Question

DataSpan, Inc., automated Its plant at the start of the current year and Installed a flexible manufacturing system. The compa

Required 1 Required 2 Required 3 Evaluate the companys performance over the last four months. (Indicate the effect of each t

Required 1 Required 2 Required 3 3-a. (Month 5) Refer to the move time, process time, and so forth, given for month 4. Assume

0 0
Add a comment Improve this question Transcribed image text
Answer #1
Ans. Throughput Time Delivery Cycle Manufacturing Cycle
Months Time Efficiency
1 9.8 days 27.8 days 36.7%
2 10.2 days 29.9 days 33.33%
3 11 days 34 days 29.09%
4 11.6 days 36.4 days 25.86%
*Calculations for 1 a, b, c are shown below:
Ans. 1 a Throughput time = Move time + Process time + Queue time + Inspection time
Months
Particulars 1 2 3 4
Move time per unit 0.9 0.5 0.6 0.6
Process time per unit 3.6 3.4 3.2 3
Inspection time per unit 0.6 0.8 0.8 0.6
Queue time 4.7 5.5 6.4 7.4
Total (Throughput Time) 9.8 days 10.2 days 11 days 11.6 days
Ans. 1 b Manufacturing cycle efficiency = Process time or value added time / Throughput time * 100
Months
1 3.6 / 9.8 * 100 36.7%
2 3.4 / 10.2 * 100 33.33%
3 3.2 / 11 * 100 29.09%
4 3 / 11.6 * 100 25.86%
Ans. 1 c Delivery cycle time = Throughput time + Wait time per order before start of production
Months
1 9.8 + 18 27.8 days
2 10.2 + 19.7 29.9 days
3 11 + 23 34 days
4 11.6 + 24.8 36.4 days
Ans. 2 The Throughput time measure displays Favorable trends
Delivery cycle time - days measure displays Favorable trends
Manufacturing cycle efficiency - days measure displays Unfavorable trends
*Throughput time and delivery cylce time are increasing every month, so these are favorable trends and
Manufacturing cycle efficiency is an unfavorable trend as it is decreasing every month.
Ans. 3 Month 5 Month 6
Throughput time 4.2 days 3.6 days
Manufacturing cycle efficiency (MCE) 71.43% 83.33%
*Calculations:
Ans. 3 a Month 5 :
Throughput time:
Move time per unit 0.6
Process time per unit 3
Inspection time per unit 0.6
Total 4.2 days
MCE (manufacturing cycle efficiency) = Process time / Throughput time * 100
3 / 4.2 * 100
71.43%
Ans. 3 b Month 6 :
Throughput time:
Move time per unit 0.6
Process time per unit 3
Total 3.6 days
MCE (manufacturing cycle efficiency) = Process time / Throughput time * 100
3 / 3.6 * 100
83.33%
Add a comment
Know the answer?
Add Answer to:
DataSpan, Inc., automated Its plant at the start of the current year and Installed a flexible...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • DataSpan, Inc., automated its plant at the start of the current year and installed a flexible...

    DataSpan, Inc., automated its plant at the start of the current year and installed a flexible manufacturing system. The company is also evaluating its suppliers and moving toward Lean Production. Many adjustment problems have been encountered, including problems relating to performance measurement. After much study, the company has decided to use the performance measures below, and it has gathered data relating to these measures for the first four months of operations. Month Throughput time (days) Delivery cycle time (days) Manufacturing...

  • DataSpan, Inc., automated its plant at the start of the current year and installed a flexible...

    DataSpan, Inc., automated its plant at the start of the current year and installed a flexible manufacturing system. The company is also evaluating its suppliers and moving toward Lean Production. Many adjustment problems have been encountered, including problems relating to performance measurement. After much study, the company has decided to use the performance measures below, and it has gathered data relating to these measures for the first four months of operations, Month 34 Throughput time (days) Delivery cycle time (days)...

  • DataSpan, Inc., automated its plant at the start of the current year and installed a flexible...

    DataSpan, Inc., automated its plant at the start of the current year and installed a flexible manufacturing system. The company is also evaluating its suppliers and moving toward Lean Production. Many adjustment problems have been encountered, including problems relating to performance measurement. After much study, the company has decided to use the performance measures below, and it has gathered data relating to these measures for the first four months of operations. Month 2 1 Throughput time (days) Delivery cycle time...

  • DataSpan, Inc., automated its plant at the start of the current year and installed a flexible...

    DataSpan, Inc., automated its plant at the start of the current year and installed a flexible manufacturing system. The company is also evaluating its suppliers and moving toward Lean Production. Many adjustment problems have been encountered, including problems relating to performance measurement. After much study, the company has decided to use the performance measures below, and it has gathered data relating to these measures for the first four months of operations. Month 1 2 3 ? Throughput time (days) Delivery...

  • DataSpan, Inc., automated its plant at the start of the current year and installed a flexible...

    DataSpan, Inc., automated its plant at the start of the current year and installed a flexible manufacturing system. The company is also evaluating its suppliers and moving toward Lean Production. Many adjustment problems have been encountered, including problems relating to performance measurement. After much study, the company has decided to use the performance measures below, and it has gathered data relating to these measures for the first four months of operations. Problem 10-14 Measures of Internal Business Process Performance (LO10-3]...

  • DataSpan, Inc., automated its plant at the start of the current year and installed a flexible...

    DataSpan, Inc., automated its plant at the start of the current year and installed a flexible manufacturing system. The company is also evaluating its suppliers and moving toward Lean Production. Many adjustment problems have been encountered, including problems relating to performance measurement. After much study, the company has decided to use the performance measures below, and it has gathered data relating to these measures for the first four months of operations. Month 1 2 3 4 Throughput time (days) ?...

  • DataSpan, Inc., automated its plant at the start of the current year and installed a flexible...

    DataSpan, Inc., automated its plant at the start of the current year and installed a flexible manufacturing system. The company is also evaluating its suppliers and moving toward Lean Production. Many adjustment problems have been encountered, including problems relating to performance measurement. After much study, the company has decided to use the performance measures below, and it has gathered data relating to these measures for the first four months of operations. Month ? Throughput time (days) Delivery cycle time (days)...

  • DataSpan, Inc. automated its plant at the start of the current year and installed a flexible...

    DataSpan, Inc. automated its plant at the start of the current year and installed a flexible manufacturing system. The company is also evaluating its suppliers and moving toward Lean Production. Many adjustment problems have been encountered, including problems relating to performance measurement. After much study, the company has decided to use the performance measures below, and it has gathered data relating to these measures for the first four months of operations. Throughout te (days) Delivery cycle time (days) Manufacturing cycle...

  • DataSpan, Inc., automated its plant at the start of the current year and installed a flexible manufacturing system. The...

    DataSpan, Inc., automated its plant at the start of the current year and installed a flexible manufacturing system. The company is also evaluating its suppliers and moving toward Lean Production. Many adjustment problems have been encountered, including problems relating to performance measurement. After much study, the company has decided to use the performance measures below, and it has gathered data relating to these measures for the first four months of operations. Month 1 2 3 4 Throughput time (days) ?...

  • DataSpan, Inc., automated its plant at the start of the current year and installed a flexible...

    DataSpan, Inc., automated its plant at the start of the current year and installed a flexible manufacturing system. The company is also evaluating its suppliers and moving toward Lean Production. Many adjustment problems have been encountered, including problems relating to performance measurement. After much study, the company has decided to use the performance measures below, and it has gathered data relating to these measures for the first four months of operations. Month 3 2 ? 4 ? ? ? Throughput...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT