1. SQSP = Standard Cost of Standard Material
2. AQSP = Standard cost of Actual Material
3. AQAP = Actual Cost of Actual Material
Where
SQ = Standard Quantity for Actual Production or output
SP = Standard Price
AQ = Actual Quantity of Materials Consumed
AP = Actual Price
Material price variance =SQSP - AQAP
=500*20*1.35 - 9500*1.38
=13,500 - 13,110
= 390(F)
Material Purchase Price
Variance = AQSP - AQAP
=9,500*1.35 - 9,500*1.38
=12,825 - 13,110
=285 (A)
Material quantity variance= SQSP - AQSP
=500*20*1.35 - 9500*1.35
=13,500- 22,825
=675 (F)
1.SRSH = Standard Cost of Standard Labour
2. SRAH = Standard Cost of Actual Labour
3. ARAH = Actual Cost of Labour
Where,
SR = Standard Rate of Labour Per Hour
SH = Standard Hours for Actual Production or output
AH = Actual Hours
AR = Actual Rate of Labour per Hour
Labour Rate Variance =SRAH - ARAH
=9*2100 - 9.15*2100
=18,900 -19,215
=315 (A)
Labour efficiency variance= SRSH - SRAH
=9*4*500 - 9*2100
=18,000 - 18,900
=900(A)
The current response is incorrect (math is right, equations are wrong). It's misuing material used with martial purchased. Be sure to check your formuals
During May. Joliet Fabrics Corporation manufactured 500 units of a special multilayer fabric with the trade...
During May, Joliet Fabrics Corporation manufactured 560 units of a special multilayer fabric with the trade name Stylex. The following information from the Stylex production department also pertains to May. Direct material purchased: 18,600 yards at $1.44 per yard Direct material used: 10,100 yards at $1.44 per yard Direct labor: 2,700 hours at $9.21 per hour $ 26,784 14,544 24,867 The standard prime costs for one unit of Stylex are as follows: Direct material: 20 yards at $1.41 per yard...
During May, Joliet Fabrics Corporation manufactured 570 units of a special multilayer fabric with the trade name Stylex. The following information from the Stylex production department also pertains to May. Direct material purchased: 18,700 yards at $1.45 per yard Direct material used: 10,200 yards at $1.45 per yard Direct labor: 2,800 hours at $9.22 per hour $ 27,115 14,790 25,816 The standard prime costs for one unit of Stylex are as follows: Direct material: 20 yards at $1.42 per yard...
During May, Joliet Fabrics Corporation manufactured 600 units of a special multilayer fabric with the trade name Stylex. The following information from the Stylex production department also pertains to May. Direct material purchased: 19,000 yards at $1.48 per yard Direct material used: 10,500 yards at $1.48 per yard Direct labor: 3,100 hours at $9.25 per hour $ 28,120 15,540 28,675 The standard prime costs for one unit of Stylex are as follows Direct material: 20 yards at $1.45 per yard...
During May, Joliet Fabrics Corporation manufactured 650 units of
a special multilayer fabric with the trade name Stylex. The
following information from the Stylex production department also
pertains to May.
Direct material purchased: 19,500 yards at $1.53 per yard
$
29,835
Direct material used: 11,000 yards at $1.53 per yard
16,830
Direct labor: 3,600 hours at $9.30 per hour
33,480
The standard prime costs for one unit of Stylex are as follows:
Direct material: 20 yards at $1.50 per yard...
Part 1, 2, & 3
Check my work During May. Joliet Fabrics Corporation manuf nformation from the Stylex production department also pertains t octured 620 unts floyer fabric with the trade name Stylex The tollowing Direet material purchased: 19,200 yards at $1.50 per yard Direct material used: 10,700 yards at $1.50 per yard Direct labor: 3,300 hours at $9.27 per hour $ 28,800 16,050 30,591 The standard prime costs for one unit of Stylex are as follows Direct material: 20...
question 3&4
French Co. makes berets out of a special dyed wool fabric. During the month, the company made 12,000 berets using 13,200 decimeters of fabric. The fabric cost 522,720 Euros. According to company standards, each beret requires 1.2 decimeters of fabric at a cost of 36 Euros per decimeter. Find a) actual price of fabric per decimeter; b) standard quantity given the number of berets produced; c) amount of material price variance; d) amount of material quantity (efficiency) variance...
Exercise 4 French Co. makes berets out of a special dyed wool fabric. During the month, the company made 8000 berets using 8800 decimeters of fabric. The fabric cost 232320 Euros. According to company standards, each beret requires 1.2 decimeters of fabric at a cost of 24 Euros per decimeter What is the actual price of fabric per decimeter? х What is the standard quantity given the number of berets produced? X What is the amount of material pricévariance? X...
Please complete fully, thanks
i Data Table Kimartin Fabrics manufactures a specialty monogrammed blanket. The following are the cost standards for this blanket (Click the icon to view the standards.) Actual results from last month's production of 2,200 blankets are as follows: (Click the icon to view the actual results.) Direct materials (fabric) ............ Direct labor.... .... ....4.0 yards per blanket at $9.50 per yard ...... 1 direct labor hours per blanket at $11.00 per hour . Read the innents...
Grand Guard, which used a standard cost accounting system, manufactured 130.000 boat fenders during the year using 1.130 000 eet of extruded vinyl purchased at $1.50 per foot. Production required 4,000 direct labor hours that cost $15.50 per hour. The materials standard was 6 feet of vinyl per fender at a standard cost of $150 per foot. The labor standard was 0.025 direct labor hour per fender at a standard cost of $14.50 per hour Read More Requirement 1. Compute...
Question 14 Partially correct Mark 0.62 out of 1.00 P Hag question Variance Computations and Explanations Outdoor Company manufactures camping tents from a lightweight synthetic fabric. Each tent has a standard materials cost of $21, consisting of 4 yards of fabricat $5.25 per yard. The standards call for 2 hours of assembly at $10 per hour. The following data were recorded for October, the first month of operations: Fabric purchased 0,000 yards x 55.00 per yard Fabric used in production...