Requirement A:
| Materials | |||
| Total units | % of completion | Equivalent units | |
| Work in process inventory , April 1 | 3,000 | 0% | 0 |
| Units started and completed [12,000-3,000-1,000] | 9,000 | 100% | 9,000 |
| Total units completed during April | 12,000 | 9,000 | |
| Work in process inventory, April 30 | 1,000 | 50% | 500 |
| Total | 13,000 | 9,500 | |
Requirement B:
| Conversion cost | |||
| Total units | % of completion | Equivalent units | |
| Work in process inventory , April 1 | 3,000 | 40% | 1,200 |
| Units started and completed [12,000-3,000-1,000] | 9,000 | 100% | 9,000 |
| Total units completed during April | 12,000 | 10,200 | |
| Work in process inventory, April 30 | 1,000 | 50% | 500 |
| Total | 13,000 | 10,700 | |
Requirement C:
| Coversion cost during April | $36,800 |
| ÷ Equivalent units | 10,700 |
| =Conversion cost per equivalent unit | $3.44 |
1. The debits to Work in Process-Assembly Department for April, together with data concerning production, are...
The debits to Work in Process-Assembly Department for April, together with data concerning production, are as follows: April 1, work in process: Materials cost, 3,000 units Conversion costs, 3,000 units, 80% completed Materials added during April, 10,000 units Conversion costs during April Goods finished during April, 11,500 units April 30 work in process, 1,500 units, 60% completed $8,900 6,000 26,100 34,700 All direct materials are placed in process at the beginning of the process and the average cost method is...
The debits to Work in Process—Assembly Department for April, together with data concerning production, are as follows: April 1, work in process: Materials cost, 3,000 units $ 8,504 Conversion costs, 3,000 units, 40% completed 5,821 Materials added during April, 10,000 units 25,416 Conversion costs during April 33,120 Goods finished during April, 12,000 units 0 April 30 work in process, 1,000 units, 40% completed 0 All direct materials are added at the beginning of the process, and the first-in, first-out method...
The debits to Work in Process-Assembly Department for April, together with data concerning production, are as follows: April 1, work in process: Materials cost, 3,000 units $ 8,351 Conversion costs, 3,000 units, 40% completed 5,863 Materials added during April, 10,000 units 27,989 Conversion costs during April 30,741 Goods finished during April, 12,000 units 0 April 30 work in process, 1,000 units, 40% completed 0 All direct materials are added at the beginning of the process, and the first-in, first-out method...
The debits to Work in Process—Assembly Department for April, together with data concerning production, are as follows: April 1, work in process: Materials cost, 3,000 units $9,000 Conversion costs, 3,000 units, 80% completed 5,600 Materials added during April, 10,000 units 27,500 Conversion costs during April 32,800 Goods finished during April, 11,500 units — April 30, work in process, 1,500 units, 60% completed — All direct materials are placed in process at the beginning of the process, and the weighted average...
The debits to Work in Process—Assembly Department for April, together with data concerning production, are as follows: April 1, work in process: Materials cost, 3,000 units $8,300 Conversion costs, 3,000 units, 80% completed 5,400 Materials added during April, 10,000 units 27,900 Conversion costs during April 34,900 Goods finished during April, 11,500 units — April 30, work in process, 1,500 units, 60% completed — All direct materials are placed in process at the beginning of the process, and the weighted average...
1)
2)
3)
4)
5)
The debits to Work in Process-Assembly Department for April, together with data concerning production, are as follows: April 1, work in process: $8,900 5,500 27,500 32,000 Materials cost, 3,000 units Conversion costs, 3,000 units, 80% completed Materials added during April, 10,000 units Conversion costs during April Goods finished during April, 11,500 units April 30 work in process, 1,500 units, 60% completed 0 All direct materials are placed in process at the beginning of the process...
The debits to Work in Process—Assembly Department for May, together with data concerning production, are as follows: May 1, work in process: Materials cost, 3,000 units $7,800 Conversion costs, 3,000 units, 50% completed 5,000 Materials added during May, 10,000 units 25,000 Conversion costs during May 30,400 Goods finished during May, 11,500 units 0 May 31 work in process, 1,500 units, 50% completed 0 All direct materials are placed in process at the beginning of the process, and the first-in, first-out...
The debits to Work in Process—Assembly Department for May, together with data concerning production, are as follows: May 1, work in process: Materials cost, 3,000 units $8,800 Conversion costs, 3,000 units, 50% completed 5,700 Materials added during May, 10,000 units 25,600 Conversion costs during May 31,900 Goods finished during May, 11,500 units 0 May 31 work in process, 1,500 units, 50% completed 0 All direct materials are placed in process at the beginning of the process, and the first-in, first-out...
Question 17 (6 points) **The debits to Work in Process --Assembly Department for April, together with data concerning production, are as follows: Work in process, April 1, 5,000 units: Direct materials cost, 5,000 units $ 7,200 Conversion costs, 5,000 units, 60% completed $ 6,000 Direct materials added during April, 12,000 units $ 27,000 Conversion costs during April $ 35,750 Goods finished during April, 16,000 units Goods finished during April, 16,000 units Work in process, April 30, 1,000 units, 40% completed...
The debts to work in Process Assembly Department for May, together with data concerning production are as follows: May 1, work in process: Materials cost, 3,000 units $8,500 Conversion costs, 3,000 units, 50% completed 5,300 Materials added during May, 10,000 units 26,700 Conversion costs during May 31,200 Goods finished during May, 11,500 units May 31 work in process, 1.500 units, 50% completed All direct materials are placed in process at the beginning of the process, and the first in first-out...