Question

American Electronics produces​ Tough-Robot for lawn mowing purposes. The production manager of American Electronics would like...

American Electronics produces​ Tough-Robot for lawn mowing purposes. The production manager of American Electronics would like to create an MRP for their​ Tough-Robot with a minimum cost possible for the plan. The following table show gross requirements of​ Tough-Robot for ten weeks. You are asked to develop a solution using an ordering system that always orders 100 units the week prior to a shortage​ (a fixed order quantity of​ 100) as a Lot Sizing technique. What is the cost of this ordering​ system?     

Period

1

2

3

4

5

6

7

8

9

10

Gross requirements

45

20

40

0

10

40

30

0

30

55

Holding cost = ​$1/unit/week;

setup cost =​ $200​;

lead time = 1 ​week;

beginning inventory = 45 units.

Prepare a net requirements plan ​(enter your responses as whole​ numbers).

Period

1

2

3

4

5

6

7

8

9

10

Gross requirements

45

20

40

0

10

40

30

0

30

55

​On-hand at beginning of period

45

?

?

?

?

?

?

?

?

?

?

​On-hand at end of period

?

?

?

?

?

?

?

?

?

?

Net requirements

?

?

?

?

?

?

?

?

?

?

Order receipt

?

?

?

?

?

?

?

?

?Order release

?

?

?

?

?

?

?

?

?

a.) The holding cost of this ordering system is ​? ​(enter your response as a whole​ number).

b.) The setup cost of this ordering system is ​$? (enter your response as a whole​ number).

c.)The total cost of this ordering system is ​$? ​(enter your response as a whole​ number).

0 0
Add a comment Improve this question Transcribed image text
Answer #1

wem Puriod Cn o 50 30 30 5S equrremen hedule reteipk on hand Net requirements la Eolül-Tec 3stolap1 Plannesl order steceiphs 100 100 planned ordex oreleose 100 inventory on hand is the be ginmning v The inven tory on hand to the next puilod is the e ot puvoah ding vui tried my best please appreciate ??

Add a comment
Know the answer?
Add Answer to:
American Electronics produces​ Tough-Robot for lawn mowing purposes. The production manager of American Electronics would like...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Using gross requirements schedule below, prepare an alternative ordering system that always orders 100 units the...

    Using gross requirements schedule below, prepare an alternative ordering system that always orders 100 units the week prior to a shortage (a fixed order quantity of 100) as a Lot Sizing technique. What is the cost of this ordering system? Period Gross requirements 25 20 50 0 10 40 30 0 30 65 1 2 3 45 6 7 8 9 10 Holding cost $1/unitweek; setup cost $200; lead time 1 week beginning inventory 25 units. Prepare a net requirements...

  • Sigma Electronics produces telephone cameras for cell phone. The production manager would like to create an...

    Sigma Electronics produces telephone cameras for cell phone. The production manager would like to create an MRP for their cell phone cameras with a minimum cost possible. The following table show gross requirements of the product Develop a Part Period Balancing (PPB) solution and calculate the total relevant costs for the MRP. 2 4 8 11 Period Gross requirements 1 20 3 40 5 40 6 60 7 30 9 20 10 70 12 50 Also, for this plan the...

  • Develop a lot-for-lot solution and calculate total relevant costs for the gross requirements in the following table Per...

    Develop a lot-for-lot solution and calculate total relevant costs for the gross requirements in the following table Period 1 23 4 5 6 7 89 10 12 Gross requirements 30 40 40 70 20 10 80 60 Holding cost $1.50/unit/week; setup cost $150; lead time 1 week; beginning inventory 40 Develop a lot-for-lot solution (enter your responses as whole numbers) Period 1 2 3 45 6 7 8 9 10 111 Gross requirements 30 40 40 70 20 10 80...

  • Best-Appliance makes high-powered industrial strength microwave oven and wants to create an MRP for their oven...

