a)
amount of revenue, expense, and net income for each of the three
years 2012 -14
under Cost-to-Cost Method (in Million $)
| Cost-to-Cost Method | ||||
| Percent | ||||
| Year | Costs Incurred (a) |
Percent of total expected Cost (b) = (Costs Incurred (a) / Total Cost) |
Revenue Recognized ($120 million x (b) |
Income (Revenue Recognized - Costs |
| 2012 | $ 10 | (10/85) = 12% | $14 | (14-10) = $4 |
| 2013 | 25 | (25/85) = 29% | 35 | (35-25) = $10 |
| 2014 | 50 | (50/85) = 59% | 71 | (71-50) = $21 |
| Total | $85 | $120 | $35 | |
b)
Answer - The cost-to-cost method is an acceptable method under GAAP for contracts spanning more than one accounting period.
The cost-to-cost method is based on Percent of Completion of project which is acceptable method under GAAP for estimating revenue and net income for each period if project span is more than one year. Here project completed in three year.
Constructing and Assessing Income Statements Using Cost-to-Cost Method On March 15, 2012, Frankel Construction contracted to...
Constructing and Assessing Income Statements Using Cost to Cost Method On March 15, 2012. Frankel Construction contracted to build a shopping center Year Cash Collections Cost a contract price of $120 million. The schedule of expected which c a sh collections and contactos (a) Calculate the amount of revenue expense, and net income for each of the three years 2012 through 2014 using the cost to cost method Rounding instructions: Round percentages to the nearest whole number. Use rounded percentages...
Constructing and Assessing Income Statements Using Percentage of Completion On March 15, 2017, Frankel Construction is contracted to build a shopping center at a contract price of $120 million. The schedule of expected (equals actual) cash collections and contract costs follows Year Cash Collections Cost Incurred 2017 2018 2019 $30 million 15 million 50 million40 mlion 40 million 30 million Total $120 million 85 million Calculate the amount of revenue, expense, and income for each of the three years 2017...
Constructing and Assessing Income Statements Using Cost-to-Cost Method Assume General Electric Company agreed in May 2016 to construct a nuclear generator for NSTAR, a utility company serving the Boston area. General Electric Company estimated that its construction costs would be $840 million. The contract price of $1,050 million is to be paid as follows: $350 million at the time of signing; $350 million on December 31, 2016; and $350 million at completion in May 2017. General Electric incurred the following...
On June 15, 2021, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $310 million. The expected completion date is April 1, 2023, just in time for the 2023 baseball season. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows $ in millions): 2021 $ 70 2022 $60 30 2023 $30 Costs incurred during the year Estimated costs to complete as of December...
On June 15, 2018, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $360 million. The expected completion date is April 1, 2020, just in time for the 2020 baseball season. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows ($ in millions): 2018 2019 2020 Costs incurred during the year Estimated costs to complete as of December 31 S 30 140 $40...
On June 15, 2021, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $310 million. The expected completion date is April 1, 2023, just in time for the 2023 baseball season. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows ($ in millions): 2021 $ 70 130 Costs incurred during the year Estimated costs to complete as of December 31 2022 $60 30...
Quantitative Problem: Rosnan Industries' 2013 and 2012 balance sheets and income statements are shown below. Balance Sheets: 2013 2012 Cash and equivalents $100 $85 Accounts receivable 275 200 Inventories 375 250 Total current assets $750 $635 Net plant and equipment 2,000 1,490 Total assets $2,750 $2,125 Accounts payable $150 $85 Accruals 75 50 Notes payable 150 75 Total current liabilities $375 $210 Long-term debt 450 290 Common stock 1,225 1,225 Retained earnings 700 400 Total liabilities and equity $2,750 $2,125 ...
On June 15, 2018, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $360 million. The expected completion date is April 1, 2020, just in time for the 2020 baseball season. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows ($ in millions): 2018 2019 2020 Costs incurred during the year $ 60 $ 120 $ 70 Estimated costs to complete as of...
7 On June 15, 2018, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $220 million. The expected completion date is April 1, 2020, just in time for the 2020 baseball season. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows ($ in millions): 0.5 points 2018 2019 2020 Costs incurred during the year Estimated costs to complete as of December 31 120...
LO4 Comparative statements of financial position for 2013 and 2012, the income statement for 2013, and additional information from the accounting records of Red Ltd are provided below. E 21-27 Statement of cash flows; direct method - LO3 LOS LOS LOS RED LTD Comparative Statements of Financial Position December 31, 2013 and 2012 is in millions) 2013 2012 $ 24 178 $110 132 Assets Cash Accounts receivable Prepaid insurance Inventory Buildings and equipment Less: Accumulated depreciation 175 350 285 400...