It is important to plan for in performing the project to assure that the work is done according to specifications and applicable standards and that deliverables meet acceptance criteria
| A | time |
| B | quality |
| C | resources |
| D | scope creep |
Answer : D. Scope creep
Note : To plan for scope creep in the project is necessary to avoid the potential risks in projects and to carry out the project as per specifications, standards and the acceptance criteria.
It is important to plan for in performing the project to assure that the work is done...
The project team you are working with is doing the work of obtaining formal stakeholders’ acceptance of the completed project and associated deliverables. Each deliverable is reviewed to check that it has been completed satisfactorily. What is this process called? A. Validate Scope B. Define Scope C. Control Scope D. Plan Scope Management
The evaluation team should be made up of: a. representatives from potential contractors. b. several individuals from different depar ackgrounds and from different departments in the organization with various viewpoints and different c. Several of the stakeholders of the project from the community. d. one person from the company. The project charter helps the team to: a. set the evaluation criteria to select the project. b. decide which contractor to select to work on a project. c. develop a detailed...
QUESTION 4 Match the process with the appropriate definition. The process of identifying quality requirements and /or standards for the project and its deliverables, and documenting how the project will demonstrate compliance with quality requirements and/or standards. The process of translating the quality management plan into executable quality activities that incorporate the organization's quality policies into the project. The process of developing options, selecting strategies, and agreeing on actions to address overall project risk exposure, as well...
Please choose the incorrect answer
is not true
EMBA 660 FBSU Project Management Q#4) Multiple Choice: (Which of the following is not true) B) The Project Scope defines: A) What is included and what is noi included in the project? C) The product acceptance criteria. Who will be responsible for each deliverable? The deliverables D) The point where the incremental revenue from an improvement equals the cost to implement it is referred to as: A) Kaizen B) Marginal Analysis C)...
Which of the following expectation should be included in an evaluation of the project team? a.) Achieve quality standards set for an activity. b.) Meet expected participation levels in project meetings. c.) Complete assigned deliverable according to specifications. d.) Tested deliverable after implementation to check for any issues
1 According to the project plan, a contractor is scheduled to deliver some software components today afternoon. A regular payment is due to be made to this contractor tomorrow. You and your project team received a note this morning informing you that the software delivery will be delayed by 2 weeks. What should you do right now? a You should delay the payment for two weeks b You must immediately find a different contractor c You should conduct a meeting...
Lab3- Project Budgeting (use Excel) NewCo Company Statement of Work (SOW) for NOMO Inc.Online Training Module Introduction: The NewCo Company is contracting NOMO Inc. to design and develop a 1-hour training module for new employee orientation. Purpose: This Statement of Work (SOW) defines the effort and deliverables required from NOMO Inc. (hereafter known as Subcontractor) by the NewCo Company (hereafter known as Buyer) for the Online Training Module. Scope: The Subcontractor will design and develop a 1-hour online training module...
You are the project manager for a power plant project. You have completed project initiation activities and you are now creating a document that describes processes to document the scope, decompose deliverables into work packages, verify that all work is complete and manage changes to the baseline. What process plan would you choose to perform? A. Develop project management plan B. Develop project management life cycle C. Develop WBS and define scope D. Develop project charter
!!!Only Project 2 need to be answered!!! Project Report 1 Once the business case has been approved, you need to make a project plan showing each task. Assume you are a project manager to lead your team to acquire an additional delivery van for the company. Please find the details below. The current month is January. Activity (What is to be done?) Objective (Why will we do it?) Resources (Where will it be done?) Procedures (How will it be done?)...
Which of the following is not an activity related to the Direct and Manage Project Work process? A. Inspect the project deliverables for completeness. B. Provide, train, and manage the team members assigned to the project. C. Create project deliverables to meet the planned project work. D. Perform activities to accomplish project objectives.