    Best-Appliance makes high-powered industrial strength microwave oven and wants to create an MRP for their oven assembly with a minimum cost possible. Following table show gross requirements of their product for twelve weeks. Develop a Part Period Balancing (PPB) solution and calculate the total relevant costs for the plan Week 1 2 3 4 5 6 8 10 11 12 7 Gross requirements 20 40 40 70 30 10 80 40 Also, for this plan the Holding cost $2.50/unit/week; setup...

  • The total cost is $____ )enter your response as a whole number) Develop a lot-for-lot solution and calculate total rele...

    The total cost is $____ )enter your response as a whole number) Develop a lot-for-lot solution and calculate total relevant costs for the gross requirements in the following table*. Period 1 6 11 12 2 4 7 8 10 Gross requirements 30 70 30 10 80 20 30 60 Holding cost= $3.50/unit/week; setup cost = $150; lead time= week; beginning inventory 40. Develop a lot-for-lot solution (enter your responses as whole numbers). Period 1 2 3 6 7 10 12...

  • Problem 14.22 Develop a lot-for-lot solution and calculate total relevant costs for the gross requirements in the follo...

    Problem 14.22 Develop a lot-for-lot solution and calculate total relevant costs for the gross requirements in the following table Period 1 2 3 4 5 6 789 10 11 12 Gross requirements 30 40 40 70 20 10 80 60 Holding cost$1.50unit/week; setup cost $150; lead time 1 week; beginning inventory 40 Develop a lot-for-lot solution (enter your responses as whole numbers). Period 1 2 3 4 5 6 78 9 0 11 12 Gross requirements 40 40 70 20...

  • Best-Appliance makes​ high-powered industrial strength microwave oven and wants to create an MRP for their oven...

    Best-Appliance makes​ high-powered industrial strength microwave oven and wants to create an MRP for their oven assembly with a minimum cost possible. Following table show gross requirements of their product for twelve weeks. Develop a Part Period Balancing​ (PPB) solution and calculate the total relevant costs for the plan.        Week 1 2 3 4 5 6 7 8 9 10 11 12 Gross requirements 20 30 40 60 20 10 80 40 ​Also, for this plan the Holding cost =​$2.50​/unit/week;...

  • 3. Develop a lot-for-lot solution and calculate total relevant costs for the gross requirements in the...

    3. Develop a lot-for-lot solution and calculate total relevant costs for the gross requirements in the following table" Period 1 2 3 4 5 6 789 10 12 Gross requirements20 40 40 70 30 10 70 50 Holding cost- $3.50/unit/week; setup cost $150; lead time 1 week; beginning inventory 40 Develop a lot-for-lot solution (enter your responses as whole numbers) Period Gross 3 4 5 6 9 20 40 40 70 30 10 uirements On-hand at beginning of On-hand at...

  • Develop a lot-for-lot solution and calculate total relevant costs for the gross requirements in the following...

    Develop a lot-for-lot solution and calculate total relevant costs for the gross requirements in the following table*. Period | 1 2 3 4 5 6 7 8 9 10 11 12 Gross requirements | 30 40 30 70 30 20 70 50 *Holding cost = $3.50/unit/week; setup cost = $150; lead time = 1 week; beginning inventory = 40. Develop a lot-for-lot solution (enter your responses as whole numbers). 2 4 8 11 3 40 5 30 6 70 7...

  • What will the total cost be? (nearest whole number) Develop a lot-for-lot solution and calculate total...

    What will the total cost be? (nearest whole number) Develop a lot-for-lot solution and calculate total relevant costs for the gross requirements in the following table". Period 1 2 3 4 5 6 7 8 9 10 11 12 Gross requirements 20 40 40 60 30 10 80 50 "Holding cost = $3.50/unit/week; setup cost = $200; lead time = 1 week; beginning inventory = 40. Develop a lot-for-lot solution (enter your responses as whole numbers). Period 1 2 3...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT