7- A simple CPM network has three activities, A, B, and C. A is an immediate predecessor of B and of C. B is an immediate predecessor of C. The activity durations are A=4, B=3, C=8.
Define the critical path (CPM)
Network diagram refers to the sequence of how the activities will be performed and arrange the activities in sequence and how they are dependent on one another.
CPM refers to critical path method where shortest path is taken to plan the project. The steps in CPM schedule include: -
7- A simple CPM network has three activities, A, B, and C. A is an immediate...
A simple CPM network has three activities, A, B, and C. A is an immediate predecessor of B and of C. B is an immediate predecessor of C. The activity durations are A=4, B=3, C=5. The network has no critical path. The critical path cannot be determined without knowing PERT expected activity times. The critical path is A-C, duration 10.5. The critical path is A-B-C, duration 9. The critical path is A-B-C, duration 12.
Question 14 Not yet answered A simple CPM network has five activities, A, B, C, D, and E. A is an immediate predecessor of Cand of D.B is also an immediate predecessor of Cand of D. C and D are both immediate predecessors of E. Which of the following statements is true? Points out of 1.00 P Flag question Select one: a. There are four paths in this network b. There are three paths in this network. c. There are...
From this schedule of activities: Activity Immediate Predecessor Activity Time A --- 4 B A 2 C B 3 D B 5 E A 1 F C, D 3 G E, F 2 a. Draw the PERT/CPM network b. Complete the forward and backward pass c. Determine the critical path d. Determine the total duration of the project.
The following activities are part of a project to be scheduled using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) A — 3 B A 9 C A 5 D C 2 E B D 7 F D 6 G E F 4 b. What is the critical path? A-B-D-F-G A-B-E-G A-C-D-F-G A-C-D-E-G c. How many weeks will it take to complete the project? Number of weeks d. How much slack does activity B have? Slack of activity B week(s)
Problem 5-7 (Algo) The following activities are part of a project to be scheduled using CPM ACTIVITY IMMEDIATE PREDECESSOR TIME (HEEKS) A 9 B A. 3 C A. 7 D C E BD 4 F 3 E F G a. What is the critical path? A-C-D-E-G O A-B-D-F-G A-B-E-G A-C-D-F-G b. How many weeks will it take to complete the project? Number of weeks <Prey 3 of 8 Next>
Given the following activities and precedents, draw a PERT/CPM diagram. ACTIVITY IMMEDIATE PREDECESSOR DURATION (DAYS) A - 10 B - 12 C A 4 D A, B 8 E A, B 9 F C 10 G D, F 12 H E, G 15 Answer the following: What is the critical path? How long will it take to complete this project? Can activity E be delayed without delaying the completion of the project? If so, how many days?
Problem 5-7 The following activities are part of a project to be scheduled using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) A — 7 B A 6 C A 2 D C 4 E B D 3 F D 4 G E F 6 b. What is the critical path? A-B-D-F-G A-C-D-E-G A-C-D-F-G A-B-E-G c. How many weeks will it take to complete the project? Number of weeks d. How much slack does activity B have? Slack of activity B week(s)
Schedule the following activities using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) A — 1 B A 4 C A 3 D B 2 E C, D 5 F D 2 G F 2 H E, G 3 b. What is the critical path? A-B-D-F-G-H A-C-D-F-G A-C-E-H A-B-D-E-H c. How many weeks will it take to complete the project? Number of weeks d. Which activities have slack, and how much? D, 2 weeks; G, 1 week; and H, 1 week....
Problem 5-7 The following activities are part of a project to be scheduled using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) А 7 B 6 2 3 B.D D b. What is the critical path? Оооо A-C-D-E-G A-B-D-F-G A-B-E-G O A-C-D-F-G c. How many weeks will it take to complete the project? Number of weeks d. How much slack does activity B have? Slack of activity B week(s)
Paragraph HOMEWORK Number 8 a) Construct a CPM network for the project shown in a tabular form b) Calculate ES(early start) and LS (Late Start) of each activity c) Find critical path and its duration, make it bold or red color. Activity Immediate Predecessor Activity Duration(weeks}} А А A B.C 12 D CB н EEG