(1)initial cost
=acquisition cost+exploration cost+ development cost + present value of restoration cost
=$2million+$1.5million+$5 million
=8.5$ million
restoration cost
| 1 | 1000000 | 10% | 100000 | ||
| 2 | 1400000 | 60 | 840000 | ||
| 3 | 1800000 | 30 | 540000 | ||
| total cost | 1480000 | ||||
present value = 1480000*[1/1.07]5
=0.712986*1480000
=1055220$
initial cost = 1055220+8500000
=9555220$
(2)
2018=1055220*7%*1year =73865$
2019=1129085*7%*1 year =79036$
(3)book value
1055220+73865=1129085 =2018
2019 = 1129085+73865=1202950
(4)book value at 2023
| book value | accretion cost | book value | |
| 2018 | 1055220 | 73865 [1055220*7%] | 1129085 |
| 19 | 1129085 | 79036[1129085*7%] | 1208121 |
| 20 | 1208121 | 84568 | 1292689 |
| 21 | 1292689 | 90488 | 1383177 |
| 22 | 1383177 | 96822 | 14800000 |
gain(Loss) =book value- actual cost
=13700000-14800000
=110000$ Gain
Calegari Mining paid $2 million to obtain the rights to operate a coal mine in Tennessee....
Smithson Mining operates a silver mine in Nevada. Acquisition, exploration, and development costs totaled $6.9 million. After the silver is extracted in approximately five years, Smithson is obligated to restore the land to its original condition, including constructing a wildlife preserve. The company’s controller has provided the following three cash flow possibilities for the restoration costs: (1) $630,000, 20% probability; (2) $680,000, 45% probability; and (3) $780,000, 35% probability. The company’s credit-adjusted, risk-free rate of interest is 5%. (FV of...
Smithson Mining operates a silver mine in Nevada. Acquisition, exploration, and development costs totaled $7.3 million. After the silver is extracted in approximately five years, Smithson is obligated to restore the land to its original condition, including constructing a wildlife preserve. The company's controller has provided the following three cash flow possibilities for the restoration costs: (1) $670,000, 10% probability; (2) $720,000, 50% probability; and (3) $820,000, 40% probability. The company's credit-adjusted, risk-free rate of interest is 5%. (FV of...
On April 17, 2018, the Loadstone Mining Company purchased the rights to a coal mine. The purchase price plus additional costs necessary to prepare the mine for extraction of the coal totaled $4,750,000. The company expects to extract 950,000 tons of coal during a four-year period. During 2018, 245,000 tons were extracted and sold immediately. Required: 1. Calculate depletion for 2018.
Jackpot Mining Company operates a copper mine in central Montana. The company paid $1,150,000 in 2018 for the mining site and spent an additional $630,000 to prepare the mine for extraction of the copper. After the copper is extracted in approximately four years, the company is required to restore the land to its original condition, including repaving of roads and replacing a greenbelt. The company has provided the following three cash flow possibilities for the restoration costs (FV of $1,...
Jackpot Mining Company operates a copper mine in central Montana. The company paid $1,000,000 in 2018 for the mining site and spent an additional $600,000 to prepare the mine for extraction of the copper. After the copper is extracted in approximately four years, the company is required to restore the land to its original condition, including repaving of roads and replacing a greenbelt. The company has provided the following three cash flow possibilities for the restoration costs (FV of $1....
Brief Exercise 10-5 (Static) Asset retirement obligation (LO10-1) Smithson Mining operates a silver mine in Nevada. Acquisition, exploration, and development costs totaled $5.6 million. After the silver is extracted in approximately five years, Smithson is obligated to restore the land to its original condition, including constructing a wildlife preserve. The company's controller has provided the following three cash flow possibilities for the restoration costs: (1) $500,000, 20% probability: (2) $550,000, 45% probability; and (3) $650,000, 35% probability. The company's credit-adjusted,...
Jackpot Mining Company operates a copper mine in central
Montana. The company paid $1,650,000 in 2021 for the mining site
and spent an additional $730,000 to prepare the mine for extraction
of the copper. After the copper is extracted in approximately four
years, the company is required to restore the land to its original
condition, including repaving of roads and replacing a greenbelt.
The company has provided the following three cash flow
possibilities for the restoration costs: (FV of $1,...
On April 17, 2021, the Loadstone Mining Company purchased the rights to a coal mine. The purchase price plus additional costs necessary to prepare the mine for extraction of the coal totaled $6,540,000. The company expects to extract 1,090,000 tons of coal during a four-year period. During 2021, 259,000 tons were extracted and sold immediately. Required:1. Calculate depletion for 2021.2. Is depletion considered part of the product cost and included in the cost of inventory?
value 5.00 points On April 17,2016, the Loadstone Mining Company purchased the rights to a coal mine The purchase price plus additional costs necessary to prepare the mine for extraction of the coal totaled $2,790,000. The company expects to extract 930,000 tons of coal during a four year period. During 2016, 350,000 tons were extracted and sold immediately Required 1. Calculate depletion for 2016
Jackpot Mining Company operates a copper mine in central Montana. The company paid $1,150,000 in 2018 for the mining site and spent an additional $630,000 to prepare the mine for extraction of the copper. After the copper is extracted in approximately 4 years the company is required to restore the land to its original condition, including repaving of roads and replacing a greenbelt. The company has provided the following three cash flow possibilities for the restoration costs: (FV of $1,...