QUESTION TWO:
Comprehensive Variance Analysis in a Hospital
Marc Goudreau, administrator of Clearwater Hospital, was puzzled by the prior month's reports. "Every month, it's anyone's guess whether the lab will show a profit or a loss. Perhaps the only answer is to increase our lab fees again."
"We can't," replied Rhoda Groves, the controller. "There are still a lot of complaints about the last increase, particularly from the insurance companies and government health units. They're now paying only about 80% of what we bill. I'm beginning to think the problem is on the cost side."
To determine if the Clearwater lab costs are in line with those of other hospital labs, Goudreau has asked you to evaluate the costs for the past month. Groves has provided you with the following information:
Clearwater Hospital has never used standard costs. By searching industry literature, however, you have determined the following nationwide averages for hospital labs:
Plates: Three plates are required per lab test. These plates cost $2.50 each and are disposed of after the test is completed.
Labour: Each smear should require 0.3 hours to complete, and each blood test should require 0.6 hours to complete. The average cost of this lab time is $12 per hour.
Overhead: Overhead cost is based on direct labour-hours. The average rate of variable overhead is $6 per hour. The average rate of fixed overhead is $8 per hour. These rates are based on a denominator activity level of 1,250 hours per month.
Required:
| Please hit LIKE button if this helped. For any further explanation, please put your query in comment, will get back to you. | ||||
| Working-1 | ||||
| Total Plates Needed (3 plates per test) | ||||
| Blood Test | 900 | A | ||
| Smear Test | 2,700 | B | ||
| Total Test | 3,600 | C=A+B | ||
| Plate neeed per test | 3 | D | ||
| Total Plates needed | 10,800 | E=C*D | ||
| 1. Material Price & Quantity Variance | ||||
| Material Price Variance | (Actual Rate-Standard Rate)*Actual Quantity Purchased | |||
| (2.4-2.5)*16,000 | ||||
| 1600 | Favorable | |||
| Actual Rate | 2.5 | given | ||
| Standard Rate | 2.4 | 38400/16000 | ||
| Actual Quantity Pur | 16000 | given | ||
| Material Quantity Variance | (Standard Q-Actual Q USED)*Standard Rate | |||
| (10800-14000)*2.4 | ||||
| 7680 | Unfavorable | |||
| Standard Rate | 2.4 | 38400/16000 | ||
| Actual Quantity USED | 14000 | 16,000-2,000 | ||
| Standard Quantity | 10800 | Working-1 | ||
| 2a.Labor efficiency & Labor Rate | ||||
| Standard Hour Required | (Blood Test*Hour)+(Smear Test*Hour) | |||
| (900*0.6)+(2700*0.3) | ||||
| 1350 | ||||
| Standard Rate | 12 | |||
| Actual Rate | 1800 Hour at cost of 18450 | |||
| 18450/1800 | ||||
| 10.25 | ||||
| Labor Rate Varaince | (Actual Rate-Standard Rate)*Actual Hours Purchased | |||
| (10.25-12)*1800 | ||||
| 3150 | Favorable | |||
| Labor efficiency Variance | (Standard Hr-Actual Hrs)*Standard Rate | |||
| (1350-1800)*12 | ||||
| 5400 | Unfavorable | |||
| 2b. Existing policy is not recommended as work of senior technician can not be performed with same quality by Assistant and that can be seen in efficiency variance above which is unfavorable | ||||
| 3a.Variable Overhread Rate and efficiency | ||||
| Actual Variable Ovh Rate | 11700 Last Month overhead, 1800 hours | |||
| 11700/1800 | ||||
| 6.5 | ||||
| Standard Variable Ovh Rate | 6 | |||
| Ovh Rate Varaince | (Standard Rate-Actual Rate)*Actual Hours Purchased | |||
| (6-6.5)*1800 | ||||
| 900 | Unfavorable | |||
| Ovh efficiency Variance | (Standard Hr-Actual Hrs)*Standard Rate | |||
| (1350-1800)*6 | ||||
| 2700 | Unfavorable | |||
| Yes, There is direct relationship between two. Since inefficient labor will make both Variable overhead efficiency unfavorable | ||||
| 4. Fixed overhead: | ||||
| Actual Fixed Overhead | $ 10,400 | a | ||
| Budgeted Fixed Overhead | 1,250*$8 | $ 10,000 | b | |
| Applied Fixed overhead | 1,350*$8 | $ 10,800 | c | |
| Fixed overhead volume variance | $ 800 | Unfavorable | b-c | |
| Fixed overhead budget variance | $ 400 | Unfavorable | a-b | |
QUESTION TWO: Comprehensive Variance Analysis in a Hospital Marc Goudreau, administrator of Clearwater Hospital, was puzzled...
Marc Goudreau, administrator of Clearwater Hospital, was puzzled by the prior month’s reports. “Every month, it’s anyone’s guess whether the lab will show a profit or a loss. Perhaps the only answer is to increase our lab fees again.” “We can’t,” replied Rhoda Groves, the controller. “There are still a lot of complaints about the last increase, particularly from the insurance companies and government health units. They’re now paying only about 82% of what we bill. I’m beginning to think...
Problem 9-22 Variance Analysis in a Hospital John Fleming, the chief administrator for Valley View Hospital, is concerned about the costs for tests in the hospital’s lab. Charges for lab tests are consistently higher at Valley View than at other hospitals and have resulted in many complaints. Also, because of strict regulations on amounts reimbursed for lab tests, payments received from insurance companies and governmental units have not been high enough to cover lab costs. Mr. Fleming has asked you...
Problem 9-22 Variance Analysis in a Hospital [LO9-4, LO9-5, LO9-6] John Fleming, chief administrator for Valley View Hospital, is concerned about the costs for tests in the hospital’s lab. Charges for lab tests are consistently higher at Valley View than at other hospitals and have resulted in many complaints. Also, because of strict regulations on amounts reimbursed for lab tests, payments received from insurance companies and governmental units have not been high enough to cover lab costs. Mr. Fleming has...
Problem 9-22 Variance Analysis in a Hospital [LO9-4, LO9-5, LO9-6] John Fleming, chief administrator for Valley View Hospital, is concerned about the costs for tests in the hospital’s lab. Charges for lab tests are consistently higher at Valley View than at other hospitals and have resulted in many complaints. Also, because of strict regulations on amounts reimbursed for lab tests, payments received from insurance companies and governmental units have not been high enough to cover lab costs. Mr. Fleming has...
John Fleming, chief administrator for Valley View Hospital, is concerned about the costs for tests in the hospital's lab. Charges for lab tests are consistently higher at Valley View than at other hospitals and have resulted in many complaints. Also, because of strict regulations on amounts reimbursed for lab tests, payments received from Insurance companies and governmental units have not been high enough to cover lab costs Mr. Fleming has asked you to evaluate costs in the hospital's lab for...
John Fleming, chief administrator for Valley View Hospital, is concerned about the costs for tests in the hospital's lab. Charges for lab tests are consistently higher at Valley View than at other hospitals and have resulted in many complaints. Also, because of strict regulations on amounts reimbursed for lab tests, payments received from insurance companies and governmental units have not been high enough to cover lab costs. Mr. Fleming has asked you to evaluate costs in the hospital's lab for...
John Fleming, chief administrator for Valley View Hospital, is concerned about the costs for tests in the hospital’s lab. Charges for lab tests are consistently higher at Valley View than at other hospitals and have resulted in many complaints. Also, because of strict regulations on amounts reimbursed for lab tests, payments received from insurance companies and governmental units have not been high enough to cover lab costs. Mr. Fleming has asked you to evaluate costs in the hospital’s lab for...
John Fleming, chief administrator for Valley View Hospital, is concerned about the costs for tests in the hospital’s lab. Charges for lab tests are consistently higher at Valley View than at other hospitals and have resulted in many complaints. Also, because of strict regulations on amounts reimbursed for lab tests, payments received from insurance companies and governmental units have not been high enough to cover lab costs. Mr. Fleming has asked you to evaluate costs in the hospital’s lab for...
John Fleming, chief administrator for Valley View Hospital, is concerned about the costs for tests in the hospital's lab. Charges for lab tests are consistently higher at Valley View than at other hospitals and have resulted in many complaints. Also, because of strict regulations on amounts reimbursed for lab tests, payments received from insurance companies and governmental units have not been high enough to cover lab costs. Mr. Fleming has asked you to evaluate costs in the hospital's lab for...
John Fleming, chief administrator for Valley View Hospital, is concerned about the costs for tests in the hospital's lab. Charges for lab tests are consistently higher at Valley View than at other hospitals and have resulted in many complaints. Also, because of strict regulations on amounts reimbursed for lab tests, payments received from insurance companies and governmental units have not been high enough to cover lab costs. Mr. Fleming has asked you to evaluate costs in the hospital's lab for...