Question

Current Attempt in Progress Nash Furniture Company started construction of a combination office and warehouse building for it
0 0
Add a comment Improve this question Transcribed image text
Answer #1

1.Here the project is financed by 1.Construction loan (specific project realated)

2. Short term and long term loans (general loans)

Given ,the Weighted average amount of accumulated expenditure is $6,840,000

Out of the $6,840,000(Weighted-average), $3,800,000 is financed by Construction loan (specific loan). The rest i.e. $3,040,000 is financed out of the general loans. The interest rate on Construction loan (specific loan) is 12% while the weighted interest rate on the general loans is calculated below.

Loan Principal Rate Annual Interest
short trem 2,660,000 10% 266,000
long term 1,900,000 11% 209,000
4,560,000 475,000
Weighted-average Interest Rate = $475,000 = 10.41%
$4,560,000

The above calculations furnish us with all the data needed to arrive at an estimate of avoidable interest.

Funding Amount Rate Avoidable Interest
Specific Loan 3,800,000 12% 456,000
General pool 3,040,000 10.41% 316,464
772,464

This $772,464 is the amount of interest that could have been avoided. This much interest can be capitalized provided it doesn’t exceed the actual interest expense for the period.

2.Straight line depreciation is a common method of depreciation where the value of a fixed asset is reduced gradually over its useful life..

Depreciation under Straight Line Method = Initial cost of the asset less the estimated salvage value / estimated full useful life( in years)

here, the cost of the project = $9,880,000, useful life= 30 years, salvage value = $570,000

So Depreciation is 9,880,000 - 570,000 / 30 = $310,333..33 or $310,333 (rounded off).

Hope you are satisfied with the answers.Please share your feedback.Thank you

Add a comment
Know the answer?
Add Answer to:
Current Attempt in Progress Nash Furniture Company started construction of a combination office and warehouse building...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Question 3 Headland Furniture Company started construction of a combination office and warehouse building for its...

    Question 3 Headland Furniture Company started construction of a combination office and warehouse building for its own use at an estimated cost of $9,500,000 on January 1, 2020. Headland expected to complete the building by December 31, 2020. Headland has the following debt obligations outstanding during the construction period. Construction loan-12% interest, payable semiannually, issued December 31, 2019 Short-term loan-10% interest, payable monthly, and principal payable at maturity on May 30, 2021 Long-term loan-11% interest, payable on January 1 of...

  • Windsor Furniture Company started construction of a combination office and warehouse building for its own use at an esti...

    Windsor Furniture Company started construction of a combination office and warehouse building for its own use at an estimated cost of $10,500,000 on January 1, 2020. Windsor expected to complete the building by December 31, 2020. Windsor has the following debt obligations outstanding during the construction period. Construction loan-12% interest, payable semiannually, issued December 31, 2019 $4,200,000 Short-term loan-10% interest, payable monthly, and principal payable at maturity on May 30, 2021 2,940,000 Long-term loan-11% interest, payable on January 1 of...

  • Exercise 10-07 Tamarisk Furniture Company started construction of a combination office and warehouse building for its...

    Exercise 10-07 Tamarisk Furniture Company started construction of a combination office and warehouse building for its own use at an estimated cost of $9,000,000 on January 1, 2020. Tamarisk expected to complete the building by December 31, 2020. Tamarisk has the following debt obligations outstanding during the construction period. Construction loan-12% interest, payable semiannually, issued December 31, 2019 Short-term loan-10% interest, payable monthly, and principal payable at maturity on May 30, 2021 Long-term loan-11% interest, payable on January 1 of...

  • Stellar Furniture Company started construction of a combination office and warehouse building for its own use...

    Stellar Furniture Company started construction of a combination office and warehouse building for its own use at an estimated cost of $11,000,000 on January 1, 2020. Stellar expected to complete the building by December 31, 2020. Stellar has the following debt obligations outstanding during the construction period. $4,400,000 Construction loan-12% interest, payable semiannually, issued December 31, 2019 3,080,000 Short-term loan-10% interest, payable monthly, and principal payable at maturity on May 30, 2021 Long-term loan-11% interest, payable on January 1 of...

  • Carla Furniture Company started construction of a combination office and warehouse building for its own use...

    Carla Furniture Company started construction of a combination office and warehouse building for its own use at an estimated cost of $6,000,000 on January 1, 2020. Carla expected to complete the building by December 31, 2020. Carla has the following debt obligations outstanding during the construction period. Construction loan-14% interest, payable semiannually, issued December 31, 2019 $2,400,000 Short-term loan-12% interest, payable monthly, and principal payable at maturity on May 30, 2021 1,680,000 Long-term loan-13% interest, payable on January 1 of...

  • Sheridan Furniture Company started construction of a combination office and warehouse building for its own use...

    Sheridan Furniture Company started construction of a combination office and warehouse building for its own use at an estimated cost of $13,500,000 on January 1, 2020. Sheridan expected to complete the building by December 31, 2020. Sheridan has the following debt obligations outstanding during the construction period. Construction loan-12% interest, payable semiannually, issued December 31, 2019 Short-term loan-10% interest, payable monthly, and principal payable at maturity on May 30, 2021 Long-term loan-11% interest, payable on January 1 of each year....

  • Oriole Furniture Company started construction of a combination office and warehouse building for its own use...

    Oriole Furniture Company started construction of a combination office and warehouse building for its own use at an estimated cost of $13,500,000 on January 1, 2020. Oriole expected to complete the building by December 31, 2020. Oriole has the following debt obligations outstanding during the construction period. Construction loan-12% interest, payable semiannually, issued December 31, 2019 $5,400,000 Short-term loan-10% interest, payable monthly, and principal payable at maturity on May 30, 2021 3,780,000 Long-term loan-11% interest, payable on January 1 of...

  • Sage Furniture Company started construction of a combination office and warehouse building for its own use...

    Sage Furniture Company started construction of a combination office and warehouse building for its own use at an estimated cost of $11,000,000 on January 1, 2020. Sage expected to complete the building by December 31, 2020. Sage has the following debt obligations outstanding during the construction period. Construction loan-12% interest, payable semiannually, issued December 31, 2019 $4,400,000 Short-term loan-10% interest, payable monthly, and principal payable at maturity on May 30, 2021 3,080,000 Long-term loan-11% interest, payable on January 1 of...

  • Martinez Furniture Company started construction of a combination office and warehouse building for its own use...

    Martinez Furniture Company started construction of a combination office and warehouse building for its own use at an estimated cost of $15,000,000 on January 1, 2020. Martinez expected to complete the building by December 31, 2020. Martinez has the following debt obligations outstanding during the construction period. Construction loan-12% interest, payable semiannually, issued December 31, 2019 Short-term loan-10% interest, payable monthly, and principal payable at maturity on May 30, 2021 Long-term loan-11% interest, payable on January 1 of each year....

  • Pearl Furniture Company started construction of a combination office and warehouse building for its own use...

    Pearl Furniture Company started construction of a combination office and warehouse building for its own use at an estimated cost of $7,500,000 on January 1, 2020. Pearl expected to complete the building by December 31, 2020. Pearl has the following debt obligations outstanding during the construction period. Construction loan-12% interest, payable semiannually, issued December 31, 2019 Short-term loan-10% interest, payable monthly, and principal payable at maturity on May 30, 2021 Long-term loan-11% interest, payable on January 1 of each year....

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT