Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,910,000. The project began in 2021 and was completed in 2022. Data relating to the contract are summarized below:

2021 2022
Costs incurred during the year $ 376,000 $ 2,265,000
Estimated costs to complete as of 12/31 1,504,000 0
Billings during the year 535,000 1,810,000
Cash collections during the year 500,000 1,845,000


Required:
1. Compute the amount of revenue and gross profit or loss to be recognized in 2021 and 2022 assuming Nortel recognizes revenue over time according to percentage of completion.
2. Compute the amount of revenue and gross profit or loss to be recognized in 2021 and 2022 assuming this project does not qualify for revenue recognition over time.
3. Prepare a partial balance sheet to show how the information related to this contract would be presented at the end of 2021 assuming Nortel recognizes revenue over time according to percentage of completion.
4. Prepare a partial balance sheet to show how the information related to this contract would be presented at the end of 2021 assuming this project does not qualify for revenue recognition over time.

1 0
Add a comment Improve this question Transcribed image text
✔ Recommended Answer
Answer #1

1.

Compute revenue as follows:

Particulars 2021 2022
Cost incurred 376000
Estimated cost to complete 1504000
Total cost 1880000
% completion 20%
Total project revenue 2910000
Revenue for the year 582000 2328000

Compute gross profit as follows:

Particulars 2021 2022
Revenue for the year 582000 2328000
Less: Cost incurred -376000 -2265000
Gross profit 206000 63000

2.

When the project does not qualify for revenue recognition over time, the complete revenue is recognized on completion of the project.

Particulars 2021 2022
Revenue for the year - 2910000
Less: Cost incurred -376000 -2265000
Gross profit (loss) -376000 645000

3.

Partial balance sheet if revenue is recognized overtime as follows:

Balance Sheet (Partial)
At December31, 2021
Current assets:
Accounts receivable (535000-500000) 35000
Cost and profit in excess of billings (582000 - 535000) 47000
Current liabilities:

4.

Partial balance sheet if revenue is not recognized overtime as follows:

Balance Sheet (Partial)
At December31, 2021
Current assets:
Accounts receivable(535000-500000) 35000
Current liabilities:
Billings in excess of costs (535000-376000) 159000
Add a comment
Know the answer?
Add Answer to:
Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,910,000. The project began...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Similar Homework Help Questions
  • Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,250,000. The project began...

    Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,250,000. The project began in 2021 and was completed in 2022. Data relating to the contract are summarized below: 2022 $1,720,000 Costs incurred during the year Estimated costs to complete as of 12/31 Billings during the year Cash collections during the year 2021 $ 320,000 1,280,000 405.000 300,000 1.670.000 1,775,000 Required: 1. Compute the amount of revenue and gross profit or loss to be recognized in 2021 and...

  • Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2.250,000. The project began...

    Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2.250,000. The project began in 2021 and was completed in 2022. Data relating to the contract are summarized below: 2022 $1,720,000 Costs incurred during the year Estimated costs to complete as of 12/31 Billings during the year Cash collections during the year 2021 $ 320,000 1,280,000 405,000 300,000 1,670,000 1,775,000 Required: 1. Compute the amount of revenue and gross profit or loss to be recognized in 2021 and...

  • Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,600,000. The project began...

    Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,600,000. The project began in 2021 and was completed in 2022. Data relating to the contract are summarized below: 2021 2022 Costs incurred during the year $ 348,000 $ 1,995,000 Estimated costs to complete as of 12/31 1,392,000 0 Billings during the year 465,000 1,740,000 Cash collections during the year 395,000 1,810,000 Required: 1. Compute the amount of revenue and gross profit or loss to be recognized in...

  • & Exit 6 Check m Assume Nortel Networks contracted to provide a customer with Internet infrastructure...

    & Exit 6 Check m Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,910,000. The project began in 2021 and was completed in 2022. Data relating to the contract are summarized below 2021 S 376,000 $2,265,800 1,504,000 535,000 S00,000 Doints Costs incurred during the year Estinated costs to complete as of 12/31 Billings during the year Cash collections during the year 2022 1,810,000 1.845,c00 eBook Required: 1. Compute the amount of revenue and gross profit or...

  • Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,700,000. The project began...

    Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,700,000. The project began in 2021 and was completed in 2022. Data relating to the contract are summarized below: 2021 2022 Costs incurred during the year $ 356,000 $ 2,135,000 Estimated costs to complete as of 12/31 1,424,000 0 Billings during the year 475,000 1,760,000 Cash collections during the year 415,000 1,820,000 Required: 1. Compute the amount of revenue and gross profit or loss to be recognized in...

  • Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,300,000. The project began...

    Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,300,000. The project began in 2021 and was completed in 2022. Data relating to the contract are summarized below: 2021 2022 Costs incurred during the year $ 324,000 $ 1,800,000 Estimated costs to complete as of 12/31 1,296,000 0 Billings during the year 410,000 1,680,000 Cash collections during the year 310,000 1,780,000 Required: 1. Compute the amount of revenue and gross profit or loss to be recognized in...

  • Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,450,000. The project began...

    Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,450,000. The project began in 2021 and was completed in 2022. Data relating to the contract are summarized below: 2021 2022 Costs incurred during the year $ 336,000 $ 1,870,000 Estimated costs to complete as of 12/31 1,344,000 0 Billings during the year 446,000 1,710,000 Cash collections during the year 361,000 1,795,000 Required: 1. Compute the amount of revenue and gross profit or loss to be recognized in...

  • Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,650,000. The project began...

    Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,650,000. The project began in 2021 and was completed in 2022. Data relating to the contract are summarized below: 2021 2022 Costs incurred during the year $ 352,000 $ 2,025,000 Estimated costs to complete as of 12/31 1,408,000 0 Billings during the year 470,000 1,750,000 Cash collections during the year 405,000 1,815,000 Required: 1. Compute the amount of revenue and gross profit or loss to be recognized in...

  • Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,650,000. The project began...

    Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,650,000. The project began in 2021 and was completed in 2022. Data relating to the contract are summarized below: Costs incurred during the year Estimated costs to complete as of 12/31 Billings during the year Cash collections during the year 2021 $ 352,000 1,408,000 470,000 405,000 2022 $2,025,000 0 1,750,000 1,815,000 Required: 1. Compute the amount of revenue and gross profit or loss to be recognized in 2021...

  • Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,960,000. The project began...

    Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,960,000. The project began in 2021 and was completed in 2022. Data relating to the contract are summarized below: 2022 $2,300,000 Costs incurred during the year Estimated costs to complete as of 12/31 Billings during the year Cash collections during the year 2021 $ 380,000 1,520,000 540,000 510,000 1, 820,000 1,850,000 Required: 1. Compute the amount of revenue and gross profit or loss to be recognized in 2021...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT