| a | IRR | 9.70% |
| b | NPV | -52.59 |
| c | Payback | 2.5 |
d: The project should be rejected since NPV is negative.
Workings
| Year | Initial cost | cumulative CF |
| 0 | -10000 | -10000 |
| 1 | 4000 | -6000.00 |
| 2 | 4000 | -2000.00 |
| 3 | 4000 | 2000.00 |
Payback = Year in which Cumulative CF is last negative -(Last negative cumulative CF/ CF of next year

2. A firm has well spend -10,000 today for a project. The after tax cash flow...
Given the following after-tax cash flow on a new toy for Tyler's Toys, find the project's payback period, NPV, and IRR. The appropriate discount rate for the project is 9%. If the cutoff period is 6 years for major projects, determine whether management will accept or reject the project under the three different decision models. Initial cash outflow: $12,800,000 Years one through four cash inflow: $3,200,000 each year Year five cash outflow: $1,280,000 Years six through eight cash inflow: $548,667...
A project that costs $1 million will yield annual after-tax operating cash flow (including depreciation tax shields) of $500,000 for the next five years. The firm has a D/E ratio of 0.5 and after-tax cost of equity and debt of 20% and 10%, respectively. As this project is slightly riskier than the firm's normal operations, it is decided that an adjustment factor of +3% will be added to the discount rate for the project. What is this project's NPV?
A firm with a 14% WACC is evaluating two projects for this year's capital budget. After-tax cash flows, including depreciation, are as follows: 0 1 2 3 4 5 Project M -$24,000 $8,000 $8,000 $8,000 $8,000 $8,000 Project N -$72,000 $22,400 $22,400 $22,400 $22,400 $22,400 Assuming the projects are independent, which one(s) would you recommend? -Select-Only Project M would be accepted because NPV(M) > NPV(N).Only Project N would be accepted because NPV(N) > NPV(M).Both projects would be accepted since both...
Please do not work in excel and also please show your calculations. FastTrack Bikes, Inc. is thinking of developing a new composite road bike. Development will take six years and the cost is $200,000 per year. Once in production, the bike is expected to make $300,000 (after expenses) per year for 10 years. The cash inflows begin at the end of year 7. At FastTrack, there is a difference of opinion as to the "best" decision rule to use. The...
A firm with a 14% WACC is evaluating two projects for this year's capital budget. After-tax cash flows, including depreciation, are as follows: 0 1 2 3 4 5 Project M -$15,000 $5,000 $5,000 $5,000 $5,000 $5,000 Project N -$45,000 $14,000 $14,000 $14,000 $14,000 $14,000 Calculate NPV for each project. Do not round intermediate calculations. Round your answers to the nearest cent. Project M: $ Project N: $ Calculate IRR for each project. Do not round intermediate calculations. Round your answers to...
A firm with a 14% WACC is evaluating two projects for this year's capital budget. After-tax cash flows, including depreciation, are as follows: 0 1 2 3 4 5 Project M -$24,000 $8,000 $8,000 $8,000 $8,000 $8,000 Project N -$72,000 $22,400 $22,400 $22,400 $22,400 $22,400 Calculate NPV for each project. Round your answers to the nearest cent. Do not round your intermediate calculations. Project M $ Project N $ Calculate IRR for each project. Round your answers to two decimal places. Do...
A firm with a 13% WACC is evaluating two projects for this year's capital budget. After-tax cash flows, including depreciation, are as follows: 0 1 2 3 4 5 Project M -$21,000 $7,000 $7,000 $7,000 $7,000 $7,000 Project N -$63,000 $19,600 $19,600 $19,600 $19,600 $19,600 Calculate NPV for each project. Round your answers to the nearest cent. Do not round your intermediate calculations. Project M $ Project N $ Calculate IRR for each project. Round your answers to two decimal places. Do...
A firm with a 13% WACC is evaluating two projects for this year's capital budget. After-tax cash flows, including depreciation, are as follows: 0 1 2 3 4 5 Project M $(21,000) $7,000 $7,000 $7,000 $7,000 $7,000 Project N $(63,000) $19,600 $19,600 $19,600 $19,600 $19,600 Calculate NPV for each project. Round your answers to the nearest cent. Do not round your intermediate calculations. Project M $ Project N $ Calculate IRR for each project. Round your answers to two decimal places. Do...
Please show work, don't give me an excel based response, thank you! Consider a capital expenditure project to purchase and install new equipment with an initial cash outlay of $25,000. The project is expected to generate net after-tax cash flows each year of $6800 for ten years, and at the end of the project, a one-time after-tax cash flow of $11,000 is expected. The firm has a weighted average cost of capital of 12 percent and requires a 3-year payback...
6. Given the following, what is the after-tax cash flow? Assume No Cap. Ex and no principal payments Cost of goods 100 Depreciation and Amortization 35 Revenues 150 Selling, General, and Admin Exp 5 Tax rate 30% After cash flow = Use this data for the next two problems Sales $100.00 COGS 0.2 General and Admin $15.00 Depreciation $35.00 Interest Expense $35.00 Tax rate 0.25 7. Is the company profitable and by how much? (yes/ no) 8. Does the company...