $14.95 per hour |
| Standard hours allowed per completed unit | 4.4 |
| Actual labor hours worked | 5,335.4 |
| Actual total labor costs | $81,365 |
| Overhead: | |
| Actual and budgeted fixed overhead | $1,110,000 |
| Standard variable overhead rate | $28.00 per standard labor hour |
| Actual variable overhead costs | $149,391 |
| Overhead is applied on standard labor hours. | |
Round your intermediate calculations and final answer to the nearest cent.
The direct materials price variance is
a.$7,362.87 unfavorable
b.$2,945.15 favorable
c.$7,362.87 favorable
d.$2,945.15 unfavorable
We need at least 10 more requests to produce the answer.
0 / 10 have requested this problem solution
The more requests, the faster the answer.
The following data are given for Stringer Company: Budgeted production 909 units Actual production 1,036 units...
The following data is given for the Stringer Company: Budgeted production 900 units Actual production 1,056 units Materials: Standard price per ounce $1.9 Standard ounces per completed unit 12 Actual ounces purchased and used in production 13,052 Actual price paid for materials $26,757 Labor: Standard hourly labor rate $14.30 per hour Standard hours allowed per completed unit 5.0 Actual labor hours worked 5,438.4 Actual total labor costs $82,936 Overhead: Actual and budgeted fixed overhead $1,153,000 Standard variable overhead rate $28.00...
22. The following data is given for the Stringer Company: Budgeted production 917 units Actual production 1,002 units Materials: Standard price per ounce $1.75 Standard ounces per completed unit 11 Actual ounces purchased and used in production 11,353 Actual price paid for materials $23,274 Labor: Standard hourly labor rate $14.38 per hour Standard hours allowed per completed unit 5.0 Actual labor hours worked 5,160.3 Actual total labor costs $78,695 Overhead: Actual and budgeted fixed overhead $1,124,000 Standard variable overhead rate...
The following data are given for Harry Company: Budgeted production 1,054 units Actual production 937 units Materials: Standard price per ounce $1.919 Standard ounces per completed unit 11 Actual ounces purchased and used in production 10,616 Actual price paid for materials $21,763 Labor: Standard hourly labor rate $14.76 per hour Standard hours allowed per completed unit 4.3 Actual labor hours worked 4,826 Actual total labor costs $78,423 Overhead: Actual and budgeted fixed overhead $1,025,000 Standard variable overhead rate $24.00 per...
Use this information for Stringer Company to answer the question that follow. The following data are given for Stringer Company: Budgeted production 920 units Actual production 1,021 units Materials: Standard price per ounce $1.81 Standard ounces per completed unit 11 Actual ounces purchased and used in production 11,568 Actual price paid for materials $23,714 Labor: Standard hourly labor rate $14.51 per hour Standard hours allowed per completed unit 4.4 Actual labor hours worked 5,258.15 Actual total labor costs $80,187 Overhead:...
The following data is given for the Bahia Company: Budgeted production 1,040 units Actual production 906 units Materials: Standard price per pound $1.866 Standard pounds per completed unit 11 Actual pounds purchased and used in production 9,667 Actual price paid for materials $19,817 Labor: Standard hourly labor rate $14.62 per hour Standard hours allowed per completed unit 4.0 Actual labor hours worked 4,665.9 Actual total labor costs $71,155 Overhead: Actual and budgeted fixed overhead $1,181,000 Standard variable overhead rate $26.00...
Use this information for Stringer Company to answer the question that follow. The following data are given for Stringer Company: 941 units Budgeted production 1,061 units Actual production Materials: $1.77 Standard price per ounce 10 Standard ounces per completed unit 10,928 Actual ounces purchased and used in production $22,402 Actual price paid for materials Labor: $14.86 per hour Standard hourly labor rate Standard hours allowed per completed unit 4.1 Actual labor hours worked 5,464.15 Actual total labor costs $83,328 Overhead:...
The following data is given for the Bahia Company: Budgeted production (at 100% of normal capacity) 1,077 units Actual production 917 units Materials: Standard price per pound $1.76 Standard pounds per completed unit 12 Actual pounds purchased and used in production 10,674 Actual price paid for materials $21,882 Labor: Standard hourly labor rate $14.01 per hour Standard hours allowed per completed unit 4.3 Actual labor hours worked 4,722.55 Actual total labor costs $72,019 Overhead: Actual and budgeted fixed overhead $1,035,000...
1,005 units 956 units $1.90 11 10,201 $20,912 The following data are given for Bahia Company: Budgeted production (at 100% of normal capacity) Actual production Materials: Standard price per pound Standard pounds per completed unit Actual pounds purchased and used in production Actual price paid for materials Labor: Standard hourly labor rate Standard hours allowed per completed unit Actual labor hours worked Actual total labor costs Overhead: Actual and budgeted fixed overhead Standard variable overhead rate Actual variable overhead costs...
1)
2)
3)
4)
5)
A favorable cost variance occurs when Oa. actual costs are the same as standard costs Ob. actual costs are more than standard costs Oc. standard costs are more than actual costs Od. standard costs are less than actual costs The Flapjack Corporation had 8,042 actual direct labor hours at an actual rate of $12.00 per hour. Original production had been budgeted for 1,100 units, but only 999 units were actually produced. Labor standards were 7.9...
The following data relate to direct materials costs for February: Materials cost per yard: standard, $1.98; actual, $2.04 Standard yards per unit: standard, 4.63 yards; actual, 4.91 yards Units of production: 9,100 Calculate the direct materials quantity variance. a.$5,045.04 favorable b.$5,045.04 unfavorable c.$5,197.92 unfavorable d.$5,197.92 favorable Flapjack Corporation had 7,768 actual direct labor hours at an actual rate of $12.40 per hour. Original production had been budgeted for 1,100 units, but only 971 units were actually produced. Labor standards were...