Question 2 If cumulative PV 100, cumulative EV 98 and cumulative AC 104, the project is likely to be: Item EV 10,000 7,000 8,000 5,000 PV 10,000 9,000 8,000 7,000 AC 1,000 8,000 8,000 7,000 Which ite... related homework questions