Orange, Inc. has identified the following cost drivers for its expected overhead costs for the year:
| Cost Pools | Budgeted Cost | Cost Driver | Cost Driver Level | |||
| Setup | $ | 220,000 | Number of setups | 1,100 | ||
| Ordering | 110,000 | Number of orders | 5,500 | |||
| Maintenance | 275,000 | Machine hours | 27,500 | |||
| Power | 55,000 | Kilowatt hours | 55,000 | |||
Total direct labor hours budgeted = 11,000 hours.
The following data applies to Product X, one of the products completed during the year.
| Direct materials | $ | 5,500 |
| Direct labor | $ | 6,600 |
| Units completed | 550 | |
| Direct labor hours | 220 | |
| Number of setups | 22 | |
| Number of orders | 44 | |
| Machine hours | 275 | |
| Kilowatt hours | 550 | |
If the activity-based cost drivers are used to allocate overhead cost, the total overhead cost of Product X will be:
Multiple Choice
$8,520.
$8,580.
$11,000.
$13,200.
$9,580.
Answer
--Correct Answer = Option #2: $ 8580
| Cost pool | Overhead rate | Activity driver for Product X | Overhead cost allocated | ||
| Setup | 200 | per setup | 22 | setup | $4,400 |
| Ordering | 20 | per orders | 44 | orders | $880 |
| Maintenance | 10 | per MHs | 275 | MHs | $2,750 |
| Power | 1 | per KHs | 550 | KHs | $550 |
| $8,580 Answer | |||||
--Calculation
| Cost pool | Overhead rate | Activity driver for Product X | Overhead cost allocated | ||
| Setup | =220000/1100 | per setup | 22 | setup | =200*22 |
| Ordering | =110000/5500 | per orders | 44 | orders | =20*44 |
| Maintenance | =275000/27500 | per MHs | 275 | MHs | =10*275 |
| Power | =55000/55000 | per KHs | 550 | KHs | =1*550 |
Orange, Inc. has identified the following cost drivers for its expected overhead costs for the year:...
Orange, Inc. has identified the following cost drivers for its expected overhead costs for the year: Cost Pools Budgeted Cost Cost Driver Cost Driver Level Setup $ 61,000 Number of setups 305 Ordering 30,500 Number of orders 1,525 Maintenance 76,250 Machine hours 7,625 Power 15,250 Kilowatt hours 15,250 Total direct labor hours budgeted = 3,050 hours. The following data applies to Product X, one of the products completed during the year. Direct materials $ 1,525 Direct labor $ 1,830 Units...
Orange, Inc. has identified the following cost drivers for its expected overhead costs for the Cost Pools Setup Ordering Maintenance Power Budgeted Cost $70,000 35,000 87,500 17,500 Cost Driver Number of setups Number of orders Machine hours Kilowatt hours Cost Driver Level 350 1,750 8,750 17,500 Total direct labor hours budgeted = 3,500 hours. The following data applies to Product X, one of the products completed during the year. Direct materials Direct labor Units completed Direct labor hours Number of...
Orange, Inc. has identified the following cost drivers for its expected overhead costs for the year: Expected Quantity 250 1,500 2,000 4,000 Expected Cost Overhead Item Cost Driver $ 59,500 Number of setups Setup costs Ordering costs Maintenance Power Total Overhead 49,000 Number of orders 138,000 Machine hours 29,500 Kilowatt hours $ 276,000 Total direct labor hours budgeted - 2,000 hours The following actual data applies to one of the products completed during the year: Product X Direct materials Direct...
Orange, Inc. has identified the following cost drivers for its expected overhead costs for the year: Overhead Item Expected Cost Cost Driver Expected Quantity Setup costs $ 50,000 Number of setups 250 Ordering costs 30,000 Number of orders 1,500 Maintenance 100,000 Machine hours 2,000 Power 20,000 Kilowatt hours 4,000 Total Overhead $ 200,000 Total direct labor hours budgeted = 2,000 hours. The following actual data applies to one of the products completed during the year: Product X Direct materials $...
A company has identified the following overhead costs and cost drivers for the coming year: Budgeted Overhead Item Cost Driver Budgeted Cost Activity Level Machine setup Number of setups $ 12,000 150 Inspection Number of inspections 85,000 4,250 Material handling Number of material moves 66,000 5,500 Engineering Engineering hours 11,000 550 Budgeted direct labor cost was $87,000 and budgeted direct material cost was $241,600. The following information was collected on...
Bonita Inc. has identified the following overhead costs and cost
drivers for next year.
Overhead
Item
Expected
Cost
Cost
Driver
Expected
Actual Transactions
Setup costs
$87,912
No. of setups
396
Ordering costs
46,800
No. of orders
3,900
Maintenance costs
125,000
Machine hours
25,000
Power
26,495
Kilowatt hours
75,700
The following are two of the jobs completed during the
year:
Job 700
Job 701
Direct materials
$1,200
$600
Direct labour
$890
$420
Units completed
250
100
Direct labour hours
40
20...
Multiple Versus Single Overhead Rates, Activity Drivers Deoro Company has identified the following overhead activities, costs, and activity drivers for the coming year: Activity Expected Cost Activity Driver Activity Capacity Setting up equipment $492,660 Number of setups 630 Ordering costs 361,200 Number of orders 17,200 Machine costs 882,000 Machine hours 42,000 Receiving 399,000 Receiving hours 9,500 Deoro produces two models of dishwashers with the following expected prime costs and activity demands: Model A Model B Direct materials $599,000 $ 780,000...
A company has identified the following overhead costs and cost drivers for the coming year: (CIA adapted) Overhead Item Machine setup Inspection Material handling Engineering Cost Driver Budgeted Cost Number of setups $ 20,000 Number of inspections 130,000 Number of material moves 80,000 Engineering hours 50,000 Budgeted Activity Level 200 6,500 8,000 1,000 Budgeted direct labor cost was $100,000 and budgeted direct material cost was $280,000. The following Information was collected on three jobs that were completed during the year:...
same question in both pictures
20) The Gardenview Corporation has identified the following overhead costs and activity drivers for next year: Overhead Item Expected Cost Activity Driver Expected Quantity Setup costs $ 200,000 Number of setups 250 Ordering costs 80,000 Number of orders 1,600 Manintenance 400,000 Machine hours 2,000 Power 40,000 Kilowatt hours 40,000 The following are two of the jobs completed during the year: JOB 6A JOB 8B Direct materials $ 3,000 $ 4,000 Direct labor $ 2,800 $...
Deoro Company has identified the following overhead activities, costs, and activity drivers for the coming year: Activity Expected Cost Activity Driver Activity Capacity Setting up equipment $469,800 Number of setups 580 Ordering costs 348,000 Number of orders 17,400 Machine costs 747,000 Machine hours 41,500 Receiving 462,000 Receiving hours 10,500 Deoro produces two models of dishwashers with the following expected prime costs and activity demands: Model A Model B Direct materials $647,000 $779,000 Direct labor $471,000 $484,000 Units completed 15,600 7,200...