Answer:-
a) Balance in work in progress Inventory on January 31 are as follows :-
In the above information it was given that only job H21 was not completed and all job was completed so work in progress balance is calculated for H21 Job .
| Job H21 | |
| Manufacturing cost on Dec.31 | $4,000 |
| Manufacturing cost in January : | |
| Direct Material | $8,000 |
| Direct Labour | $14,000 |
| Manufacturing overhead | $21,000 |
| Work in progress inventory Balance on January 31 | $47,000 |
b) Balance in Finished Goods Inventory on January 1 is as follows :-
In the following information it was given that only H20 job is completed on December and Job is completed at January .Thus ,we calculate the balance of finished goods inventory Balance of H20 job.
Finished goods inventory Balance of H20 job is $18,000
c) Total value of applied overhead in January = Manufacturing overhead of Job H21 + Manufacturing overhead of Job H22 + Manufacturing overhead of H23
Total value of applied overhead in January = $21,000 + $1,500 + $7,500
Total value of Applied overhead in January = $30,000
c) Actual overhead cost for January = $32,500
Applied overhead = $30,000
It seems that the overhead cost is underapplied as Actual overhead cost is more than applied overhead cost for January.Thus ,the correct answer is Underapplied
By How much = $32,500 - $30,000 = $2,500
As HOMEWORKLIB RULES rule,we only give answer to first four sub part . For this reason I give the answer to (e) part but not explaining it.
(e) When Subatomic assigns overapplied or underapplied to cost of goods sold,then the amount Increase the value of Cost of Goods in January.
Question 1 (9 marks - suggested time 16 minutes) Sheldon and Leonard recently opened their company...
Question 5 (7 marks, suggested time 10 minutes) The following information was obtained from the job order cost system of Leonard Company for jobs worked on during September 2019: 2.150 Job Number Direct Materials Direct Labour Applied Overhead Total Cost 08.09 $264 5365 SS11 S1,140 08-12 172 2 40 336 09.01 365 520 728 11.613 09.02 2.180 1.825 2355 6.560 09-03 374 740 1016 1.820 980 09.05 R37 640 2.373 09.06 289 720 1.008 2017 09-07 351 470 658 1.479...
Dreckman Inc, uses a job order costing system in which any underappiled or overapplied overhead is closed to cost of goods sold at the end of the month. In August the company completed job M27K that consisted of 17000 units of one of the company's standard products. No other jobs were in process during the month The total manufacturing cost for job M27K according to its job cost sheet was 51118.600,hence the per unit product cost is $65.80. During the...
Abramov Inc. uses a job-order costing system in which any underapplied or overapplied overhead is closed to cost of goods sold at the end of the month. In May the company completed job N29W that consisted of 37,625 units of one of the company's standard products. No other jobs were in process during the month. The job cost sheet for job N29W shows that the job's total cost was $1,640,450. During the month, the actual manufacturing overhead cost incurred was...
The Modern Company builds kitchen cabinets. On January 1, 2019, one job (D42) was in progress. The order is from Dallas Apartment Corporation and was begun on December 21, 2018. Costs accumulated to date on that job are materials, $1,874; labor, $1,200; and overhead, $480. During January, the following costs were incurred in production work on Job D42 and on Jobs J01 and J02, which were started on January 5, 2019: Materials Labor Overhead Quantity Job D42 $ 540 $...
7) Molzahn Corporation is a manufacturer that uses job-order costing. The company closes out any overapplied or underapplied overhead to Cost of Goods Sold at the end of the year. The company has supplied the following data for the just completed year: Estimated total manufacturing overhead at the beginning 5481,250 of the year Estimated direct labor-hours at the beginning of the year 35.000 direct labor hours Results of operations: Actual direct labor-hours 40,000 direct labor-hours Manufacturing overhead: Indirect labor cost...
2. Warden Inc. uses a job-order costing system in which any underapplied or overapplied overhead is closed out to cost of goods sold at the end of the month. The company's cost of goods manufactured for March was $152,000 and its beginning and ending inventories were: Inventories: Beginning Ending Work in process ..... $20,000 $14,000 Finished goods ....... $45,000 $29,000 During the month, the manufacturing overhead cost incurred was $59,000 and the manufacturing overhead cost applied was $63,000. Required: Determine...
QUESTION 6 25 points Shatrau Inc., which uses job-order costing, has provided the following data for December: Direct materials ....... Direct labor cost ....... Manufacturing overhead cost incurred..... Manufacturing overhead cost applied ....... $32.000 $45,000 $42.000 $45,000 Inventories: Work in process ..... Finished goods ....... Beginning $24,000 $35,000 Ending $14,000 $48,000 Required: Determine the unadjusted cost of goods sold (in other words, the cost of goods sold before adjusting for any underapplied or overapplied overhead) for December. Show your work!
Luzadis Company makes furniture using the latest automated technology. The company uses a job-order costing system and applies manufacturing overhead cost to products on the basis of machine-hours. The predetermined overhead rate was based on a cost formula that estimates $1,615,000 of total manufacturing overhead for an estimated activity level of 85,000 machine-hours. During the year, a large quantity of furniture on the market resulted in cutting back production and a buildup of furniture in the company's warehouse. The company's...
Luzadis Company makes furniture using the latest automated technology. The company uses a job-order costing system and applies manufacturing overhead cost to products on the basis of machine-hours. The predetermined overhead rate was based on a cost formula that estimates $765,000 of total manufacturing overhead for an estimated activity level of 85,000 machine-hours. During the year, a large quantity of furniture on the market resulted in cutting back production and a buildup of furniture in the company’s warehouse. The company’s...
Luzadis Company makes furniture using the latest automated technology. The company uses a job-order costing system and applies manufacturing overhead cost to products on the basis of machine-hours. The predetermined overhead rate was based on a cost formula that estimates $560,000 of total manufacturing overhead for an estimated activity level of 70,000 machine-hours. During the year, a large quantity of furniture on the market resulted in cutting back production and a buildup of furniture in the company's warehouse. The company's...