Question

of the following is incorrect about variance reports? facilitate management by exception they should only be sent to the top
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Answer 23 - Variance report is sent not only to the top management.

Therefore, the correct answer is option (b).

Answer 24 - In using Variance reports to evaluate cost control, management normally looks into both favourable and unfavourable variances that exceed a predetermined quantity measure such as a percentage or dollar amount.

Therefore, the correct answer is option (d).

Answer 25 - Standard costing system reports both favourable and unfavourable variances. It is incorrect to say that it reports only favourable variances.

Therefore, the correct answer is option (c).

Answer 26 - In a decision to repair, retain or replace equipment, the book value of the old equipment is considered as sunk cost. Because it is not recoverable and is irrelevant.

Therefore, the correct answer is option (b).

Answer 27 - If an unprofitable segment of the company is eliminated, fixed expenses allocated to the eliminated segment will have to be absorbed by other segments. Because fixed cost remains same and the part of the fixed cost which belonged to the eliminated segment will be transferred to other segments.

Therefore, the correct answer is (c).

Answer 28 - Eliminate the segment, net income will be $10000 greater.

If segment is eliminated, loss of $40000 is eliminated ($200000 - $140000 - $100000 = -$40000)

And 50% of fixed costs is also eliminated that is, $50000. So, it is net benefit of $10000.

Therefore, the correct answer is option (b).

Add a comment
Know the answer?
Add Answer to:
of the following is incorrect about variance reports? facilitate management by exception" they should only be...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Which of the following statements concerning performance reports is​ incorrect? A. The activity level used to...

    Which of the following statements concerning performance reports is​ incorrect? A. The activity level used to populate the flexible budget is based on the actual​ “units.” B. The master budget and the flexible budget use the same cost behavior equation to calculate budgeted expenses. C. All unfavorable flexible budget variances should be investigated. D. A favorable sales revenue flexible budget variance would indicate that the actual sales price was higher than the sales price used in the master budget. E....

  • Budgeting and Variance Analysis In an effort to better plan for and control OR costs, SHH management asked Jack to calculate the flexible budget variance (i.e., flexible budget costs - actual costs) f...

    Budgeting and Variance Analysis In an effort to better plan for and control OR costs, SHH management asked Jack to calculate the flexible budget variance (i.e., flexible budget costs - actual costs) for OR nursing costs, including the price variance and efficiency variance. Given that Jack is interested in comparing the reported costs of both systems, he decided to prepare the requested OR variance analysis for both the current cost system and the vital-signs costing system. In addition, Jack chose...

  • Use the following information to answer questions 5 through 8: Actual results Budget data 20,000 units...

    Use the following information to answer questions 5 through 8: Actual results Budget data 20,000 units produced and sold 19,000 units planned $1,806,700 $90 Direct materials: 62,300 units of input purchased and used @ $29 per input unit - 2.575 Direct labor: 51,500 hours used per output unit @ $21.50 per hour Direct materials: 3 units of input allowed per output unit @ $30 per input unit 47,500 Direct labor: 2.5 hours of input allowed per output unit @ $20...

  • 1.Which of the following is true about "management by exception"? It requires managers to investigate all...

    1.Which of the following is true about "management by exception"? It requires managers to investigate all favorable and unfavorable variances. It requires the use of variance analysis. It rarely requires the use of variance analysis. It requires managers to calculate standard costs, but ignore actual costs. None of the answer choices is correct. 2.Which of the following is most likely to cause an unfavorable direct materials quantity variance? Low quality materials increased waste of materials. High quality materials reduced waste...

  • Budgeting and Variance Analysis In an effort to better plan for and control OR costs, SHH...

    Budgeting and Variance Analysis In an effort to better plan for and control OR costs, SHH management asked Jack to calculate the flexible budget variance (i.e., flexible budget costs - actual costs) for OR nursing costs, including the price variance and efficiency variance. Given that Jack is interested in comparing the reported costs of both systems, he decided to prepare the requested OR variance analysis for both the current cost system and the vital-signs costing system. In addition, Jack chose...

  • #3 only. 14-23 Flexible Budgets; Total Operating Income Variance; Breakdown of the Total Operating Income Variance;...

    #3 only. 14-23 Flexible Budgets; Total Operating Income Variance; Breakdown of the Total Operating Income Variance; Spreadsheet Application The following information is available for Brownstone Products Company for the month of July Units Sales revenue Variable manufacturing costs Fixed manufacturing costs Variable selling and administrative expenses Fixed selling and administrative expenses Actual Master Budget 3.800 4,000 $53,200 $60,000 19.000 16,000 16.000 15,000 7,700 8,000 10.000 9,000 Required 1. What was the total operating income variance for July, rounded to the...

  • The management of Shatner Manufacturing Company is trying to decide whetehr to continue manufacturing a part...

    The management of Shatner Manufacturing Company is trying to decide whetehr to continue manufacturing a part or to buy it from an outside supplier. The part, called CISCO. is a component of the company's finished product. The following information was collected from the accounting records and production data for the year ending December 31, 2020. 1. 8000 units of CISCO were produced in the Machining Department 2. Variable manufacturing costs applicable to the production of each CISCO unit were: direct...

  • #4 only. 14-23 Flexible Budgets; Total Operating Income Variance; Breakdown of the Total Operating Income Variance;...

    #4 only. 14-23 Flexible Budgets; Total Operating Income Variance; Breakdown of the Total Operating Income Variance; Spreadsheet Application The following information is available for Brownstone Products Company for the month of July Units Sales revenue Variable manufacturing costs Fixed manufacturing costs Variable selling and administrative expenses Fixed selling and administrative expenses Actual Master Budget 3.800 4,000 $53.200 $60,000 19.000 16,000 16.000 15,000 7.700 8,000 10,000 9,000 Required 1. What was the total operating income variance for July, rounded to the...

  • Current Artempein Progress The management of Ivanhoe Manufacturing Company is trying to decide whether to continue...

    Current Artempein Progress The management of Ivanhoe Manufacturing Company is trying to decide whether to continue manufacturing a part or to buy it from an outside supplier. The part, called CISCO is a component of the company's finished product. The following information was collected from the accounting records and production data for the year ending December 31, 2020 1.8,000 units of CISCO were produced in the Machining Department. 2. Variable manufacturing costs applicable to the production of each CISCO unit...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT