An activity was observed multiple (fifteen)
times, and the durations were recorded (in hours):
8, 12, 15, 11, 11, 24, 9, 11, 15, 11, 10, 11, 11, 10,
11
a.Based on this data, what is the most likely time for the activity
(in hours)?
b.Based on this data, what is the 'optimistic' time
for the activity (in hours)?
| Individual Durations (in hrs) | Probablity |
| 24 | 1/15 |
| 15 | 2/15 |
| 12 | 1/15 |
| 11 | 7/15 |
| 10 | 2/15 |
| 9 | 1/15 |
| 8 | 1/15 |
a)
| Most Likely Time: The duration which has the highest probability |
| Hence, 11 hrs |
b)
| Most optimistic Time: Shortest time in which, the activity can be completed |
| Hence, 8 hours |
An activity was observed multiple (fifteen) times, and the durations were recorded (in hours): 8, 12, 15, 11, 11, 24, 9, 11, 15, 11, 10, 11, 11, 10, 11 a.Based...
Question 1. Activities and activity durations of a Project is given below. (10 points) Find the probability of completing the Projcct in 50 weeks b. (10 points) Find the probability of completing the Project in 20 weeks. (10 points) Find the probability of completing the Project in 58 weeks. d. (10 points) Find the probability of completing the Project in 90 weeks. Most Pessimistic Time (weeks) 6 Most Optimistic Time (weeks) Most Probable Previous Activity 2 Activity Time (weeks) 4...
Given the following activity list and times in days: (15 points) Activity Optimistic Most Likely Pessimistic Time Time Time A 7 10 12 B 6 8 14 C 5 9 12 D 12 14 21 E 10 12 15 F 4 5 8 G 1 3 8 H 12 15 17 NOTE 1: ASSUME THE CRITTCAL PATH IS “B-E-H”. Calculate the schedule duration of the critical path in days. What is the probability of the project being completed...
An activity on a PERT network has an optimistic time of 10 hours, a most likely time of 13 hours, and a pessimistic time of 28 hours. Find its VARIANCE. 20.25 hour2 25 hour? 9 hour2 16 hour2 12.25 hour2
Alcohol Placebo 9 8 10 8 11 9 12 16 13 11 15 11 17 12 19 13 20 15 21 15 What is the mean, median, mode, and standard deviation for the alcohol group? what is the mean median, mode, and standard deviation for the placebo group? what is the most appropriate graph to use for the placebo group?
In a time study of a manufacturing operation, 15 actual times were recorded for the duration of producing a product for a skilled worker who has an experience of 10 years and for an unskilled worker who started to work one months ago: For the skilled worker, the average time observed to complete a product was 12 minutes. The performance rating applied to the observed worker was 1.10 and the allowance during a 10-hour shift was 30% or 180 minutes....
The estimated times and immediate predecessors for the activities in a project at Caesar Douglas’s screening company are given in the following table. Assume that the activity times are independent. All times are in weeks. Activity Predecessors Optimistic Time (a) Most Likely Time (m) Pessimistic Time (b) A -- 9 10 11 B -- 4 10 16 C A 9 10 11 D B 5 8 11 What is the critical path based on expected times? You may use any...
QUESTION 1 G E. H. C A Finish Start D. Complete the network activity diagram using the table below to answer questions 1-15. The expected activity completion times are provided in days. Each question is 1 point. Most Probable Activity Optimistic Pessimistic A 7 B 12 C 5 12 7 E 10 15 20 6 9 18 G 6 13 H 11 What is the early start (ES) time for activity F? 13 12 10 None of the above are...
Suppose that the following estimates of activity times (in weeks) were provided for the network shown below: Activity Optimistic Most Probable Pessimistic A 4 6 8 B 2.5 4.5 5.5 C 5 6.5 8 D 4 5.5 8 E 6.5 7.5 9 F 2 3.5 5 G 7 9 12 H 5 6 13 What is the probability that the project will be completed. If required, round your answers to four decimal places. Within 20 weeks? Within 22.5 weeks? Within...
Suppose that the following estimates of activity times (in weeks) were provided for the network shown below: Activity Optimistic Most Probable Pessimistic A 4 6 8 B 2.5 4.5 5.5 C 5 6.5 8 D 4 5.5 8 E 6.5 7.5 9 F 2 3.5 5 G 7 9 12 H 5 6 13 What is the probability that the project will be completed. If required, round your answers to four decimal places. Within 20 weeks? Within 22.5 weeks? Within...
Estimated activity times and precedences are given below: Activity Optimistic Most Likely Pessimistic Required Precedence A 6 7 14 B 8 10 12 C 2 3 4 D 6 7 8 A E 5 5.5 9 B, C F 5 7 9 B, C G 4 6 8 D, E H 2.7 3 3.5 F What is the probability that the project will be completed within: A. 21 Days B. 22 Days C. 25 Days