Question

Given the project network provided in the attachment, what task or tasks would you crash to...

Given the project network provided in the attachment, what task or tasks would you crash to reduce the project by one day? What is the cost of the project after you crash the cost by one day? What is the new duration? Please include your excel file with all calculations.

Normal Crash Crash Cost Per Day
Task Pred Duration Cost Duration Cost
a - 5 $        500 5 $        500
b a 10 $    2,000 8 $    2,400
c a 5 $    1,500 3 $    4,500
d b 15 $    1,500 14 $    2,000
e c 30 $    4,500 25 $ 15,000
f d, e 5 $        500 5 $        500

***Please show Excel calculation along with screenshot of formula used.

0 0
Add a comment Improve this question Transcribed image text
Answer #1
activity required time cost time available for crashing= normal duration-crashed duration cost of crashing per period= (crashing cost-normal cost)/periods available for crashing
normal duration crashed duration normal cost crashing cost
A 5 5                     500                   500 0 -
B 10 8                 2,000               2,400 10-8= 2 (2400-2000)/2= $200
C 5 3                 1,500               4,500 2 $1,500
D 15 14                 1,500               2,000 1 $500
E 30 25                 4,500             15,000 5 $2,100
F 5 5                     500                   500 0 -

Steps for crashing

Steps for crashing a project
1 select the critical path and find the process with the least cost of crashing per week
2 If there are multiple critical paths, look for processes that are common, common processes may have low effective cost as common process crashes more than 1 path at once
3 you can only crash an activity depending on the time available for crashing. If an activity is only crashed that much time, choose another activity
4 add the cost of crashing later

Crashing by 1 day

crash period 1
PATH normal duration crash C by 1 period
ABDF 35 35
ACEF 45 44
Cost $10,500 $1,500

what task or tasks would you crash to reduce the project by one day:  Crash C

What is the cost of the project after you crash the cost by one day:  10500+1500= $ 12000

What is the new duration: 44 days

Please ask, if you have any doubts through the comment section. Do rate the answer

Add a comment
Know the answer?
Add Answer to:
Given the project network provided in the attachment, what task or tasks would you crash to...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • For the project outlined on the following table, (a) draw a network diagram (arrow or PDM,...

    For the project outlined on the following table, (a) draw a network diagram (arrow or PDM, as you prefer), and (b) identify the critical path and duration. (c) Identify the task(s) you would crash and the incremental cost to reduce project duration by (i) one week; (ii) a second week; (iii) a third week. Duration (Weeks) Cost (Dollars) Task Follows Task(s) Normal Crash Normal Crash (Start) (Start) A, B B C D uun $500 400 600 $600 450 750 550...

  • Consider a project having the following six activities:                                  

    Consider a project having the following six activities:                                                      Immediate                                                  Max        Crash cost             Activity                           Predecessors           Time (weeks)             Crash*    per week                   A                                none                                    6                          6                N/A                   B                                none                                    5                          2               $500                   C                                A                                       3                          2             $1000                   D                                A, B                                    4                          2             $2000                   E                                 C, D                                    5                          2             $1250                   F                                D                                       6                          2             $1000                                                                                                 *Shortest possible time for the task 1. Draw the project network and list...

  • Consider a project having the following six activities:                                  

    Consider a project having the following six activities:                                                      Immediate                                                  Max            Crash cost             Activity                           Predecessors          Time (weeks)             Crash*    per week                   A                                none                                    7                          7         N/A                   B                                none                                    3                          2        $500                   C                                A                                       5                          3      $1000                   D                                A, B                                    6                          4      $2000                   E                                 C, D                                    4                          3      $1250                   F                                D                                       3                          2      $1000                                                                                                 *Shortest possible time for the task 1. Draw the project network and list...

  • Question 2. (30%) The following table provides the information necessary to construct project network and calculate...

    Question 2. (30%) The following table provides the information necessary to construct project network and calculate a total project cost. In case of activity crash, the information includes crash cost for each activity. Activity Immediate predecessor(s) Activity time (weeks) Normal cost (x1000$) Additional cost for crashing one week (x1000$) Normal After maximum crash A - 16 12 2,000 300 B - 14 9 1,000 160 C A 8 6 500 100 D A 5 4 600 700 E B 4...

  • 62. Task ID Predecessors Normal Time Maximum Crash Time Normal Cost Crash Cost (Slope) 1 -...

    62. Task ID Predecessors Normal Time Maximum Crash Time Normal Cost Crash Cost (Slope) 1 - 5 1 50 20 2 - 3 2 60 60 3 1 4 0 70 0 4 1 2 1 50 10 5 2 5 3 100 60 6 3 2 1 90 100 7 4 5 1 50 30 8 5 2 0 60 40 9 6,7,8 3 1 200 200 Consider the project above. If the indirect costs of the project are:...

  • Question 15 The following information about a project was provided: • Indirect costs per day: $233...

    Question 15 The following information about a project was provided: • Indirect costs per day: $233 • Late completion penalty of $84 per day beyond day 19 • The current Critical Path duration is 26 Acitvity А B с D E F G Immed Normal Normal Pred(s) Time (days) Cost ($) 3 7,000 1 3,000 A 4 12,000 B 2 12,000 1 8,000 DE 4 5,000 E 2 9,000 Crash Time Crash Cost (days) 2 10,000 1 3,000 2 40,000...

  • The following information about a project was provided: • Indirect costs per day: $341 • Late...

    The following information about a project was provided: • Indirect costs per day: $341 • Late completion penalty of $145 per day beyond day 19 • The current Critical Path duration is 24 Acitvity Immed Pred(s) Normal Time Normal (days) Cost ($) Crash Time Crash Cost (days) ($) 3 1 A B с D E F G 4 2 A B C DE E 7,000 3,000 12,000 12.000 8.000 5,000 9,000 2 1 2 1 1 2 10,000 3,000 40,000...

  • Consider the project network information in Table 1 of Case Study A on Page 3 below....

    Consider the project network information in Table 1 of Case Study A on Page 3 below. Assuming the project starts at time zero and all activity connections are finish-to-start, draw an Activity on the Node (AON) network diagram of the project, determine the expected project completion time, state the critical activities and critical path(s). Crash the project by 1 week and state the total crash cost. (b) (18 nar Case Study A Table 1 below contains activities associated with a...

  • Consider the project network information in Table 1 of Case Study A on Page 3 below....

    Consider the project network information in Table 1 of Case Study A on Page 3 below. Assuming the project starts at time zero and all activity connections are finish-to-start, draw an Activity on the Node (AON) network diagram of the project, determine the expected project completion time, state the critical activities and critical path(s). Crash the project by 1 week and state the total crash cost. (b) (18 narl Case Study A Table 1 below contains activities associated with a...

  • what is the normal cost of this project? what is the cost of the project after...

    what is the normal cost of this project? what is the cost of the project after 2 days shortening? what is the crashing cost per day for avtivity G? Given the following data and network, find answer the questions 18-20 if you're asked to finish this project 2 days earlier than its normal duration. Indirect cost (overhead) is $200 per day. 9.12 E 1.8 اليا 12.19 10.13 B 7 H 7 1.8 13, 20 0.1 1.7 8.15 20,25 15, 20...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT