Compute construction in progress Amount as follows:
| 2021 | 2022 | 2023 | |
| Billing during the year (A) | $2,090,000 | $2,838,000 | $5,072,000 |
| Cost incured during the year (B) | $2,581,000 | $2,347,000 | $3,049,200 |
| Cumulative cost to date (C) | $2,581,000 | $4,928,000 | $7,977,200 |
| Add: Estimated costs to complete as of year end (D) | $6,319,000 | $2,772,000 | |
| Estimated total cost (E = C+D) | $8,900,000 | $7,700,000 | $7,977,200 |
| % of Completion (F = C/E) | 29.0% | 64.0% | 100.0% |
| Contract price (G) | $10,000,000 | $10,000,000 | $10,000,000 |
| Construction in progress (F × G) | $2,900,000 | $6,400,000 | $10,000,000 |
13 Return to question Part 3 of 5 Required information [The following information applies to the...
Required information [The following information applies to the questions displayed below.) In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2023 $3,849,200 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,581,000 6,319,000 2,890,000 1,845,000 2022 $2,347,000 2,772,000 2,838,000 2,900,000 5,072,000 5,255,000...
Return to question Required information (The following information applies to the questions displayed below! Part 2 of 5 In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: points 2023 $3,849,200 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,581,000 6,319,000 2,090,000...
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,581,000 $ 2,347,000 $ 3,049,200 Estimated costs to complete as of year-end 6,319,000 2,772,000 0 Billings during the year 2,090,000 2,838,000 5,072,000 Cash collections during the year 1,845,000 2,900,000 5,255,000 Westgate recognizes revenue over time according to...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,581,000 $ 2,347,000 $ 3,049,200 Estimated costs to complete as of year-end 6,319,000 2,772,000 0 Billings during the year 2,090,000 2,838,000 5,072,000 Cash collections during the year 1,845,000 2,900,000 5,255,000 Westgate recognizes revenue over time according to...
Required information [The following information applies to the
questions displayed below.] In 2021, the Westgate Construction
Company entered into a contract to construct a road for Santa Clara
County for $10,000,000. The road was completed in 2023. Information
related to the contract is as follows: 2021 2022 2023 Cost incurred
during the year $ 2,016,000 $ 2,808,000 $ 2,613,600 Estimated costs
to complete as of year-end 5,184,000 2,376,000 0 Billings during
the year 2,180,000 2,644,000 5,176,000 Cash collections during the...
! 7 Required information [The following information applies to the questions displayed below.] Part 3 of 5 In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 10 points Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,640,000 6,160,000 2,080,000 1,840,000 2022...
Required information [The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2022 $3, 984, 000 1, 826, 000 4, 444, 000 3, 900, 000 2021 $2, 490, 000 2023 $2, 008, 600 Cost incurred during the year Estimated costs to complete as of year-end Billings during...
pleass help on wrong answers!!!
Required information The following information applies to the questions displayed below) In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2023 $2,655,400 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,059,000 5,041,000 2,190,000 1,895,000 2022 $2,627,000...
5 Required information (The following information applies to the questions displayed below.) Part 1 of 5 In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: - 2023 $2,926,000 10 points Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,640,000 6,160,000 2,080,000...
Required information [The following information applies to the
questions displayed below.] In 2021, the Westgate Construction
Company entered into a contract to construct a road for Santa Clara
County for $10,000,000. The road was completed in 2023. Information
related to the contract is as follows: 2021 2022 2023 Cost incurred
during the year $ 2,016,000 $ 2,808,000 $ 2,613,600 Estimated costs
to complete as of year-end 5,184,000 2,376,000 0 Billings during
the year 2,180,000 2,644,000 5,176,000 Cash collections during the...