Requirements 1. Complete the performance evaluation report for this subunit. 2. Based on the data presented, what type of responsibility center is the subunit? 3. Which items should be investigated if part of management's decision criteria is to investigate all variances exceeding $ 2 comma 800 or 12 % question mark 4. Should only unfavorable variances be investigated? Explain. Requirement 1. Complete the performance evaluation report for this subunit. (Enter the variances as positive numbers. Round the variance percentages to the nearest hundredth percent, X.XX%. Label each variance as favorable (F) or unfavorable (U). If the variance is 0, make sure to enter in a "0". A variance of zero is considered favorable.) Variance Product Actual Budgeted (U or F) Direct materials $12,930 $12,000 Direct labor 13,265 14,000 Indirect labor 23,380 20,000 Utilities 16,455 15,000 Depreciation 30,250 30,250 Repairs and maintenance 4,205 5,000 Total $100,485 $96,250
| Performance Evaluation Report | |||||
| Accel- SubUnit | Actual | Flexible Budget | Flexible Budget Variance (F or U) | % Variance | F or UF |
| Direct materials | 12,930.00 | 12,000.00 | -930.00 | 7.75% | UF |
| Direct Labor | 13,265.00 | 14,000.00 | 735.00 | 5.25% | F |
| Indirect Labour | 23,380.00 | 20,000.00 | -3,380.00 | 16.90% | UF |
| Utilities | 16,455.00 | 15,000.00 | -1,455.00 | 9.70% | UF |
| Depreciation | 30,250.00 | 30,250.00 | - | 0.00% | Nil |
| Repair & Maintainance | 4,205.00 | 5,000.00 | 795.00 | 15.90% | F |
| Total | 1,00,485.00 | 96,250.00 | |||
Part-2: Subunit is a cost centre.
Part-3: Indirect Labour and Repair Maintainance Should be reviewed.
Part-4: No Favorable variances should also be investigated since this investigation helps for setting up the most right standards. some time standards setup are not accurate results into a positive variances.
Requirements 1. Complete the performance evaluation report for this subunit. 2. Based on the data presented,...
all information is shown
One subunit of Winter Sports Manufacturing Company had the following financial results last month HE (Click the icon to view the financial results) Requirements 1. Complete the performance evaluation report for this subunit. 2. Based on the data presented, what type of responsibility center is the subunt? 1. Which items should be investigated if part of management's decision criteria is to investigate al variancesceng $3,200 of 10%? 4. Should only unfavorable variances be investigated? Explain Requirement...
One subunit of All Season Sports Manufacturing Company had the following financial results last month: Click the icon to view the financial results.) Requirements 1. Complete the performance evaluation report for this subunit. 2. Based on the data presented, what type of responsibility center is the subunit? 3. Which items should be investigated if part of management's decision criteria is to investigate all variances exceeding $3,200 or 11.5%? 4. Should only unfavorable variances be investigated? Explain. Requirement 1. Complete the...
Requirement 1. Complete the performance evaluation report for this subunit Enter the variance percent as a percentage of the budgeted amount rounded to two places. (Er enter a 0 in the variance column and then leave the For U box blank. Enter the variance percent as a percentage rounded to two decimal places, X00%) % Variance (For U) Accel-Subunit X Data Table Direct Materials Flexible Budget Variance (F or U) 2100U 700 F 3100 U Direct Labor Actual . Flexible...
.
One subunit of Extreme Sports Company had the following financial results last month: (Click the icon to view the financial results.) Read the requirements Requirement 1. Complete the performance evaluation report for this subunit. Enter the variance percent as a percentage of the budgeted amount rounded to two places. (Enter a variance for each account as a positive number, and select whether the variance is favorable [F] or unfavorable [U]. For any zero variances, enter a 0 in the...
One subunit of Pike Sports Company had the following financial results last month: Pike-Subunit X Actual Results Flexible Budget Flexible Budget Variance (F or U) % Variance (F or U) Direct Materials $28,800 $27,000 Direct Labor 13,400 14,200 Indirect Labor 26,100 23,000 Utilities 12,200 11,300 Depreciation 29,000 29,000 Repairs and Maintenance 4,800 5,700 Total $114,300 $110,200 Requirements: 1. Complete the performance evaluation report for this subunit. Enter the variance percent as a percentage of the budgeted amount rounded to two...
One subunit of Winter Sports Manufacturing Company had the following financial results last month: : (Click the icon to view the financial results.) Requirements 1. Complete the performance evaluation report for this subunit. 2. Based on the data presented, what type of responsibility center is the subunit? 3. Which items should be investigated if part of management's decision criteria is to investigate all variances exceeding $3,100 or 13%? 4. Should only unfavorable variances be investigated? Explain. X Reqi varia Data...
Requirement 1. Complete the performance evaluation report for the subunit. (Enter a variance for each account, and select whether the variance is unfav numbers. Enter the variance percentages rounded to three decimal places, X.XXX%.)
Please open enlarge and view. The blue box data table is
included.
Options for requirement 3 are Depreciation, direct labor, direct
materials, indirect labor, repairs and maintenance, utilities
Options for req 4 Yes or no And (never need to be
investigated because they increase net income, should be
investigated to make sure the variance does not happen again,
should be investigated to make sure they are not hurting the
business in the long run.
Х Data Table Flexible Budget Variance...
One subunit of Field Sports Company had the following financial results last month: (Click the icon to view the financial results.) Read the requirements Requirement 1. Complete the performance evaluation report for the subunit. (Enter a variance for each account as a positive number and select whether the variance is favorable or unfavorable. Enter the variance percent as a percentage rounded to two decimal places, X.XX%) Actual Flexible Flexible Budget % Variance Subunit x Results Budget Variance (For U) (For...
Drop downs are F or U for the clear right boxes
Managerial Accounting Acct1212-W07-28217-SU-2019 Jacque Homework: Ch 24 Probl 1 of 1 (1 completely Score: 1.75 of 7 pts P24-20A (book/static) One subunit of Racer Sports Company had the following financial results last month: (Click the icon to view the financial results) Read the requirements Requirement 1. Complete the performance evaluation report for the subunit. (Enter a variance for each account as a positive number and select whether the variance...