SOLUTION
A. Total materials variance = Actual material cost - (Standard quantity * Standard cost)
= $27,816 - (4,400*$6)
= $27,816 - $26,400 = $1,416 U
Materials price variance = (Actual quantity * Actual price) - (Actual quantity * Standard price)
= $27,816 - (4,560*$6)
= $27,816 - $27,360 = $456 U
Materials quantity variance = (Actual quantity * Standard price) - (Standard quantity * Standard price)
= (4,560*$6) - (4,400*$6)
= $27,360 - $26,400 = $960 U
Total labor variance = Actual labor cost - (Standard hours * Standard rate)
= $26,355 - (2,200*$12.35)
= $26,355 - $27,170 = $815 F
Standard hours = 4,400*0.50 = 2,200
Labor rate variance = (Actual hours * Actual rate) - (Actual hours *Standard rate)
= $26,355 - (2,100 * $12.35)
= $26,355 - $25,935 = $420 U
Labor quantity variance = (Actual hours * Standard rate) - (Standard hours *Standard rate)
= (2,100 * $12.35) - (2,200*$12.35)
= $25,935 - $27,170 = $1,235 F
B. Total overhead variance = Actual overhead - Overhead Applied
= ($21,558 + $11,142) - (2,200 * $14)
= $32,700 - $30,800
= 1,900 U
PrOblem -A Your answer is partially correct. Try again Rogen Corporation manufactures a single product. The...
Problem 11-1A Rogen Corporation manufactures a single product. The standard cost per unit of product is shown below Direct materials-1 pound plastic at $6 per pound Direct labor-0.50 hours at $12.35 per hour Variable manufacturing overhead Fixed manufacturing overhead 6.00 6.18 3.25 3.75 $19.18 Total standard cost per unit The predetermined manufacturing overhead rate is $14 per direct labor hour ($7.00 ÷ 0.50). It was computed from a master manufacturing overhead budget based on normal production of 2,500 direct labor...
Rogen Corporation manufactures a single product. The standard
cost per unit of product is shown below.
Direct materials—1 pound plastic at $6 per pound
$ 6.00
Direct labor—0.50 hours at $11.75 per hour
5.88
Variable manufacturing overhead
3.50
Fixed manufacturing overhead
1.50
Total standard cost per unit
$16.88
The predetermined manufacturing overhead rate is $10 per direct
labor hour ($5.00 ÷ 0.50). It was computed from a master
manufacturing overhead budget based on normal production of 2,950
direct labor hours...
Problem 11-1A (Video) Partially correct answer. Your answer is partially correct. Try again. Rogen Corporation manufactures a single product. The standard cost per unit of product is shown below. Direct materials—1 pound plastic at $6.00 per pound $ 6.00 Direct labor—2.0 hours at $11.90 per hour 23.80 Variable manufacturing overhead 12.00 Fixed manufacturing overhead 20.00 Total standard cost per unit $61.80 The predetermined manufacturing overhead rate is $16.00 per direct labor hour ($32.00 ÷ 2.0). It was computed from a...
Rogen Corporation manufactures a single product. The standard
cost per unit of product is shown below.
Direct materials—1 pound plastic at $6 per pound
$ 6.00
Direct labor—1.50 hours at $12.20 per hour
18.30
Variable manufacturing overhead
9.00
Fixed manufacturing overhead
15.00
Total standard cost per unit
$48.30
The predetermined manufacturing overhead rate is $16 per direct
labor hour ($24.00 ÷ 1.50). It was computed from a master
manufacturing overhead budget based on normal production of 8,700
direct labor hours...
Rogen Corporation manufactures a single product. The standard
cost per unit of product is shown below.
Direct materials—1 pound plastic at $6.00 per pound
$ 6.00
Direct labor—2.0 hours at $11.85 per hour
23.70
Variable manufacturing overhead
12.00
Fixed manufacturing overhead
12.00
Total standard cost per unit
$53.70
The predetermined manufacturing overhead rate is $12.00 per direct
labor hour ($24.00 ÷ 2.0). It was computed from a master
manufacturing overhead budget based on normal production of 11,800
direct labor hours...
Rogen Corporation manufactures a single product. The standard cost per unit of product is shown below. Direct materials—1 pound plastic at $6.00 per pound $ 6.00 Direct labor—2.0 hours at $11.85 per hour 23.70 Variable manufacturing overhead 12.00 Fixed manufacturing overhead 12.00 Total standard cost per unit $53.70 The predetermined manufacturing overhead rate is $12.00 per direct labor hour ($24.00 ÷ 2.0). It was computed from a master manufacturing overhead budget based on normal production of 11,800 direct labor hours...
Rogen Corporation manufactures a single product. The standard cost per unit of product is shown below. Direct materials—1 pound plastic at $6 per pound $ 6.00 Direct labor—0.50 hours at $11.95 per hour 5.98 Variable manufacturing overhead 3.00 Fixed manufacturing overhead 5.00 Total standard cost per unit $19.98 The predetermined manufacturing overhead rate is $16 per direct labor hour ($8.00 ÷ 0.50). It was computed from a master manufacturing overhead budget based on normal production of 2,600 direct labor hours...
Just need help with Total
Overhead Variance- 6000 is incorrect
Rogen Corporation manufactures a single product. The standard cost per unit of product is shown below. Direct materials-1 pound plastic at $7 per pound Direct labor-1.50 hours at $11.10 per hour Variable manufacturing overhead Fixed manufacturing overhead Total standard cost per unit $7.00 16.65 11.25 6.75 $41.65 The predetermined manufacturing overhead rate is $12 per direct labor hour ($18.00+ 1.50). It was computed from a master manufacturing overhead budget based...
Problem 23-1A Rogen Corporation manufactures a single product. The standard cost per unit of product is shown below. Direct materials-1 pound plastic at $6 per pound Direct labor-2.00 hours at $12.20 per hour Variable manufacturing overhead Fixed manufacturing overhead Total standard cost per unit $ 6.00 24.40 15.00 13.00 $58.40 The predetermined manufacturing overhead rate is $14 per direct labor hour ($28.00 -2.00). It was computed from a master manufacturing overhead budget based on normal production of 10,000 direct labor...
Please answer as it is asked in the questions
Problem 23-1A Rogen Corporation manufactures a single product. The standard cost per unit of product is shown below. Direct materials-1 pound plastic at $6 per pound Direct labor-2.00 hours at $12.20 per hour Variable manufacturing overhead Fixed manufacturing overhead Total standard cost per unit $ 6.00 24.40 15.00 13.00 $58.40 The predetermined manufacturing overhead rate is $14 per direct labor hour ($28.00 - 2.00). It was computed from a master manufacturing...