The project is on time but we cannot determine whether the project is on budget. (which is Option B)
_____
Explanation:
It is clear from the information provided in the question that the three phases (out of the six phases) have been completed as planned. Therefore, it can be concluded that the project is on time. However, it is not clear as to what was the budget that was actually planned for the first three phases. We have only been provided with the information that exactly half of the approved amount is spent till the completion of phase three. It is possible that more money has been spent in the first three phases than what was initially planned and that the balance amount may not be sufficient to pay for the remaining three phases.
uestion 7 of 21 You were asked to provide & report on performance of the project...