1)Direct materials costs are recorded in the material
requisition form and direct labor costs are recorded in the
Employee time ticket
2)In material requisition form the direct material costs is
recorded and total cost:
=(40*80)+(960*6)
=8960
In employee time ticket the direct labour costs are recorded and
total costs is beloe
Kristine total hours worked=9am to 12.15pm= 3hr 15min and cost is
120 per hour
=(120*3)+(0.25*120)=390
Clarrise total hrs worked=2.15pm to 4.30pm=2hr 15min
=(120*2)+(0.25*120)=270
=390+270=660
KCC Company has incurred the following costs on Job KC123, an order for 40 gearing wheels...
Using Job-Order Costing Documents [LO2 - CC4) Cycle Gear Corporation has incurred the following costs on job W456, an order for 20 special sprockets to be delivered at the end of next month: Direct materials: • On April 10, requisition number 15673 was issued for 40 titanium blanks to be used in the special order. The blanks cost $15 each. • On April 11, requisition number 15678 was issued for 420 hardened nibs also to be used in the special...
Source Documents and Cost Flows in Job-Order Costing In job-order costing, the individual costs of each job must be kept track of separately. The costs of each job are kept track of on a job-order cost sheet. The job-order cost sheets are subsidiary records to the account. Each job order cost sheet includes the unique name assigned to the job (e.g., Smith House for a construction firm, or 2014-001 for the first job of 2014 for a custom framing shop)....
Bonita Company uses a job order cost system. On May 1, the
company has a balance in Work in Process Inventory of $3,890 and
two jobs in process: Job No. 429 $2,540, and Job No. 430 $1,350.
During May, a summary of source documents reveals the following.
Job Number Materials Requisition Slips Labor Time Tickets 429
$2,980 $2,100 430 4,000 3,500 431 4,560 $11,540 7,700 $13,300
General use 900 1,670 $12,440 $14,970 Bonita Company applies
manufacturing overhead to jobs at...
Stine Company uses a job order cost system. On May 1, the company has a balance in Work in Process Inventory of $3,500 and two jobs in process: Job No. 429 $2,000, and Job No. 430 $1,500. During May, a summary of source documents reveals the following. Job Number Materials Requisition Slips Labor Time Tickets 429 $2,500 $1,900 430 3,500 3,000 431 4,400 $10,400 7,600 $12,500 General use 800 1,200 $11,200 $13,700 Stine Company applies manufacturing overhead to jobs at...
E16-2 Stine Company uses a job order cost system. On May 1, the company has a balance in Work in Process Inventory of $3,500 and two jobs in process: Job No. 429 $2,000, and Job No. 430 $1,500. During May, a summary of source documents reveals the following. Job Number 429 430 431 General use Materials Requisition Slips $2,500 3,500 4,400 $10,400 800 $11,200 Labor Time Tickets $1,900 3,000 7,600 $12,500 1,200 $13,700 Stine Company applies manufacturing overhead to jobs...
Stine Company uses a job order cost system. On May 1, the company has a balance in Work in Process Inventory of $3,610 and two jobs in process: Job No. 429 $2,140, and Job No. 430 $1,470. During May, a summary of source documents reveals the following Materials Requisition Slips Labor Time Tickets Job Number 429 430 431 General use $2,940 4,090 4,920 $2,060 3,600 8,060 $11,950 930 $12,880 $13,720 1,590 $15,310 Stine Company applies manufacturing overhead to jobs at...
Exercise 2-2 Stine Company uses a job order cost system. On May 1, the company has a balance in Work in Process Inventory of $3,920 and two jobs in process: Job No. 429 $2,600, and Job No. 430 $1,320. During May, a summary of source documents reveals the following. Materials Labor Time Job Number Requisition Slips Tickets 429 $3,040 $2,300 430 4,020 3,400 431/ 4,740 $11,800 7,900 $13,600 General use 900 1,310 $12,700 $14,910 Stine Company applies manufacturing overhead to...
Milner Manufacturing uses a job-order costing system. On May 1, the company has a balance in Work in Process Inventory of $3,800 and two jobs in process: Job No. 429 $2,120, and Job No. 430 $1,680. During May, a summary of source documents reveals the following: Job Number Labour Time Tickets 429 Materials Requisition Slips $2,350 39 3,830 $2,020 430 3,410 7.720 4.470 431 General use $10,650 1.160 $11.810 $13,150 1,680 $14,830 Milner Manufacturing applies manufacturing overhead to jobs at...
E2-2 Stine Company uses a job order cost system. On May 1, the company has a balance Prepare in Work in Process Inventory of $3,500 and two jobs in process: Job No. 429 $2,000, and manugfa Job No. 430 $1,500. During May, a summary of source documents reveals the following. (LO 1, 2 Materials Labor Time Tickets Job Number 429 430 431 General use Requisition Slips $2,500 3,500 4,400 $1,900 3,000 7,600 $10,400 800 $11,200 $12,500 1,200 $13,700 Stine Company...
Stine Company uses a job order cost system. On May 1, the company has a balance in Work in Process Inventory of $4,240 and two jobs in process: Job No. 429 $2,580, and Job No. 430 $1,660. During May, a summary of source documents reveals the following Job Number 429 Materials Requisition Slips $3,040 3.680 4,710 $11.430 940 430 Labor Time Tickets $2,100 3,300 8,100 $13,500 1.360 $14,860 431 General use $12,370 Stine Company applies manufacturing overhead to jobs at...