Question

Determining Cost of Land Fastball Delivery Company acquired an adjacent lot to construct a new warehouse,...

Determining Cost of Land Fastball Delivery Company acquired an adjacent lot to construct a new warehouse, paying $27,000 and giving a short-term note for $268,000. Legal fees paid were $1,910, delinquent taxes assumed were $11,100, and fees paid to remove an old building from the land were $22,600. Materials salvaged from the demolition of the building were sold for $4,400. A contractor was paid $896,800 to construct a new warehouse. Determine the cost of the land to be reported on the balance sheet. $

0 0
Add a comment Improve this question Transcribed image text
Answer #1

DETERMINATION OF THE COST OF LAND TO BE REPORTED IN THE BALANCE SHEET :-

Amount paid for acquire an adjacent lot = $ 27,000

Add:- Short term note = $ 268,000

Add:- Legal fee paid = $ 1,910

Add:- Delinquent tax = $ 11,100

Add:- Fees paid to remove an old building. = $ 22,600

Less:- Salvage material sold = ($ 4,400)

COST OF LAND = ​​ $3,26,210

SO THE COST OF LAND TO BE REPORTED IN THE BALANCE SHEET IS $3,26,210.

Add a comment
Know the answer?
Add Answer to:
Determining Cost of Land Fastball Delivery Company acquired an adjacent lot to construct a new warehouse,...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Determining Cost of Land Fastball Delivery Company acquired an adjacent lot to construct a new warehouse,...

    Determining Cost of Land Fastball Delivery Company acquired an adjacent lot to construct a new warehouse, paying $41,000 and giving a short term note for $267.000. Legal fees paid were $1,815, delinquent taxes assumed were $11,200, and fees paid to remove an old building from the land were $23,000. Materials salvaged from the demolition of the building were sold for $4,600. A contractor was paid $936,300 to construct a new warehouse. Determine the cost of the land to be reported...

  • Determining Cost of Land On-Time Delivery Company acquired an adjacent lot to construct a new warehouse,...

    Determining Cost of Land On-Time Delivery Company acquired an adjacent lot to construct a new warehouse, paying $26,000 and giving a short-term note for $335,000. Legal fees paid were $1,830, delinquent taxes assumed were $9,800, and fees paid to remove an old building from the land were $21,900. Materials salvaged from the demolition of the building were sold for $5,400. A contractor was paid $1,097,400 to construct a new warehouse. Determine the cost of the land to be reported on...

  • 7. EX.09-03.ALGO (Algorithmic) Determining Cost of Land Fastball Delivery Company acquired an adjacent lot to construct...

    7. EX.09-03.ALGO (Algorithmic) Determining Cost of Land Fastball Delivery Company acquired an adjacent lot to construct a new warehouse, paying $36,000 and giving a short-term note for $336,000. Legal fees paid were $1,675, delinquent taxes assumed were $14,100, and fees paid to remove an old building from the land were $16,600. Materials salvaged from the demolition of the building were sold for $5,600. A contractor was paid $1,130,900 to construct a new warehouse. Determine the cost of the land to...

  • On-Time Delivery Company acquired an adjacent lot to construct a new warehouse, paying $35,000 in cash...

    On-Time Delivery Company acquired an adjacent lot to construct a new warehouse, paying $35,000 in cash and giving a short-term note for $294,000. Legal fees paid were $1,750, delinquent taxes assumed were $12,400, and fees paid to remove an old building from the land were $18,300. Materials salvaged from the demolition of the building were sold for $4,900. A contractor was paid $1,000,200 to construct a new warehouse.

  • en olgen 7. EX.09-03.ALGO (Algorithmic) Determining Cost of Land Fastball Delivery Company acquired an adjacent lot...

    en olgen 7. EX.09-03.ALGO (Algorithmic) Determining Cost of Land Fastball Delivery Company acquired an adjacent lot to construct a new warehouse, paying $36,000 and giving a short-term note for $336,000. Legal fees paid were $1,675, delinquent taxes assumed were $14, 100, and fees paid to remove an old building from the land were $16,600. Materials salvaged from the demolition of the building were sold for $5,600. A contractor was paid $1,130,900 to construct a new warehouse. Determine the cost of...

  • Cost of Land On-Time Delivery Company acquired an adjacent lot were $2,480, delinquent taxes demolition of...

    Cost of Land On-Time Delivery Company acquired an adjacent lot were $2,480, delinquent taxes demolition of the building were sold for $5,300. A contractor was paid $1,073,100 to construct a new warehouse. Determine the cost of the land to be reported on the balance sheet. to construct a new warehouse, paying $32,000 and giving a short-term note for $321,000. Legal fees paid assumed were $13,300, and fees paid to remove an old building from the land were $18,600. Materials salvaged...

  • Show Me How Debermining Cest of Land Festhal Delivery Company acquired en ogacent lot to construct...

    Show Me How Debermining Cest of Land Festhal Delivery Company acquired en ogacent lot to construct ฮ nre marehoune, peyno e new warehouse, paying $27,000 and giving a short-term note for $268,000. Legpal fees paid were $1,910, toremove an old buldng from the land were %22,000. Materiais salvaged from the demolbonofthe buidrg T told- for $4,400 A contractor was paid $896,800 to construct a new warehouse. Determine the cost of the land to be reported on the balance sheet mone...

  • PLEASE HELP! Determining Cost of Land On-Time Delivery Company acquired an adiacent lot to construct a...

    PLEASE HELP! Determining Cost of Land On-Time Delivery Company acquired an adiacent lot to construct a new warehouse, paying $30,000 in cash and giving a short-term nate for $289.000. Legal fees paid were $1,765, delinquent taxes assumed were $10,700, and fees paid to remove an old building from the land were $17,800. Materials salvaged from the demolition of the building were sold for $4,800. A contractor was paid $969,800 to construct a new warehouse. Determine the cost of the land...

  • Samtech Manufacturing purchased land and building for $4 million. In addition to the purchase price, Samtech made the following expenditures in connection with the purchase of the land and building:

    Samtech Manufacturing purchased land and building for $4 million. In addition to the purchase price, Samtech made the following expenditures in connection with the purchase of the land and building: Title insurance$20,000Legal fees for drawing the contract7,000Pro-rated property taxes for the period after acquisition40,000State transfer fees4,400 An independent appraisal estimated the fair values of the land and building, if purchased separately, at $3.2 and $1.8 million, respectively. Shortly after acquisition, Samtech spent $86,000 to construct a parking lot and $44,000 for landscaping. Required:1. Determine...

  • The following items represent expenditures (or receipts) related to the construction of a new home office...

    The following items represent expenditures (or receipts) related to the construction of a new home office for Secrest Investment Company. Cost of land site, which included an abandoned railroad spur $205,000 Legal fees, including title search, relating to land purchase 8,300 Cost of surveying land to confirm boundaries 1,100 Cost of removing railroad tracks 6,500 Payment of delinquent property taxes assumed by the purchaser 6,000 Proceeds from sale of timber from walnut trees cut down to prepare site for construction...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT