Question

On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. TReq 1 and 3 Req 2 Calculate the amount of interest that Mason should capitalize in 2021 and 2022 using the specific interestReq 1 and 3 Req 2 What is the total cost of the building? (Do not round intermediate calculations.) Total cost of building

1 0
Add a comment Improve this question Transcribed image text
Answer #1

Answer 1

Expenditure for 2021
Expenditure for 2021 Amount Time factor Weighted Average
01-Jan-21 $         1,870,000 12/12 $      1,870,000
01-Mar-21 $         1,560,000 10/12 $      1,300,000
30-Jun-21 $         1,760,000 6/12 $ 880,000
01-Oct-21 $         1,560,000 3/12 $ 390,000
Accumulated capital Expenditure before interest capitalized $ 6,750,000
Average Accumulated capital Expenditure $      4,440,000
Interest capitalized in 2021
Average Accumulated capital Expenditure Multiplied by: interest rate Interest capitalized in 2021
$ 4440,000 15.00% $              6,66,000
Total capitalized value in 2021 $ 6,750,000 $              666,000 $      7,416,000
Expenditure for 2022
Expenditure for 2022 Amount Time factor Weighted Average
01-Jan-22 $         7,416,000 9/9 $      7,416,000
31-Jan-22 $             414000 8/9 $          368,000
30-Apr-22 $             747,000 5/9 $          415,000
31-Aug-22 $         1,044,000 1/9 $          116,000
Accumulated capital Expenditure before interest capitalized $ 9,621,000
Average accumulated capital Expenditure $      8,315,000
Weighted average rate for other debt
$ 2,000,000 8.00% $              160,000
$ 8,000,000 12.00% $ 960,000
$                                       10,000,000 $ 1120,000
Weighted average rate for other debt (Total interest/Total loan ) $ 1120,000 $        10,000,000 11.20%
Interest capitalized in 2022
For construction loan $         4,600,000 15.00% $          690,000
Other debt (8315000-4600000) $         3,715,000 11.20%

$ 416080

Interest for annual $      1,106,080
Interest capitalized in 2022 (1106080* 9/12)

$ 8,29,560

Answer 2

The total cost of the building
Expenditure in 2021 $ 6,750,000
Interest capitalized in 2021 $ 666,000
Expenditure in 2022 $      2,205,000
Interest capitalized in 2022 $ 8,29,560
The total cost of the building $    10,450,560

Answer 3

Interest expense charged to income statement
Construction loan $         4,600,000 15.00% $          690,000
Other debt 1 $ 2,000,000 8.00% $          160,000
Other debt 2 $ 8,000,000 12.00% $ 960,000
Total interest paid $ 1,810,000
Interest expense charged to income statement
Year 2021 2022
Total interest paid $          1,810,000 $      1,810,000
Less: interest capitalized $              666,000 $ 8,29,560
Interest expense charged to income statement $ 1,144,000 $ 980,440
Add a comment
Know the answer?
Add Answer to:
On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used...

    On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2022. Expenditures on the project were as follows: January 1, 2021 March 1, 2021 June 30, 2021 October 1, 2021 January 31, 2022 April 30, 2022 August 31, 2022 $1,280,000 960,000 1,160,000 960,000 324,000 657,000 954,000 On January 1, 2021, the company obtained a $3,600,000 construction loan with a 15% interest rate. The...

  • On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used...

    On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2022. Expenditures on the project were as follows: January 1, 2021 March 1, 2021 June 30, 2021 October 1, 2021 January 31, 2022 April 30, 2022 August 31, 2022 $1,420,000 1,140,000 1,340,000 1,140,000 351,000 684,000 981,000 On January 1, 2021, the company obtained a $3,900,000 construction loan with a 12% interest rate. The...

  • On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used...

    On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2022. Expenditures on the project were as follows: January 1, 2021 March 1, 2021 June 30, 2021 October 1, 2021 January 31, 2022 April 30, 2022 August 31, 2022 $1,310,000 1,020,000 1,220,000 1,020,000 333,000 666,000 963,000 On January 1, 2021, the company obtained a $3,700,000 construction loan with a 12% interest rate. The...

  • On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used...

    On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2022. Expenditures on the project were as follows: January 1, 2021 $ 1,350,000 March 1, 2021 1,080,000 June 30, 2021 1,280,000 October 1, 2021 1,080,000 January 31, 2022 342,000 April 30, 2022 $675,000 August 31, 2022 $972,000 On January 1, 2021, the company obtained a $3,800,000 construction loan with a 15% interest rate....

  • On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used...

    On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2022. Expenditures on the project were as follows: January 1, 2021 March 1, 2021 $1,850,000 1,500,000 1,700,000 1,500,000 June 30, 2021 October 1, 2021 January 31, 2022 April 30, 2022 August 31, 2022 405,000 738,000 1,035,000 On January 1, 2021, the company obtained a $4,500,000 construction loan with a 12% interest rate. The...

  • On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used...

    On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2022. Expenditures on the project were as follows: January 1, 2021 March 1, 2021 June 30, 2021 October 1, 2021 January 31, 2022 April 30, 2022 August 31, 2022 $1.850,000 1.500.000 1,700,000 1.500.000 405,000 738.000 1,035,000 On January 1, 2021, the company obtained a $4,500,000 construction loan with a 12% Interest rate. The...

  • On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used...

    On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2022. Expenditures on the project were as follows: January 1, 2021 $ 1,090,000 March 1, 2021 780,000 June 30, 2021 980,000 October 1, 2021 780,000 January 31, 2022 297,000 April 30, 2022 630,000 August 31, 2022 927,000 On January 1, 2021, the company obtained a $3,300,000 construction loan with a 16% interest rate....

  • On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used...

    On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2022. Expenditures on the project were as follows: January 1, 2021 March 1, 2021 June 30, 2021 October 1, 2021 January 31, 2022 April 30, 2022 August 31, 2022 $1.290, eee 78e, eee 980.ee 780, Bee 297, eee 630, eee 927.090 On January 1, 2021, the company obtained a $3,300,000 construction loan with...

  • On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used...

    On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2022. Expenditures on the project were as follows: $1,e9e, eee 780,000 98e, eee 780,eee 297,eee 630,eee 927,e00 January 1, 2021 March 1, 2021 June 30, 2021 October 1, 28e21 January 31, 2022 April 30, 2822 August 31, 2022 es On January 1, 2021, the company obtained a $3,300,000 construction loan with a 16...

  • On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used...

    On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2022. Expenditures on the project were as follows: January 1, 2021 $ 1,500,000 March 1, 2021 1,200,000 June 30, 2021 1,400,000 October 1, 2021 1,200,000 January 31, 2022 360,000 April 30, 2022 693,000 August 31, 2022 990,000 On January 1, 2021, the company obtained a $4,000,000 construction loan with a 14% interest rate....

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT