Question

SML and WACC. An all-equity firm is considering the following projects: The T-bill rate is 4...

SML and WACC. An all-equity firm is considering the following projects:

The T-bill rate is 4 percent, and the expected return on the market is 12 percent.

a. Which projects have a higher expected return than the firm’s 12 percent cost of capital?

b. Which projects should be accepted?

c. Which projects will be incorrectly accepted or rejected if the firm’s overall cost of capital were used as a hurdle rate?

0 0
Add a comment Improve this question Transcribed image text
Answer #1

In evaluating multiple individual projects each projects has to be individually evaluated. Projects have to be evaluated based on the internal rate of return (IRR) of the project and market returns.

(a)

Consider the following information about the firm:

Project

Beta

IRR

W

0.80

10.2%

X

0.90

11.4%

Y

1.10

12.6%

Z

1.35

15.1%

The risk-free rate is 4%.

The Expected return on market is 12%.

The cost of capital is 12%.

Project Y and Project Z have a higher expected return than the firm’s 12 percent cost of capital. Project Y has an expected return of 12.6%, while Project Z has an expected return of 15.1%.

(b) Calculate the firm’s expected return:

In order to evaluate which project should be accepted, calculate the expected return on equity for each of the four projects.

Expected return on project can be calculated as follows:

Where,

Substitute values and calculate expected return for each project as shown below:

For the project W:

Hence, expected return on Project W is 10.4%.

For the Project X:

Hence, expected return on Project X is 11.2%.

For the Project Y:

Hence, expected return on Project Y is 12.8%

For the Project Z:

Hence, expected return on Project Z is 14.8%

Therefore, project Y and project Z give higher expected return than the market expectation rate.

(c)

Each project has its own risk as reflected by the value of beta. The firm’s overall cost of capital can be used as a hurdle rate only when the risk associated with the firm as a whole is equal to the risk associated with these projects.

Calculate the value of beta for the firm as a whole. Cost of capital is 12 %, market risk premium is 8 % and risk free rate is 4 %, then beta for company can be calculated as given below:

So, for the projects having beta less than 1.0 (project W and project X), firm’s cost of capital used as a hurdle rate will be incorrectly rejected though their risk is less than the firm. So the firm’s overall cost of capital is not appropriate to use as a hurdle rate.

Similarly, for the projects having beta more than 1.0 (project Y and project Z), firm’s cost of capital used as a hurdle rate will be incorrectly accepted though their risk is more than the firm. So the firm’s overall cost of capital is not appropriate to use as a hurdle rate.

Add a comment
Know the answer?
Add Answer to:
SML and WACC. An all-equity firm is considering the following projects: The T-bill rate is 4...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • 17. SML and WACC [LO1] An all-equity firm is considering the following projects: Project Beta IRR...

    17. SML and WACC [LO1] An all-equity firm is considering the following projects: Project Beta IRR W 8.9% X .85 .92 1.09 1.35 10.8 12.8 < 13.3 N The T-bill rate is 4 percent, and the expected return on the market is 11 percent. a. Which projects have a higher expected return than the firm's 11 percent cost of capital? b. Which projects should be accepted? c. Which projects would be incorrectly accepted or rejected if the firm's overall cost...

  • An all-equity firm is considering the following projects: Project Beta IRR W .64     9.5 % X...

    An all-equity firm is considering the following projects: Project Beta IRR W .64     9.5 % X .75     10.6 Y 1.31     14.1 Z 1.42     17.2 The T-bill rate is 5.2 percent, and the expected return on the market is 12.2 percent. a. Which projects have a higher/lower expected return than the firm’s 12.2 percent cost of capital? b. Which projects should be accepted? c. Which projects will be incorrectly accepted/rejected or correctly accepted/rejected if the firm's overall cost of capital were...

  • An all-equity firm is considering the following projects: Project Beta IRR W .65       10.0 %...

    An all-equity firm is considering the following projects: Project Beta IRR W .65       10.0 % X .90       10.5 Y 1.20       14.0 Z 1.80       17.0 The T-bill rate is 5 percent, and the expected return on the market is 12 percent. Required: (a) Which projects have a higher expected return than the firm’s 12 percent cost of capital? Project W has a (Click to select)lowerhigher expected return, Project X has a (Click to select)lowerhigher expected return, Project...

  • An all-equity firm is considering the following projects: Project Beta 80 90 1.10 1.35 IRR 9.3%...

    An all-equity firm is considering the following projects: Project Beta 80 90 1.10 1.35 IRR 9.3% 11.4 12.1 15.1 The T-bill rate is 4 percent, and the expected return on the market is 12 percent. a. Which projects have a higher expected return than the firm's 12 percent cost of capital? expected retum, Project X has a Project W has a expected return, and Project Z has a expected return, Project Y has a expected return. b. Which projects should...

  • n all-equity firm is considering the following projects: Project W Beta IRR .80 9.3% х .90...

    n all-equity firm is considering the following projects: Project W Beta IRR .80 9.3% х .90 11.4 Y 1.10 12.1 Z 1.35 15.1 he T-bill rate is 4 percent, and the expected return on the market is 12 percent. . Which projects have a higher expected return than the firm's 12 percent cost of capital? expected return, Project X has a Project W has a expected return, Project Y has a expected return expected return, and Project Z has a...

  • An all-equity firm is considering the following projects: Project Beta .89 76 141 IRR 10.3% 108...

    An all-equity firm is considering the following projects: Project Beta .89 76 141 IRR 10.3% 108 143 173 1.52 The T-bill rate is 5.3 percent, and the expected return on the market is 12.3 percent. a. Which projects have a higher/lower expected return than the firm's 12.3 percent cost of capital? expected return, Project X has a expected return, Project Y has a Project W has a expected return, and Project Z has a expected return b. Which projects should...

  • An all-equity firm is considering the following projects: Project Beta IRR W .58 9% X .87...

    An all-equity firm is considering the following projects: Project Beta IRR W .58 9% X .87 9.7% Y 1.13 12.1% Z 1.47 15.2% The T-bill rate is 4.2 percent, and the expected return on the market is 11.2 percent. Compared with the firm's 11.2 percent cost of capital, Project W has a _____(answer 1) (lower or Higher)____ expected return, Project X has a _____(answer 2) (lower or Higher)____ expected return, Project Y has a _____(answer 3) (lower or Higher)____ expected...

  • An all-equity firm is considering the following projects: Project Beta IRR W .89 10.3 % X...

    An all-equity firm is considering the following projects: Project Beta IRR W .89 10.3 % X .76 10.8 Y 1.41 14.3 Z 1.52 17.3 The T-bill rate is 5.3 percent, and the expected return on the market is 12.3 percent. a. Which projects have a higher/lower expected return than the firm’s 12.3 percent cost of capital?    Project W has a (Click to select)higherlower expected return, Project X has a (Click to select)higherlower expected return, Project Y has a (Click...

  • (5 points) An all equity firm is considering the following projects: 2. Project Beta 0.8 1.2...

    (5 points) An all equity firm is considering the following projects: 2. Project Beta 0.8 1.2 IRR 10% 12% The risk-free rate is 3% and the expected market rate premium is 8%. The firm has a beta equal to 1 (1 point) What is the firm's cost of capital? a. b. (2 points) Which projects should be accepted? Explain (2 point) Which projects will be incorrectly accepted or rejected if the firm's overall cost of capital were used to as...

  • An all-equity firm is considering the projects shown below. The T-bill rate is 3 percent and...

    An all-equity firm is considering the projects shown below. The T-bill rate is 3 percent and the market risk premium is 8 percent. Project Expected Return 8% 20 MUA Beta 0.6 1.3 1.5 1.7 14 Calculate the project-specific benchmarks for each project. (Round your answers to 2 decimal places.) Project A Project B Project C Project D If the firm uses its current WACC of 12 percent to evaluate these projects, which project(s), will be incorrectly accepted?

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT