Assembly Department Cost of Production Report
Quantity Schedule
| Unit Received from Preceding Department | $60,000 | |
| Unit Transferred to next department | $50,000 | |
| units still in process (All material 2/3 Labor & Overhead) | $9,000 | |
| Unit Lost in Process (Abnormal loss 1/2 Materials Labor Overhead | $1000 | $60,000 |
| Cost charged to the Department | Total Cost | Unit Cost |
| Cost from Preceding Department ; | ||
| Transferred in during the month (60,000) | $212,400 | $3.54 |
| Cost added by the Department | ||
| Material | $41,650 | .70 |
| Labor | $101,700 | 1.80 |
| Factory Overheads | $56,500 | 1.00 |
| Total Cost Added | $199,850 | 3.50 |
| Total Cost to be accounted for | $412,250 | 7.04 |
Cost Accounted for as follows;
| Transferred to Next Department (50000×7.04) | $352,000 | |
| Transferred to Factory Overheads; | ||
| From Precession department (1000×35.4) | $3,540 | |
| Materials (1000×1/2×.70) | $350 | |
| Labor (1000×1/2× $1.80) | $900 | |
| Factory Overheads (1000×1/2×$1) | $500 | $5,290 |
| Work in process ending inventory; | ||
| Cost from Preceding Department (9000×3.54) | $31,860 | |
| Materials (9000×.70) | $6,300 | |
| Labor (9,000×2/3×$1.80) | $10,800 | |
| Factory Overheads (9,000×2/3×1) | $6,000 | $54,960 |
| Total Cost Accounted | $412,250 |
Calculations;
Materials = 50,000+ $9,000+1000/2 lost unit = 59,500 Units
Labor and Factory Overheads =$50,000+(9000×2/3)+1000/2 lost unit = $56,500
Materials = .70 Per Unit ($41,650 /$59,500)
Factory Overheads = 1 Per Unit ($56,500/$56,500)
Labor =$ 1.80 Per Unit ($101,700/$56,500)
plz solve step by step 5. Costing of Units Transferred Out; Abnormal Loss During February, the...
plz solve step by step
6. Cost of Production Report; Normal and Abnormal Loss: The Sterling Company uses process costing. In department B, conversion costs are incurred uniformly throughout the process. Materials are added at the end of the process, following inspection. Normal spoilage is expected to be 5% of good output. The following information related to department B for January: Dollars $84,000 Units 12,000 9,000 2,000 Received from department A Transferred to finished goods Ending inventory (70% complete) Cost...
plz solve step by step
4. Equivalent Units of Production: During April, 20,000 units were transferred in from department A at a cost of $39,000. Materials cost of $6,500 and conversion cost of $9,000 were added in department B. On April 30, department B had 5,000 units of work in process 60% complete as to conversion as costs. Materials are added in the beginning of the process in department B. Required: 1. Equivalent units of production calculation. 2. The cost...
plz solve step by step
7. Cost of Production Report; Spoiled Units - Normal and Abnormal: Hettinger Inc., uses process costing system in its two producing departments. In department 2, inspection takes place at the 96% stage of completion, after which materials are added to good units. A spoilage rate of 3% of good output is considered normal. Department 2 records for April shows: Received from department 1 cost Materials Conversion cost (labor + factory overhead) Transferred to finished goods...
plz solve step by step
2. Cost of Production Report - Normal Loss: For December, the Production Control Department of Carola Chemical, Inc., reported the following production data for Department 2: Transferred in from Department 1 55,000 liters Transferred out to Department 3 39,500liters In process at the end of December (with 1/2 labor and factory overhead) 10,500 liters All materials were put into process in Department 1. The cost department collected following figures for department 2: Unit cost for...
plz solve step by step
3. Cost of Production Report: Brooks Inc. uses process costing. The costs for Department 2 for April were: $20,000 Cost from preceding department Cost added by department: Materials Labor Factory overhead (FOH) $21,816 7,776 4,104 33,696 The following information was obtained from the department's quantity schedule: Units received 5,000 Units transferred out 4,000 Units still in process 1,000 The degree of completion of the work in process as to costs originating in department 2 was:...
plz solve step by step
1. Cost of Production Report: A company's Department 2 costs for June were: $16320 Cost from Department 1 Cost added in Department 2: Materials Labor Factory overhead (FOH) 43,415 56,100 58,575 The quantity schedule shows 12,000 units were received during the month from Department 1; 7,000 units were transferred to finished goods; and 5,000 units in process at the end of June were 50% complete as to materials cost and 25% complete as to conversion...
Problem 5.4: Process Cost example with Normal Loss, Abnormal Loss, Abnormal Galli The following information is available about process B. 20000 units were transferred to process B @ Rs. 4 per unit. Normal loss in the production process is estimated @ 10% of process input. Output of process B is transferred to finished stock account. Amount (Rs. '000) Particulars Labor Cost 1000 Materials 4000 Proportionate share of factory overhead 700 You are required to prepare the process cost account for...
Determine the assignment of costs to goods transferred out and
in process.
Costs accounted for:
Transferred out
$
Work in process, November 30
Materials
$
Conversion costs
Total costs
$
Prepare a production cost report for the Assembly
Department.
RIV
Rivera Company has several processing departments. Costs charged to the Assembly Department for November 2020 totaled $2,293,806 as follows. $78,800 49,000 Work in process, November 1 Materials Conversion costs Materials added Labor Overhead $127,800 1,599,280 225,800 340,926 Production records show...
18-39 Physical units, inspection at various levels of completion, weighted-average process costing SunEnergy produces solar panels. A key step in the conversion of raw silicon to a completed solar panel occurs in the assembly department, where lightweight photovoltaic cells are assembled into modules and connected on a frame. In this department, materials are added at the beginning of the process and conver sion takes place uniformly At the start of November 2017, SunEnergy's assembly department had 2,400 panels in beginning...
mul Mchine hours were Cutting 1.680 and 7. Transferred good & Transferred goodscos sferred goods costing 567,600 from the Cutting Department to the Assembly Department sferred goods costing $134,900 from Assembly to Finished Goods. Sold goods costing $150,000 for $200,000 on account Instructions sumalize the transactions. (Omit explanations.) 53.5 (LO 3, 4), AP In Sh. HO 3, 4), AP In Shady Company, materials are entered at the beginning of each process. Work in s inventories, with the percentage of work...