Question













Problem 3: A potential CB project has the following cash flows: CFO = -$500, CF1 = $300, CF2 = $200, CF3 = $150. WACC = 6%. C
0 0
Add a comment Improve this question Transcribed image text
Answer #1

NPV is sum of present value of all cash flows.              
Present value of cash flows = cash flows * PVF              
              
PVF formula = 1/(1+Discount rate)^period              
For year 1, PVF = 1/(1+6%)^1=   0.9433962264          
For year 2, PVF = 1/(1+6%)^2=   0.88999644          
and so on.              
Project payback period is time period required to recover the cost of an investment. In other words, how long it will take to pay the investment back.              
              
              
For payback We will calculate Cumulative present value of cash flow              
Year   cash inflows   PVF@6%   PV of cash flows   Cumulative cash inflows
year 0   -500   1   -500   -500
Year 1   300   0.9433962264   283.0188679   -200
Year 2   200   0.88999644   177.999288   0
Year 3   150   0.839619283   125.9428925   150
              
              
NPV=           86.96104837  
              
Payback year = year before positive cumulative cash flow + (cumulative cash flow to make cum. cash flow to 0/Cash flow of first positive cumulative CF)              
   2 +0/0          
              
Payback period   2   years      
              
IRR =    16.46%          
              
IRR function = irr(CF0:CF13)              
              
NPV is positive and IRR is greater than 6%, so accept the project               
              
              

Add a comment
Know the answer?
Add Answer to:
Problem 3: A potential CB project has the following cash flows: CFO = -$500, CF1 =...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • You work as a financial analyst for the CFO of a Fortune 500 company. You are...

    You work as a financial analyst for the CFO of a Fortune 500 company. You are have been asked to consider the following cash flows (in millions (m)) from two mutually exclusive capital budgeting projects. If the firm's WACC is 14%, find the NPV and IRR and select which one(s) you would choose. Project 1: CFO -6m CF1 -2m CF2 = 2m CF3 = 2m CF4-2m CF5 = 2m Project 2: CFO = -18m CF1-5.6m CF2 = 5.6m CF3-5.6m CF4-5.6m...

  • Problem 1: The cost of debt for firm XYZ is 6%. It's tax rate is 40%....

    Problem 1: The cost of debt for firm XYZ is 6%. It's tax rate is 40%. The cost of retained earnings is 12% and the cost of external common equity is 14%. Retained earnings is $5000. The target capital structure calls for 45% debt and 55% equity. Compute the following: A. Retained earnings break point B. WACC below the RE break point C. WACC above the RE break point Problem 2: The firm referred to in problem #1 has 3...

  • Ellmann Systems is considering a project that has the following cash flow and WACC data. The...

    Ellmann Systems is considering a project that has the following cash flow and WACC data. The WACC is 7%. The CF0 = -$1,000, CF1 = $331, CF2 = $473, and CF3 = $597. What is the project's NPV? Computer Consultants Inc. is considering a project that has the following cash flow and WACC data. The WACC is 10.2%. The CF0 = -$1,000, CF1 = $450, CF2 = $450, and CF3 = $450. What is the project's MIRR? Garner Inc. is...

  • You work as a financial analyst for the CFO of a big company, you have been...

    You work as a financial analyst for the CFO of a big company, you have been asked to consider the following cash flows (Millions) from two mutually exclisive capital budgeting projects. If the firm's WACC is 14%, find the NVP and IRR and select which one you would choose: Project 1: CF0= -6M CF1= 2M . CF2=2m CF3=2M . CF4= 2m Project 2: CF0= -18M CF1= 5.6M CF2= 5.6M CF3= 5.6M CF4= 5.6M CF5= 5.6M Answer Choices: A) Project 1:NVP=...

  • a. Find present value of the following cash flows at 3% rate: CF0 = -1000; CF1...

    a. Find present value of the following cash flows at 3% rate: CF0 = -1000; CF1 = 300; CF2 = 560; CF3 = -90; CF4 = 250. b. What is the future value of these cash flows?

  • 1. Consider two projects with the following (after-tax) cash flows. Project A: CF1 50, CF2 55,...

    1. Consider two projects with the following (after-tax) cash flows. Project A: CF1 50, CF2 55, CF3 85. Project B: CF1 140. Both projects require an initial investment of 100. Assume the cost of capital for both projects is r 5%. (a) Compute NPV and IRR for project A. (b) Compute NPV and IRR for project B. (c) Assume you replicate project B twice, i.e. reinvest 100 in t 1 and t2. Compute the NPV and IRR of the replicated...

  • No need for Explanation The CFO of a major corporation is trying to decide on what...

    No need for Explanation The CFO of a major corporation is trying to decide on what project to pursue using different investment criteria: Net Present Value (NPV), Payback Period, Discounted Payback Period, Internal Rate of Return (IRR), and the Profitability Index (PI). The CFO has four projects to choose between: Project W (which is a strip mine - see problem 6), Project X, Project Y, and Project Z. Additional information about each project is summarized below. You can use the...

  • Geraldine Consultants, Inc. is considering a project that has the following cash flows: Year Cash Flow...

    Geraldine Consultants, Inc. is considering a project that has the following cash flows: Year Cash Flow 0 -$1,000 1 400 2 300 3 500 4 400 The company's WACC is 10%. What are the project's payback, internal rate of return, and net present value? Select one: a. Payback = 2.6, IRR = 21.22%, NPV = $300. b. Payback = 2.4, IRR = 21.22%, NPV = $260. c. Payback = 2.6, IRR = 24.12%, NPV = $300. d. Payback = 2.4,...

  • Consider a project with the following cash flows: CF0=$100 million, CF1=$-60 million, CF2=$-60 million. Should you...

    Consider a project with the following cash flows: CF0=$100 million, CF1=$-60 million, CF2=$-60 million. Should you accept or reject the project if the discount rate is 12%? Group of answer choices Flip a coin Reject Accept

  • NO COMPUTER SOFTWARE IS ALLOWED TO ANSWER THIS QUESTION Consider Table 2 3. Table 2 CF3 CF4 CF2 CF1 CFO Project 75 40 6...

    NO COMPUTER SOFTWARE IS ALLOWED TO ANSWER THIS QUESTION Consider Table 2 3. Table 2 CF3 CF4 CF2 CF1 CFO Project 75 40 60 110 110 (200) (200) (200) 75 40 60 75 40 60 110 0.80 0.24 2.00 3.60 Interest Tax Shield Additional information for all projects 15% Cost (required return) on unlevered equity (%) Cost of debt capital (%) Corporation tax rate (%) Financing of each project: Debt 10% 20% 100 100 Equit alculate the value of project...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT