#1 #2 #3 #4 Time Estimates (in weeks) for SOM's Bus Project is given in the...

#1
Time Estimates (in weeks) for SOMs Bus Project is given in the following table. Activity Optimistic time Most likely time Pe
#2
A projects critical path is CDFGI. The expected time and the standard deviation of each activity are as follows. Activity AB
#3
A project being analyzed by PERT has 60 activities, 13 of which are on the critical path. If the estimated time along the cri
#4
A project being analyzed by PERT has 60 activities, 13 of which are on the critical path. If the estimated time along the cri
Time Estimates (in weeks) for SOM's Bus Project is given in the following table. Activity Optimistic time Most likely time Pessimistic time A 2 4 6 B 3 5 8 Ic с 4 6 8 D 3 5 10 Please help the project management team to find the standard deviation of Activity D. keep two decimals if not exact, either round up or down is ok. For example, for 0.1346, (0.13 or 13) and (0.14 or.14) are correct
A project's critical path is CDFGI. The expected time and the standard deviation of each activity are as follows. Activity AB c с D E F G HL Expected 2. 5 18 16 4 15 10 1 Time Standard (10 4 10 14 10 11 11 5 16 Deviation 5 19 5 What is the project standard deviation? keep two decimals if not exact, either round up or down is ok. For example, for 0.1346, (0.13 or.13) and (0.14 or.14) are correct
A project being analyzed by PERT has 60 activities, 13 of which are on the critical path. If the estimated time along the critical path is 214 days with a project variance of 81, what is Zscore for the scenario that the project will take 218 days or more to complete? -0.56 0 -0.44 0.56 0.44
A project being analyzed by PERT has 60 activities, 13 of which are on the critical path. If the estimated time along the critical path is 214 days with a project variance of 81, what is the probability that the project will take 218 days or more to complete? Choose the closest number. 0.6716 0.8413 0.0126 0.1587 0.3283
0 0
Next > < Previous
Answer

This Homework Help Question: "#1 #2 #3 #4 Time Estimates (in weeks) for SOM's Bus Project is given in the..." No answers yet.

Be the First!

Request Answer

Request answer!

We need 10 more requests to produce the answer to this homework help question. Share with your friends to get the answer faster!

0 /10 have requested the answer to this homework help question.

Request! (Login Required) Share with friends


Once 10 people have made a request, the answer to this question will be available in 1-2 days.
All students who have requested the answer will be notified once they are available.
Know the answer?
Add Answer of:
#1 #2 #3 #4 Time Estimates (in weeks) for SOM's Bus Project is given in the...
Your Answer: Your Name: What's your source?
Similar Homework Help Questions
Free Homework App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
Share Your Knowledge

Post an Article
Post an Answer
Post a Question with Answer

Self-promotion: Authors have the chance of a link back to their own personal blogs or social media profile pages.