In January, 2018, Fox Co. signed a 2-year contract to build a bridge for the City of Philadelphia for $12,000,000. By the end
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Computation of Gross profit recognised in year 2019 as per completed contract method:

Gross profit = Contract Revenue - Total cost

Total cost = $3000000 + $6375000 = $9375000

Contract Revenue = $12000000

Gross profit = $12000000 - $9375000

= $2625000.

Add a comment
Know the answer?
Add Answer to:
In January, 2018, Fox Co. signed a 2-year contract to build a bridge for the City...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a...

    On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,000,000. During 2018, costs of $2,000,000 were incurred, with estimated costs of $4,000,000 yet to be incurred. Billings of $2,500,000 were sent, and cash collected was $2,250,000. In 2019, costs incurred were $2,500,000 with remaining costs estimated to be $3,600,000. 2019 billings were $2,750,000, and $2,475,000 cash was collected. The project was completed in 2020 after additional costs of...

  • On February 1, 2016, Arrow Construction Company entered into a three-year construction contract to build a...

    On February 1, 2016, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,000,000. During 2016, costs of $2,000,000 were incurred with estimated costs of $4,000,000 yet to be incurred. Billings of $2,500,000 were sent, and cash collected was $2,250,000. In 2017, costs incurred were $2,500,000 with remaining costs estimated to be $3,600,000. 2017 billings were $2,750,000, and $2,475,000 cash was collected. The project was completed in 2018 after additional costs of...

  • Tullis Construction enters into a long-term fixed price contract to build an office tower for $10,600,000....

    Tullis Construction enters into a long-term fixed price contract to build an office tower for $10,600,000. In the first year of the contract Tullis incurs $1,600,000 of cost and the engineers determined that the remaining costs to complete are $4,800,000. Tullis billed $3,600,000 in year 1 and collected $3,500,000 by the end of the end of the year. How much gross profit should Tullis recognize in Year 1 assuming the use of the percentage-of-completion method? 18. Tullis Construction enters into...

  • On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,420,000. During 2018, costs of $2,140,000 were incurred with estimat...

    On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,420,000. During 2018, costs of $2,140,000 were incurred with estimated costs of $4,140,000 yet to be incurred. Billings of $2,640,000 were sent, and cash collected was $2,390,000. In 2019, costs incurred were $2,640,000 with remaining costs estimated to be $3,810,000. 2019 billings were $2,890,000 and $2,615,000 cash was collected. The project was completed in 2020 after additional costs of...

  • During year​ 1, Fox Co. started a construction job with a contract price of​ $1,500,000. The...

    During year​ 1, Fox Co. started a construction job with a contract price of​ $1,500,000. The job was completed in year 2 and the company uses the percentage of completion method. The following information is available for year 1 and year​ 2: Year 1 Year 2 Cost incurred to date $350,000 $1,100,000 Estimated cost to complete 650,000 0 Billings to date 300,000 1,100,000 Collections to date 100,000 1,000,000 What amount of gross profit should Fox recognize for this job for...

  • Tullis Construction enters into a long -term fixed price contract to build an office tower for...

    Tullis Construction enters into a long -term fixed price contract to build an office tower for $10,700,000. In the first year of the contract Tullis incurs $2,100,000 of cost and the engineers determined that the remaining costs to complete the project are $4,900,000. Tullis billed $4,000,000 in year 1 and collected $3,500,000 by the end of the end of the year. How much gross profit should Tullis recognize in Year 1 assuming the use of the completed- contract method? OA....

  • On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a...

    On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,450,000. During 2018, costs of $2,180,000 were incurred, with estimated costs of $4,180,000 yet to be incurred. Billings of $2,716,000 were sent, and cash collected was $2,430,000. In 2019, costs incurred were $2,716,000 with remaining costs estimated to be $3,870,000. 2019 billings were $2,966,000, and $2,655,000 cash was collected. The project was completed in 2020 after additional costs of...

  • Instructions On January 2, 2017, TI enters into a contract with Drewry Corp. to build a...

    Instructions On January 2, 2017, TI enters into a contract with Drewry Corp. to build a new piece of equipment. The contract price is $3,200,000, and construction is expected to take 18 months. Drewry is billed and pays $1,600,000 of the contract price on January 2, 2017, and will pay the balance at completion. Tl estimates that the cost of construction will be $2,200,000. Drewry includes two performance bonuses in the contact U.S. Bonus: If the equipment design receives a...

  • Google Fiber signed a contract and hired Patrick Wirelines to build a new data center in...

    Google Fiber signed a contract and hired Patrick Wirelines to build a new data center in Aksarben. They signed a fixed price contract for 80,000. Additional information about the contract is included in the schedule with the problem worksheets. Required 1. Using the Percentage of Completion Method for each year report the amount of Revenue and Gross Profit or Loss that should be recognized 2. Using the Completed Contract Method for each year report the amount of Revenue and Gross...

  • 3. On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,300,000. During 2018, costs of $2,100,000 were incurred...

    3. On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,300,000. During 2018, costs of $2,100,000 were incurred with estimated costs of $4,100,000 yet to be incurred. Billings of $2,600,000 were sent, and cash collected was $2,350,000. In 2019, costs incurred were $2,600,000 with remaining costs estimated to be $3,750,000. 2019 billings were $2,850,000 and $2,575,000 cash was collected. The project was completed in 2020 after additional costs...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT