New help filling this out

Stine Company uses a job order cost system. On May 1, the company has a balance in Work in Process Inventory of $4,210 and two jobs in process: Job No. 429 $2,550, and Job No. 430 $1,660. During May, a summary of source documents reveals the following.

Materials Labor Time Tickets Job Number 429 430 Requisition Slips $2,150 3,560 8,150 $2,670 3,830 4,720$11,220 $13,860 1,610 $15,470 General use 920 $12,140

Stine Company applies manufacturing overhead to jobs at an overhead rate of 66% of direct labor cost. Job No. 429 is completed during the month.

Work in Process Inventory

Job Cost Sheets Job Beginning Work Direct Material Direct Labor Manufacturing Overhead in Process Total 430 431

0 0
Add a comment Improve this question Transcribed image text
Answer #1
Work in Process Inventory
May 1 Balance 4210 May 31 8789
May 31 11220
May 31 13860
May 31 9148
May 31 Balance 29649
2
Job No. Beginning Work
in Process
Direct material Direct Labor Manufacturing
Overhead
Total
430 1660 3830 3560 2350 11400
431 0 4720 8150 5379 18249
1660 8550 11710 7729 29649
Note: Cost of Job 429=2550+2670+2150+(2150*66%) = $8789
Add a comment
Know the answer?
Add Answer to:
New help filling this out Stine Company uses a job order cost system. On May 1,...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Stine Company uses a job order cost system. On May 1, the company has a balance...

    Stine Company uses a job order cost system. On May 1, the company has a balance in Work in Process Inventory of $4,240 and two jobs in process: Job No. 429 $2,580, and Job No. 430 $1,660. During May, a summary of source documents reveals the following. Job Number Materials Requisition Slips Labor Time Tickets 429 $3,040 $2,100 430 3,680 3,300 431 4,710 $11,430 8,100 $13,500 General use 940 1,360 $12,370 $14,860 Stine Company applies manufacturing overhead to jobs at...

  • Stine Company uses a job order cost system. On May 1, the company has a balance...

    Stine Company uses a job order cost system. On May 1, the company has a balance in Work in Process Inventory of $4,240 and two jobs in process: Job No. 429 $2,580, and Job No. 430 $1,660. During May, a summary of source documents reveals the following Job Number 429 Materials Requisition Slips $3,040 3.680 4,710 $11.430 940 430 Labor Time Tickets $2,100 3,300 8,100 $13,500 1.360 $14,860 431 General use $12,370 Stine Company applies manufacturing overhead to jobs at...

  • Stine Company uses a job order cost system. On May 1, the company has a balance...

    Stine Company uses a job order cost system. On May 1, the company has a balance in Work in Process Inventory of $3,610 and two jobs in process: Job No. 429 $2,140, and Job No. 430 $1,470. During May, a summary of source documents reveals the following Materials Requisition Slips Labor Time Tickets Job Number 429 430 431 General use $2,940 4,090 4,920 $2,060 3,600 8,060 $11,950 930 $12,880 $13,720 1,590 $15,310 Stine Company applies manufacturing overhead to jobs at...

  • Stine Company uses a job order cost system. On May 1, the company has a balance...

    Stine Company uses a job order cost system. On May 1, the company has a balance in Work in Process Inventory of $3,500 and two jobs in process: Job No. 429 $2,000, and Job No. 430 $1,500. During May, a summary of source documents reveals the following. Job Number Materials Requisition Slips Labor Time Tickets 429 $2,500 $1,900 430 3,500 3,000 431 4,400 $10,400 7,600 $12,500 General use 800 1,200 $11,200 $13,700 Stine Company applies manufacturing overhead to jobs at...

  • E16-2 Stine Company uses a job order cost system. On May 1, the company has a...

    E16-2 Stine Company uses a job order cost system. On May 1, the company has a balance in Work in Process Inventory of $3,500 and two jobs in process: Job No. 429 $2,000, and Job No. 430 $1,500. During May, a summary of source documents reveals the following. Job Number 429 430 431 General use Materials Requisition Slips $2,500 3,500 4,400 $10,400 800 $11,200 Labor Time Tickets $1,900 3,000 7,600 $12,500 1,200 $13,700 Stine Company applies manufacturing overhead to jobs...

  • Exercise 2-2 Stine Company uses a job order cost system. On May 1, the company has...

    Exercise 2-2 Stine Company uses a job order cost system. On May 1, the company has a balance in Work in Process Inventory of $3,920 and two jobs in process: Job No. 429 $2,600, and Job No. 430 $1,320. During May, a summary of source documents reveals the following. Materials Labor Time Job Number Requisition Slips Tickets 429 $3,040 $2,300 430 4,020 3,400 431/ 4,740 $11,800 7,900 $13,600 General use 900 1,310 $12,700 $14,910 Stine Company applies manufacturing overhead to...

  • E2-2 Stine Company uses a job order cost system. On May 1, the company has a...

    E2-2 Stine Company uses a job order cost system. On May 1, the company has a balance Prepare in Work in Process Inventory of $3,500 and two jobs in process: Job No. 429 $2,000, and manugfa Job No. 430 $1,500. During May, a summary of source documents reveals the following. (LO 1, 2 Materials Labor Time Tickets Job Number 429 430 431 General use Requisition Slips $2,500 3,500 4,400 $1,900 3,000 7,600 $10,400 800 $11,200 $12,500 1,200 $13,700 Stine Company...

  • E15.2 (LO 1, 2, 3, 4) Stine Company uses a job order cost system. On May...

    E15.2 (LO 1, 2, 3, 4) Stine Company uses a job order cost system. On May 1, the company has a balance in Work in Process Inventory of $3,500 and two jobs in process: Job No. 429 $2,000, and Job No. 430 $1,500. During May, a summary of source documents reveals the following. Materials Labor Job Number Requisition Slips Time Tickets 429 $2,500 3,500 4,400 $1,900 430 3,000 431 $10,400 $12,500 7,600 General use 800 1,200 $11,200 $13,700 Stine Company...

  • Exercise 15-2 (Part Level Submission) Stine Company uses a job order cost system. On May 1,...

    Exercise 15-2 (Part Level Submission) Stine Company uses a job order cost system. On May 1, the company has a balance in Work in Process Inventory of $3,400 and two jobs in process: Job No. 429 $2,100, and Job No. 430 $1,300. During May, a summary of source documents reveals the following Materials Requisition Slips Labor Time Tickets Job Number 429 430 431 General use $2,000 3,100 7,700 $2,600 3,600 4,500 $10,700 900 $11,600 $12,800 1,300 $14,100 Stine Company applies...

  • Exercise 15-2 Exercise 15-2 Stine Company uses a job order cost system. On May 1, the...

    Exercise 15-2 Exercise 15-2 Stine Company uses a job order cost system. On May 1, the company has a balance in Work in Process Inventory of $4,080 and two jobs in process: Job No. 429 $2,330, and Job No. 430 $1,750. During May, a summary of source documents reveals the following Materials Requisition Slip:s Labor Time Tickets Job Number 429 430 431 General use $2,790 4,080 4,830 $2,130 3,460 8,160 $11,700 960 $12,660 $13,750 1,680 $15,430 Stine Company applies manufacturing...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT