Answer 1
Maintenance cost = $ 153,000
Calculations:
| Machine hours | 60,000 | 90,000 |
| Total cost | $ 174,000 | $ 246,000 |
| Utilities | $ 48,000 | $ 72,000 |
| Supervisor | $ 21,000 | $ 21,000 |
| Maintainence | $ 105,000 | $ 153,000 |
Answer 2
| Lowest range | Highest range | |
| Cost | $ 105,000 | $ 153,000 |
| Hours | $ 60,000 | $ 90,000 |
| As per High Low Method, |
| Variable cost per hour = Change in costs / change in hours |
| Variable cost per hour = (153,000-105,000)/(90,000-60,000) |
| Variable cost per hour = 48,000/30,000 |
| Variable cost per hour = $ 1.6 |
| Fixed Cost = Total Cost - Variable Cost |
| Fixed Cost = Total Cost - (Variable Cost per hour * hours) |
| Fixed Cost = 153,000-(1.6*90,000) |
| Fixed Cost = $ 9000 |
Answer 3
Total cost = ($ 9,000 + $ 21,000)+ ($ 1.6 +0.8)* Hours
Total cost = $ 30,000 + $ 2.4 * Hours
Answer 4
Total cost = $ 30,000 + $ 2.4 * Hours
= $ 30,000 + 2.4 * 75,000
= $ 210,000
In case of any doubt, please comment.
Fol variable and fixed costs!) w Method of cost analysis estimate a cost formula for maintenance...
PROBLEM 3-15 High-Low Method; Predicting Cost [LO1, LO2] Crosshill Company's total overhead costs at various levels of activity are presented below: Total Overhead Cost Month Machine Hours April. ..... May .......... June ........ July................... 70,000 60,000 80,000 90,000 $198,000 $174,000 $222,000 $246,000 Assume that the overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 60,000-machine-hour level of activity in May is as follows: Utilities (variable) .......................... $ 48,000 Supervisory salaries (fixed)... 21,000...
PROBLEM 5A-8 High-Low Method; Predicting Cost LO5-10 Nova Company's total overhead cost at various levels of activity are presented below: Total Overhead Machine- Month Cost Hours April..... May $198,000 $174,000 $222,000 $246,000 70,000 60,000 ... .. June. 80,000 July 90,000 Cost-Volume-Profit Relationships Assume that the total overhead cost above consists of utilities, supervisory salaries, and main- tenance. The breakdown of these costs at the 60,000 machine-hour level of activity is: Utilities (variable).... Supervisory salaries (fixed) Maintenance (mixed).. $ 48,000 21,000...
Problem 5A-8 High-Low Method; Predicting Cost (L05-10) Nova Company's total overhead cost at various levels of activity are presented below: Month April May June July Machine- Hours 51,000 41,000 61,000 71,000 Total Overhead Cost $ 212,630 $ 187,330 $ 237,930 $ 263,230 Assume that the total overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 41,000 machine-hour level of activity is: Utilities (variable) Supervisory salaries (fixed) Maintenance (mixed) Total overhead cost $...
Assume that the total overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 35.000 machine-hour level of activity is: Utilities (variable) Supervisory salaries (fixed) Maintenance (mixed) Total overhead cost $ 45,500 54,000 60,850 $160, 350 Nova Company's management wants to break down the maintenance cost into its variable and fixed cost elements. Required: 1. Estimate how much of the $236,250 of overhead cost in July was maintenance cost. (Hint: to do this,...
Crosshill Company's total overhead costs at various levels of activity are presented below: Month April May June July Machine- Hours 52,000 42,000 62,000 72,000 Total Overhead Cost $204,360 $180,060 $228,660 $252,960 Assume that the overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 42,000-machine-hour level of activity in May is as follows: $ Utilities (variable) Supervisory salaries (fixed) Maintenance (mixed) 54,600 60,000 65,460 Total overhead cost $ 180,060 The company wants to...
Crosshill Company’s total overhead costs at various levels of activity are presented below: Month Machine-Hours Total Overhead Cost April 54,000 $188,180 May 44,000 $163,980 June 64,000 $212,380 July 74,000 $236,580 Assume that the overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 44,000-machine-hour level of activity in May is as follows: Utilities (variable) $ 52,800 Supervisory salaries (fixed) 44,000 Maintenance (mixed) 67,180 Total overhead cost $ 163,980 The...
Crosshill Company’s total overhead costs at various levels of activity are presented below: Month Machine-Hours Total Overhead Cost April 54,000 $188,180 May 44,000 $163,980 June 64,000 $212,380 July 74,000 $236,580 Assume that the overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 44,000-machine-hour level of activity in May is as follows: Utilities (variable) $ 52,800 Supervisory salaries (fixed) 44,000 Maintenance (mixed) 67,180 Total overhead cost $ 163,980 The...
Problem 5A-8 High-Low Method; Predicting Cost (LO5-10] Nova Company's total overhead cost at various levels of activity are presented below: Total Machine- Overhead Month Hours 47,000 37,000 57,000 67,000 Cost $ 190,930 $ 167,030 $ 214,830 $ 238,730 April May June July Assume that the total overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 37,000 machine-hour level of activity is: $ 44,400 Utilities (variable) Supervisory salaries (fixed) Maintenance (mixed) 63,000 59,630...
Crosshill Company's total overhead costs at various levels of activity are presented below: Month April May Machine- Hours 49,000 39,000 59,000 69,000 Total Overhead Cost $210,730 $186,030 $ 235, 430 $260,130 June July Assume that the overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 39,000-machine-hour level of activity in May is as follows: $ Utilities (variable) Supervisory salaries (fixed) Maintenance (mixed) 50, 700 70,000 65,330 Total overhead cost $ 186,030 The...
Crosshill Company's total overhead costs at various levels of activity are presented below. Month pril May Machine Hours 19,000 39,000 59,000 69.000 Total Overhead Cost $191,860 $164,460 $219, 260 $246,660 July Assume that the overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 39,000 machine-hour level of activity in May is as follows: Utilities variable) Supervisory salaries (fixed) Maintenance mixed) 62.400 43.000 59,060 nces Total overhead coat $164.960 The company wants to...