So set up the table with Duration and Crash Durations and calculate the Cost Slope
Cost Slope = (Crash Cost - Normal Cost)/(Normal Duration - Crash Duration)
So we get Cost Slope for Activity C = 425, Cost Slope for Activity G = 0

Set up the precedence network. For each activity set up a box like and get the precdence network

Early Start for Acitivity A = 0, Early finish for Activity A = 0 + duration = 0+7 =7
so that way we get EF for Activity I = 45. Assume this to be the LF for Activity I
ES for Activity I = maximum of EF of D,G,H

So now we know the ES, EF, LS, LF of all activities, so we have

so Critical path = A-B-C-F-G-I as shown below

Critical path = A-B-C-F-G-I
Time to complete project if you go in critical path = Sum of durations of A-B-C-F-G-I= 7+5+10+11+5+7 = 41
Normal project completion time = 41 days, Total direct normal cost = 44550
Indirect cost = 200/day. So multipy indirect cost by duration = 200*45 = 9000
So total cost = 44550+9000= 53550 - this is the total cost for normal completion time
For crashing the project, we need to find the crash limit and slope for the critical path
So we find out the crash limit and slope for activities in the critical path. These are

b) So Activity I has the least slope i.e 50
So in CYCLE 1, Crash Activity by 1 day, this wil cost 50. So the project can be shortened by 1 day i.e total duration of project reduces to 40
c) So for cycle 1 we have to re-calculate critical path, we have this as follows
So now new critical path is still the same
Critical path = A-B-C-F-G-I
Time to complete project if you go in critical path = Sum of durations of A-B-C-F-G-I= 7+5+10+11+5+6 = 40days
First iteration total cost = 53550
So add 50 to this and subtract 200/day (i.e indirect cost)
So total cost after cycle 1 = 53550+50-200 = 53550-150 = 53400
c) So now cyle 2, Total cost = 53400
So we find out the crash limit and slope for activities in the critical path. These are

c) so in cycle 2 - again Activity I can be shortened by 1 day. So project duration reduces from 40 days to 39 days
Previous iteration Total cost = 53400
So add 50 to this and subtract 200/day (i.e indirect cost)
So total cost after Cycle 2 = 53400+50-200 = 53250
So now our new critical path will stil be same
d) Cycle 3 we want to reduce project duration to 37 days. Sofirst reduce from 39 to 38 as follows

So now you cant crash activity I, so you have to crash the next activity with least slope i.e Activity F
so reduce activity F by 1 day total duration is now 38days
Previous iteration Total cost = 53400
So add 250 to this and subtract 200/day (i.e indirect cost)
So total cost after Cycle 3 = 53400+250-200 = 53450
Now we still need to reduce by one more week, so look at critical path now when Activity F has reduced by 1 day
Critical path is still same so we have
so we havef for Cycle 4 - now we reduce from 38 days to 37 days

so now you cannot crash activity F or Activity I, so you have to crash the next least slope, so crash Activity A by 1 day
so project duration is shortened from 38 days to 37 days.
Previous iteration Total cost = 53400
So add 300 to this and subtract 200/day (i.e indirect cost)
So total cost after Cycle 3 = 53400+300-200 = 53500
Engineering Management rash C Duration (day) Cost (SR) Cost Slope (Skany) 300 500 Normal Activity by...
Cost and schedule data for a small project are given below. Assume an indirect Cost of $ 500/day. Determine the minimum contract duration and project cost. ActivityPreceded by Cost (S) Duration (days) Crash Normal Crash Normal 3900 6500 7200 4900 2200 1700 1200 7200 10000 9450 4700 3600 5500 6350 4700 2050 19 7200 10 4500
Problem #3 (25 points) For the construction project whose network diagram is shown below, a time-cost optimization procedure is required to determine the shortest duration and its corresponding lowest cost. Activity ID ES Darwin EF LS UF 1. Fill in values for the normal cost and crashed cost in the table below. Activities A and B already have costs associated with them. For activities through I do not use the same costs for any activity 2. Calculate the slope and...
5.) Consider a project whose activities are listed in the table below. Activity A will have slack time as long as… Activity Immediate Predecessors A None B None C A D B E C, D F E G E a. Duration of A < Duration of B b. Duration of A + Duration of C > Duration of B + Duration of D c. Duration of A + Duration of C < Duration of B + Duration of D...
Question 1:
I)-What is the normal cost of this project?
II)-What is the cost of the project after 2 days shortening?
III)-What is the crashing cost per day for activity G?
Given the following data and network, find answer the questions 18-20 if you're asked to finish this project 2 days earlier than its normal duration. Indirect cost (overhead) is $200 per day. 9.12 E 3 1.8 12. 19 10,13 B 7 1,8 13.20 0,1 1,7 8.15 20,25 15.20 F...
Activity Predecessors | Duration(days) A B | Description Build foundation Build walls and ceilings Build the roof Electrical wiring Install windows Put on siding Painting B B Ε CF Ι a) Draw the project diagram, and find the critical path, total duration, and total float and free float for every activity. b) Suppose you are expected to finish the project within 20 days. You find you have to hire more workers in order to shorten the total duration. Please find...
what is the normal cost of this project?
what is the cost of the project after 2 days shortening?
what is the crashing cost per day for avtivity G?
Given the following data and network, find answer the questions 18-20 if you're asked to finish this project 2 days earlier than its normal duration. Indirect cost (overhead) is $200 per day. 9.12 E 1.8 اليا 12.19 10.13 B 7 H 7 1.8 13, 20 0.1 1.7 8.15 20,25 15, 20...
Question 6 - 8 Activity Depends on А B C D E F G A A А B C,D D, E, F Duration (Days) Normal Crash 5 4 7 5 8 5 11 8 6 4 4 3 7 5 Cost ($) Normal Crash 500 620 350 500 800 920 1000 1300 600 750 420 500 700 1000 6. Draw the node network for the above project using the following template. For each activity, show the computed value of early...
Normal Time Crash Time Normal with Activity (weeks) (weeks) Cost Crashing Immediate Predecessor(s) $1,400 A 3 2 $2,050 $2,800 B 2 1 $2,100 1 1 $350 $350 7 $1,400 $1,700 A 6 3 $900 $1,200 $5,000 $2,000 F 2 $4,000 $1,500 C 4 G 2 D, E weeks a) Based on the given information regarding the activities for the project, the project completion date b) To reduce the duration of the project to 10 weeks at the least cost, the...
A B Start E End C D Activity Normal time (days) Normal cost Crash time Cr 3 1 А B с D E 7 3 6 3 2 $300 $250 $400 $200 $300 4 2 1 ive the crash cost per day per activity. (5 points) Search 36_WA_Homework_EV_Problems_v1 (1) - Protected View - Saved References Mailings Review View Help PROBLEM 1 Use the network diagram below and the additional information provided to answer the corresponding questions. (10 points) B E...
Question 16 4 points Save Answe The following provides information about a project, including a list of activities and precedence relationships, activity durations (normal and "crash" times), direct activity costs (normal and "crash"), indirect costs for the project, as well as calculated crash costs/day and the maximum amount that each activity can be shortened (crashed) by. There are no penalty costs for this project. Total project cost (using normal times), a network diagram, and the four paths and durations have...