
The requirement is included there but nonetheless, here they are below. Thank ms
Requirement
(a) Calculate the overhead rates and product unit costs for X, Y
and Z under the existing costing
system.
3 Marks
(b) Using the information provided, decide on the most appropriate
cost drivers and allocate the overhead costs accordingly. Calculate
product costs for the three products using activity based costing
methods to allocate overheads.
12 Marks
(c) Critically evaluate activity based costing approaches for
allocating overheads.
| Existing Cost sheets | ||||||
| Particulars | X | Y | Z | Total | ||
| Production QTY | 7,500 | 12,500 | 4,000 | |||
| Sales Value (Rs.) | 3,52,500 | 10,00,000 | 2,72,000 | 16,24,500 | ||
| Costs | ||||||
| Material | -1,35,000 | -3,12,500 | -64,000 | -5,11,500 | ||
| Labour | -30,000 | -1,00,000 | -25,600 | -1,55,600 | ||
| Overheads (in ratio of labour cost) | -1,38,565 | -4,61,882 | -1,18,242 | -7,18,688 | ||
| Total Costs | -3,03,565 | -8,74,382 | -2,07,842 | -13,85,788 | ||
| Profits | 48,935 | 1,25,618 | 64,158 | 2,38,712 | ||
| Ohds rates - existing | 18.48 | 36.95 | 29.56 | |||
| Revised Cost Sheets | ||||||
| Particulars | X | Y | Z | Total | ||
| Production QTY | 7,500 | 12,500 | 4,000 | |||
| Sales Value (Rs.) | 3,52,500 | 10,00,000 | 2,72,000 | 16,24,500 | ||
| Costs | ||||||
| Material | -1,35,000 | -3,12,500 | -64,000 | -5,11,500 | ||
| Labour | -30,000 | -1,00,000 | -25,600 | -1,55,600 | ||
| Overheads (Note 1 below) | -1,76,180 | -3,13,003 | -2,29,506 | -7,18,688 | ||
| Total Costs | -3,41,180 | -7,25,503 | -3,19,106 | -13,85,788 | ||
| Profits | 11,320 | 2,74,497 | -47,106 | 2,38,712 | ||
| Note 1 - Allocation of ohds | ||||||
| Particulars | X | Y | Z | Total | Basis of allocation | |
| Mat rec and Handling cost | 7,595 | 47,468 | 94,937 | 1,50,000 | No. of Material Movement | |
| Mach Main and Depr | 1,35,417 | 2,25,694 | 28,889 | 3,90,000 | Machine hours | |
| Set up | 1,168 | 5,840 | 11,680 | 18,688 | No. of setups | |
| Engineering Cost | 30,000 | 20,000 | 50,000 | 1,00,000 | Eng % | |
| Packaging | 2,000 | 14,000 | 44,000 | 60,000 | No. of packages | |
| 1,76,180 | 3,13,003 | 2,29,506 | ||||
| Ohd rates new | 23.49 | 25.04 | 57.38 | |||
| Ohd rates old | 18.48 | 36.95 | 29.56 | |||
| Evaluation | ||||||
| Activity based costing give true pictures of performace of various products and their costs. | ||||||
| It helps in making correct decisions based on correct information. | ||||||
| Under existing costing, all the products are profitable, hence the company is doing good. | ||||||
| However, as per ABC, product Z is in loss and cost cutting measures are required for sustainability. | ||||||
The requirement is included there but nonetheless, here they are below. Thank ms Requirement (a) Calculate...
Question 2 Grafton Ltd produces three products: X, Y and Z. The company has been using a single direct labour cost percentage to allocate overhead costs to products. Recently, managers of Grafton have noticed that, due to increasing overbeads and loss of market share, the current costing system is in need of replacement. A specific team has been charged with the responsibility of developing a new system of costing based on activities. Production information is as follows: Production volume Selling...
Bonne Nuit Ltd manufacture and sell top quality beds and mattresses. In the mattresses department, Bonne Nuit make pocket sprung, foam and latex mattresses. In the past, they have used absorption costing system to allocate overhead costs to their products, with labour hours as the allocation base. The following information relates to the production and sale of the three mattresses.Pocket sprungFoamLatexSelling price per unit£1,000£750£2,150Direct material cost per unit£238.50£156£219.60Direct labour cost per unit£90£60£150Direct labour hours to make one unit8610Annual production (units)1,4402,2961,400Number...
Krypton Ltd.’s budgeted information relating to the manufacture of two of its products is presented below: # of times driver used Activity Cost Driver Product A Product B Setup $56501 # of batches 30 10 Engineering $121204 # of engineering hours 6657 9224 Machine Maintenance $89140 # of machine hours 7000 12000 Direct labour cost $11/hour $352180 $528909 Direct materials $126718 $96026 What would be the pre-determined overhead rate under a traditional costing model, with overhead allocated based on direct...
2 sweredthe company has budgeted to produce 1718 units of one of its products. Each unit requires 2 hours of direct labour ut of Waymire Ltd. currently uses a traditional costing system based on direct labour hours to allocate overhead. This year For the coming year, the company is considering changing to an activity based costing system by allocating overhead based on 3 activities. The following are the activities, budgeted total cost and cost drivers per activity for the upcoming...
The Gadget Co produces three products, A, B and C, all made from the same material. Until now, it has used traditional absorption costing to allocate overheads to its products. The company is now considering an activity-based costing system in the hope that it will improve profitability. Information for the three products for the last year is as follows: A B C Production and sales volumes (units) 15,000 12,000 18,000 Selling price per unit $7.50 $12 $13 Raw material usage...
Please answer all parts
2. Hearts plc currently uses an absorption costing model to allocate overheads to its three products X, Y and Z. It is currently considering whether an activity-based costing model might provide more accurate cost information and, as a result, allow the company to regain its previous market position. The production overheads for the year ended 31 March 2017 were as follows: Machine set up costs £26,550 Machine running costs £66,400 Procurement costs 4 Delivery costs £48,000...
$ Additional ABC Problems 1. Activity-Based versus Traditional Costing Maglie Company manufactures two video game consoles: handheld and home. The handheld consoles are smaller and less expensive than the home consoles. Management believes that the accounting system is not accurately allocating costs to products and has asked you to investigate if there is a cost allocation problem. You find that manufacturing overhead costs are currently assigned to products based on their direct labor costs. For your investigation, you have data...
Carolina Industries manufactures two products, Product C and Product D. The company estimated it would incur $ 160,790 in manufacturing overhead costs during the current period. Overhead currently is applied to the products on the basis of direct labour hours. Data concerning the current period's operations appear below:Required:a) Compute the predetermined overhead rate under the current method, and determine the unit product cost of each product for the current year. (8 Marks)b) The company is considering using an activity-based costing...
Question 1 Goodie Inc. manufactures premium quality industrial components. The company adopts job order costing and uses normal costing with activity-based costing to allocate its manufacturing overhead. The annual total overhead costs for the year is broken down into activity cost pools and their respective cost drivers for each cost pool are tabled below. Budgeted Cost (S) Cost Driver Budgeted Activity Overhead Cost Pool Setup Costs Purchasing Costs 240 2,000 60,000 Number of Setups 40,000 Number of Purchases 120,000 Maintenance...
Use the information provided below to calculate the unit overheads cost using Activity Based Costing. INFORMATION The output of Project K of Turbo Limited is Product A and Product B and the company is keen on applying the principles of ABC costing. Relevant information pertaining to the two products for a given period appear below: Product A Product B Output in units 240 180 Machine hours per unit 7 5 Direct materials R100 R80 Direct labour cost per unit R49...