Children's scissors are made from four items: two identical blades, a 6-32 screw, and a nut. The blades are manufactured internally with a two-week lead time, and the screw and the nut are purchased from a hardware supplier each with a one-week lead time. The assembly process for one gross (which is equal to 12 dozen) of scissors takes one week. There is an order for one gross of scissors in week 7 and another for three in week 9. Moreover, there are 360 blades, 600 screws, and 100 nuts currently available in inventory.
(1) Construct a product structure tree for the scissors.
(2) Set up an MRP table for each of the four items comprising the
scissors. It is assumed that the lot-for-lot rule is used to
determine the planned order releases.
Answer 1:-

Answer 2:-
Level 0 – Scissors: lead time (LT) = 1 week
|
1 |
2 |
3 |
4 |
5 |
6 |
7 |
8 |
9 |
|
|
Gross requirements |
144 |
432 |
|||||||
|
Scheduled receipts |
|||||||||
|
Projected on-hand |
0 |
0 |
0 |
0 |
0 |
0 |
-144 |
-432 |
|
|
Net requirements |
144 |
432 |
|||||||
|
Planned order receipts |
144 |
432 |
|||||||
|
planned order release |
144 |
432 |
Level 1 – Blade: lead time (LT) = 2 weeks
|
1 |
2 |
3 |
4 |
5 |
6 |
7 |
8 |
9 |
|
|
Gross requirements |
288 |
864 |
|||||||
|
Scheduled receipts |
|||||||||
|
Projected on-hand |
360 |
360 |
360 |
360 |
360 |
72 |
72 |
-792 |
|
|
Net requirements |
792 |
||||||||
|
Planned order receipts |
792 |
||||||||
|
planned order release |
792 |
Level 1 – Screw: lead time (LT) = 1 week
|
1 |
2 |
3 |
4 |
5 |
6 |
7 |
8 |
9 |
|
|
Gross requirements |
144 |
432 |
|||||||
|
Scheduled receipts |
|||||||||
|
Projected on-hand |
600 |
600 |
600 |
600 |
600 |
456 |
456 |
456 |
24 |
|
Net requirements |
|||||||||
|
Planned order receipts |
|||||||||
|
planned order release |
Level 1 – Nut: lead time (LT) = 1 week
|
1 |
2 |
3 |
4 |
5 |
6 |
7 |
8 |
9 |
|
|
Gross requirements |
144 |
432 |
|||||||
|
Scheduled receipts |
|||||||||
|
Projected on-hand |
100 |
100 |
100 |
100 |
100 |
-44 |
-432 |
||
|
Net requirements |
44 |
432 |
|||||||
|
Planned order receipts |
44 |
432 |
|||||||
|
Planned order release |
44 |
432 |
Children's scissors are made from four items: two identical blades, a 6-32 screw, and a nut....
One unit of A is made of one unit of B and one unit of C. B is
made of four units of C and one unit each of E and F. C is made of
two units of D and one unit of E. E is made of three units of F.
Item C has a lead time of one week; Items A, B, E, and F have
two-week lead times; and Item D has a lead time of...
One unit of A is made of one unit of B and one unit of C. B is made of four units of C and one unit each of E and F. C is made of two units of D and one unit of E. E is made of three units of F. Item C has a lead time of one week; Items A, B, E, and F have two-week lead times; and Item D has a lead time of...
One unit of A is made of two units of B and one unit of C. B is made of three units of D and one unit of F. C is composed of three units of B, one unit of D, and four units of E. D is made of one unit of E. Item C has a lead time of one week; Items A, B, E, and F have two-week lead times; and Item D has a lead time...
One unit of A is made of three units of B, one unit of C, and two units of D. B is composed of two units of E and one unit of D. C is made of one unit of B and two units of E. E is made of one unit of F. Items B, C, E, and F have one-week lead times; A and D have lead times of two weeks. Assume that lot-for-lot (L4L) lot sizing is...
One unit of A is made of three units of B, one unit of C, and two units of D. B is composed of two units of E and one unit of D. C is made of one unit of B and two units of E. E is made of one unit of F. Items B, C, E, and F have one-week lead times; A and D have lead times of two weeks. Assume that lot-for-lot (L4L) lot sizing is...
Assume that Product Z is made of two units of A and three units of B. A is made of four units of C and four of D. D is made of two units of E Lead times for purchase or fabrication of each unit to final assembly are: Z takes two weeks; A, B, C, and D take one week each; and E takes three weeks. Fifty one units of Product Z are required in Period 10. (Assume that...
One unit of A is made of two units of B and one unit of C. B is made of three units of D and one unit of F. C is composed of three units of B, one unit of D, and four units of E. D is made of one unit of E. Item C has a lead time of one week; Items A, B, E, and F have two-week lead times; and Item D has a lead time...
Assume that Product Z is made of two units of A and four units of B. A is made of three units of C and four of D. D is made of two units of E. Lead times for purchase or fabrication of each unit to final assembly are: Z takes two weeks; A, B, C, and D take one week each; and E takes three weeks. Fifty units of Product Z are required in Period 10. (Assume that there...
Assume that Product Z is made of two units of A and four units of B. A is made of three units of C and three of D. D is made of three units of E Lead times for purchase or fabrication of each unit to final assembly are: Z takes two weeks; A, B, C, and D take one week each; and E takes three weeks. Fifty seven units of Product Z are required in Period 10. (Assume that...
MRP /ERP IN M 1) Each E subassembly is made up of two (2) G parts, four (5) H part, and One J part Draw the product structure tree diagram. the information provided below, complete the following MRP Record Transaction Processing for Part E and Part G only if the following information is provided (Do not order more quantity of any resources that is needed to maintain the production) sing the product structure free diagram and Subassembly Part Part Part...