Answer : $ 24.57
Unit Product Cost = Total Manufacturing cost / Units Produced
Total Manufacturing Cost = Direct Material + Direct Labour + Manufacturing Overheard
Calculation & Explanation

2, A company recently completed job #583. The company incurred direct materials of S40,610 and direct...
1. What is the company's predetermined overhead rate if the company anticipates 125,000 direct labor hours, variable manufacturing overhead costs of $7.43 per direct labor hour and total fixed manufacturing overhead of S189,000 during 2018? S189000 during 2013 overed st of 7.A8 per direr lab 2. A com pany recently completed job #583. The company incurred direct materials of S40610 and direct labor hours of 1,147. The direct labor wage rate was $11 per direct labor hour. The company completed...
Job 243 was recently completed. The following data have been recorded on its job cost sheet: Direct materials Direct labor-hours Direct labor wage rate Machine-hours Number of units completed $50,870 425 labor-hours $ 13 per labor-hour 506 machine-hours 3,100 units The company applies manufacturing overhead on the basis of machine-hours. The predetermined overhead rate is $11 per machine-hour. Required: Compute the unit product cost that would appear on the job cost sheet for this job. (Round your answer to 2...
Job 243 was recently completed. The following data have been recorded on its job cost sheet: Direct materials Direct labor-hours Direct labor vage rate Machine-hours Number of units completed $50,370 420 labor-hours $ 10 per labor-hour 501 machine-hours 3,000 units 4 The company applies manufacturing overhead on the basis of machine-hours. The predetermined overhead rate is $14 per machine- hour. Required: Compute the unit product cost that would appear on the job cost sheet for this job. (Round your answer...
Job 243 was recently completed. The following data have been recorded on its job cost sheet $57,870 Direct materials Direct labor-hours Direct labor wage rate Machine-hours Number of units completed 495 labor-hours 11 per labor-hour 576 machine-hours 4,500 units The company applies manufacturing overhead on the basis of machine-hours. The predetermined overhead rate is $13 per machine- hour Required Compute the unit product cost that would appear on the job cost sheet for this job. (Round your answer to 2...
Job 827 for the Colorado Company was recently completed. The following data have been recorded on its job cost sheet: Direct materials $61,050 Direct labor hours 1,332 labor hours Direct labor wage rate $14 per labor-hour Machine Hours 1,480 machine hours Number of units completed 3,700 units The company applies manufacturing overhead on the basis of machine-hours. The predetermined overhead rate is $13 per machine-hour. Compute the unit product cost that would appear on the job cost sheet for this...
Job 231 was recently completed. The following data have been recorded on its job cost sheet: Direct materials Direct labor-hours Direct labor wage rate Machine-hours Number of units completed $ 46,000 630 labor-hours $ 14 per labor-hour 340 machine-hours 2,500 units The company applies manufacturing overhead on the basis of machine-hours. The predetermined overhead rate is $10 per machine-hour. Required: Compute the unit product cost that would appear on the job cost sheet for this job. (Round your answer to...
Job 243 was recently completed. The following data have been recorded on its job cost sheet: Direct materials Direct labor-hours Direct labor wage rate Machine-hours Number of units completed $58,370 500 labor-hours 10 per labor-hour 581 machine-hours 4,600 units The company applies manufacturing overhead on the basis of machine-hours. The predetermined overhead rate is $14 per machine hour. Required: Compute the unit product cost that would appear on the job cost sheet for this job. (Round your answer to 2...
Job 243 was recently completed. The following data have been recorded on its job cost sheet: Direct materials Direct labor-hours Direct labor wage rate Machine-hours Number of units completed $57,370 490 labor-hours $ 12 per labor-hour 571 machine-hours 4,400 units The company applies manufacturing overhead on the basis of machine-hours. The predetermined overhead rate is $12 per machine-hour. Required: Compute the unit product cost that would appear on the job cost sheet for this job. (Round your answer to 2...
Job 243 was recently completed. The following data have been recorded on its job cost sheet: Direct materials Direct labor-hours Direct labor wage rate Machine-hours Number of units completed $52,870 445 labor-hours $ 13 per labor-hour 526 machine-hours 3,500 units The company applies manufacturing overhead on the basis of machine-hours. The predetermined overhead rate is $11 per machine- hour. Required: Compute the unit product cost that would appear on the job cost sheet for this job. (Round your answer to...
3) Job 652 was recently completed. The following data have been recorded on its job cost sheet: Direct materials Direct labor-hours Direct labor wage rate Number of units completed S 59,400 1,224 DLHs $ 15 per DLH 3,600 units The company applies manufacturing overhead on the basis of direct labor-hours. The predetermined overhead rate is $35 per direct labor-hour. Required: Compute the unit product cost that would appear on the job cost sheet for this job.