Correct Answer:
Requirement a:
|
Temperature monitor |
Harmonic analyser |
|
|
Direct material |
$ 250 |
$ 2,500 |
|
Direct labour |
$ 25 |
$ 500 |
|
Total Cost per unit |
$ 275 |
$ 3,000 |
|
Units |
$ 900 |
$ 1 |
|
Total variable cost |
$ 2,47,500 |
$ 3,000 |
|
Add: Overhead allocation as per ABC |
||
|
product design |
$ 2,350 |
$ 5,500 |
|
material ordering and handling |
$ 1,360 |
$ 2,000 |
|
inspection |
$ 1,406 |
$ 125 |
|
setup |
$ 31.25 |
$ 31.25 |
|
labour-related overhead |
||
|
depreciation of plant and equipment |
$ 8,960.00 |
$ 560.00 |
|
$ 2,61,607.50 |
$ 11,216.25 |
|
|
Units |
$ 900.00 |
$ 1.00 |
|
Cost Per Unit |
$ 290.68 |
$ 11,216.25 |
|
Mark-up at 30% per unit |
$ 87.20 |
$ 3,364.88 |
|
$ 377.88 |
$ 14,581.13 |
|
|
Number of units |
$ 900.00 |
$ 1.00 |
|
Value of order |
$ 3,40,089.75 |
$ 14,581.13 |
Requirement b:
|
data logging device |
|
|
Direct material |
$ 9,000.00 |
|
Direct labour |
$ 3,000.00 |
|
Total Cost per unit |
$ 12,000.00 |
|
Units |
$ 1.00 |
|
Total variable cost |
$ 12,000.00 |
|
Add: Overhead allocation as per ABC |
|
|
product design |
$ 1,100.00 |
|
material ordering and handling |
$ 1,200.00 |
|
inspection |
$ 62.50 |
|
setup |
$ 31.25 |
|
labour-related overhead |
|
|
depreciation of plant and equipment |
$ 800.00 |
|
$ 15,193.75 |
|
|
Units |
$ 1.00 |
|
Cost Per Unit |
$ 15,193.75 |
|
Mark-up at 30% per unit |
$ 4,558.13 |
|
$ 19,751.88 |
|
|
Number of units |
$ 1.00 |
|
Value of order |
$ 19,751.88 |
The lowest price sarif should offer their bid is at $ 19,752
Working:
|
Tempreture monitor |
Harmonic Analyzer |
data logging device |
||||||
|
Per cost driver |
Per 900 unit |
Total |
per unit |
total |
per unit |
total |
||
|
product design |
8,000,000/160,000 = |
50 |
47*50 |
$ 2,350.00 |
110*50 |
$ 5,500.00 |
22*50 |
$ 100.00 |
|
material ordering and handling |
10,000,000/125,000 = |
80 |
17*80 |
$ 1,360.00 |
25*80 |
$ 2,000.00 |
15*80 |
$ 1,200.00 |
|
inspection |
3,500,000/560,000 |
6.25 |
225*6.25 |
$ 1,406.25 |
20*6.25 |
$ 125.00 |
10*6.25 |
$ 62.50 |
|
setup |
2,500,000/800,000 = |
31.25 |
1*31.25 |
$ 31.25 |
1*31.25 |
$ 31.25 |
1*31.25 |
$ 31.25 |
|
labour-related overhead |
0.8 |
|||||||
|
depreciation of plant and equipment |
18,000000/225,000 = |
80 |
112*80 |
$ 8,960.00 |
7*80 |
$ 560.00 |
10*80 |
$ 800.00 |
End of answer.
Please give a thumbs-up, it will be highly appreciated.
Thanks.
Accounting 305 CASE 1 Sarif Industries Activity-Based Costing (ABC) Quantum TM manufactures electronic testing and measurement...
Case 2 Activity-based Costing (ABC) vs. Time-based Costing Hello company manufactures three products, A, B and C. Forecast data concerning overheads (indirect costs) of the products for the next period as follows 120 Forecast output100 (units) Machine hours per3 unit Number customer orders Number of quality 20 control inspections Number engineering consultancies Areas workshops (m 150 2 of 10 15 25 10 30 of 200 500 300 Cost pools and related cost drivers Cost pool S Machine operating 24,000 Order...
Activity-Based Costing Zeus Industries manufactures two types of electrical power units, custom and standard, which involve four factory overhead activities—production setup, procurement, quality control, and materials management. An activity analysis of the overhead revealed the following estimated activity costs and activity bases for these activities: Activity Activity Cost Activity Base Production setup $ 67,500 Number of setups Procurement 126,000 Number of purchase orders (PO) Quality control 156,000 Number of inspections Materials management 147,000 Number of components Total $496,500 The activity-base...
Activity-Based Costing Zeus Industries manufactures two types of electrical power units, custom and standard, which involve four factory overhead activities-production setup, procurement, quality control, and materials management. An activity analysis of the overhead revealed the following estimated activity costs and activity bases for these activities: Activity Activity Cost Production setup Procurement $ 58,500 136,500 182,000 200,000 Activity Base Number of setups Number of purchase orders (PO) Number of inspections Number of components Quality control Materials management Total $577,000 The activity-base...
Tidwell Industries has the following overhead costs and cost drivers. Direct labor hours are estimated at 100000 for the year. Activity Cost Pool Cost Driver Est. Overhead Cost Driver Activity Ordering and Receiving Orders $ 95000 500 orders Machine Setup Setups 274500 450 setups Machining Machine hours 1437500 125000 MH Assembly Parts 1150000 1000000 parts Inspection Inspections 275000 500 inspections If overhead is applied using activity-based costing, the overhead application rate for ordering and receiving is $0.10 per part. $6464 per...
Tidwell Industries has the following overhead costs and cost drivers. Direct labor hours are estimated at 100000 for the year. Activity Cost Pool Cost Driver Est. Overhead Cost Driver Activity Ordering and Receiving Orders $ 135000 500 orders Machine Setup Setups 310500 450 setups Machining Machine hours 1550000 125000 MH Assembly Parts 1230000 1000000 parts Inspection Inspections 315000 500 inspections If overhead is applied using activity-based costing, the overhead application rate for ordering and receiving is $7081 per order. $0.14 per...
Tidwell Industries has the following overhead costs and cost drivers. Direct labor hours are estimated at 100000 for the year. Activity Cost Pool Cost Driver Est. Overhead Cost Driver Activity Ordering and Receiving Orders $ 110000 500 orders Machine Setup Setups 288000 450 setups Machining Machine hours 1475000 125000 MH Assembly Parts 1180000 1000000 parts Inspection Inspections 290000 500 inspections If overhead is applied using activity-based costing, the overhead application rate for ordering and receiving is $220 per order. $6686 per...
What was the cost per unit of each model using ABC costing Round
cost per unit to 2 decimal places
Cost per unit Royal: Majestic:
Schultz Electronics manufactures two ultra high-definition television models: the Royale which sells for $1,530, and a new model, the Majestic, which sells for $1,270. The production cost computed per unit under traditional costing for each model in 2017 was as follows. Traditional Costing Royale Majestic Direct materials $640 $400 Direct labor ($20 per hour) 120...
Current Attempt in Progress Tidwell Industries has the following overhead costs and cost drivers. Direct labor hours are estimated at 100000 for the year. Cost Driver Orders Est. Overhead $ 150000 Cost Driver Activity 500 orders Activity Cost Pool Ordering and Receiving Machine Setup Machining Assembly Inspection 324000 1587500 Setups Machine hours Parts Inspections 450 setups 125000 MH 1000000 parts 500 inspections 1260000 330000 If overhead is applied using activity-based costing, the overhead application rate for ordering and receiving is...
what is the overhead application rate for ordering and
receiving?
Current Attempt in Progress Tidwell Industries has the following overhead costs and cost drivers. Direct labor hours are estimated at 100000 for the year. Est. Overhead $ 65000 Activity Cost Pool Cost Driver Ordering and Receiving Orders Machine Setup Setups Machining Machine hours Assembly Parts Inspection Inspections 247500 1362500 1090000 245000 Cost Driver Activity 500 orders 450 setups 125000 MH 1000000 parts 500 inspections If overhead is applied using activity-based...
x Tidwell Industries has the following overhead costs and cost drivers. Direct labor hours are estimated at 100,000 for the year. Activity Cost Pool Cost Driver Est. Overhead Cost Driver Activity Ordering and Receiving Orders $ 120,000 500 orders Machine Setup Setups 297,000 450 setups Machining Machine hours 1,500,000 125,000 MH Assembly Parts 1,200,000 1,000,000 parts Inspection Inspections 300,000 500 inspections If overhead is applied using activity-based costing, the overhead application rate for ordering and receiving is Selected Answer: A....