Jefferson County’s Board of Representatives is considering the purchase of a site for a new sanitary landfill. The purchase price for the site is $250,000 and preparatory work will cost $44,400. The landfill would be usable for 10 years. The board hired a consultant, who estimated that the new landfill would cost the county $40,000 per year less to operate than the county’s current landfill. The current landfill also will last 10 more years. For a landfill project, Jefferson County can borrow money from the federal government at a subsidized rate. The county’s hurdle rate is only 4 percent for this project. |
| Use Appendix A for your reference. (Use appropriate factor(s) from the tables provided.) |

| Required: |
| a. |
Compute the net present value of the new landfill. |
|
|
Solution a:
| Computation of NPV - Jefferson County | ||||
| Particulars | Period | Amount | PV factor at 4% | Present Value |
| Cash outflows: | ||||
| Purchase price | 0 | $250,000.00 | 1 | $250,000 |
| Prepratory work | 0 | $44,400.00 | 1 | $44,400 |
| Present Value of Cash outflows (A) | $294,400 | |||
| Cash Inflows | ||||
| Savings in annual operating costs | 1-10 | $40,000.00 | 8.111 | $324,440 |
| Present Value of Cash Inflows (B) | $324,440 | |||
| Net Present Value (NPV) (B-A) | $30,040 | |||
Jefferson County’s Board of Representatives is considering the purchase of a site for a new sanitary...
Jefferson County’s Board of Representatives is considering the
purchase of a site for a new sanitary landfill. The purchase price
for the site is $250,000 and preparatory work will cost $44,400.
The landfill would be usable for 10 years. The board hired a
consultant, who estimated that the new landfill would cost the
county $40,000 per year less to operate than the county’s current
landfill. The current landfill also will last 10 more years. For a
landfill project, Jefferson County...
Required information [The following information applies to the questions displayed below.] Washington County’s Board of Representatives is considering the construction of a longer runway at the county airport. Currently, the airport can handle only private aircraft and small commuter jets. A new, long runway would enable the airport to handle the midsize jets used on many domestic flights. Data pertinent to the board’s decision appear below. Cost of acquiring additional land for runway $ 61,500 Cost of runway construction 310,000...
Required information [The following information applies to the questions displayed below.] Washington County’s Board of Representatives is considering the construction of a longer runway at the county airport. Currently, the airport can handle only private aircraft and small commuter jets. A new, long runway would enable the airport to handle the midsize jets used on many domestic flights. Data pertinent to the board’s decision appear below. Cost of acquiring additional land for runway $ 88,500 Cost of runway construction 300,000...
Required information
[The following information applies to the questions
displayed below.]
Washington County’s Board of Representatives is considering the
construction of a longer runway at the county airport. Currently,
the airport can handle only private aircraft and small commuter
jets. A new, long runway would enable the airport to handle the
midsize jets used on many domestic flights. Data pertinent to the
board’s decision appear below.
Cost of
acquiring additional land for runway
$
75,000
Cost of runway
construction
355,000...
Washington county’s board
Required information The following information applies to the questions displayed below.] Washington County's Board of Representatives is considering the construction of a longer runway at the county airport. Currently, the airport can handle only private aircraft and small commuter jets. A new. long runway would enable the airport to handle the midsize jets used on many domestic filights. Data pertinent to the board's decision appear below. Cost of acquiring additional land for runway Cost of runway construction...
eEgg is considering the purchase of a new distributed network computer system to help handle its warehouse inventories. The system costs $56,000 to purchase and install and $31,500 to operate each year. The system is estimated to be useful for 4 years. Management expects the new system to reduce the cost of managing inventories by $60,000 per year. The firm's cost of capital (discount rate) is 9%. Required: 1. What is the net present value (NPV) of the proposed investment...
eEgg is considering the purchase of a new distributed network computer system to help handle its warehouse inventories. The system costs $40,000 to purchase and install and $29,000 to operate each year. The system is estimated to be useful for 4 years. Management expects the new system to reduce the cost of managing inventories by $50,000 per year. The firm’s cost of capital (discount rate) is 9%. Required: 1. What is the net present value (NPV) of the proposed investment...
eEgg is considering the purchase of a new distributed network computer system to help handle its warehouse inventories. The system costs $55,000 to purchase and install and $35,000 to operate each year. The system is estimated to be useful for 4 years. Management expects the new system to reduce the cost of managing inventories by $63,000 per year. The firm’s cost of capital (discount rate) is 7%. Required: 1. What is the net present value (NPV) of the proposed investment...
eEgg is considering the purchase of a new distributed network computer system to help handle its warehouse inventories. The system costs $40,000 to purchase and install and $29,000 to operate each year. The system is estimated to be useful for 4 years. Management expects the new system to reduce the cost of managing inventories by $50,000 per year. The firm’s cost of capital (discount rate) is 9%. Required: 1. What is the net present value (NPV) of the proposed investment...
eEgg is considering the purchase of a new distributed network computer system to help handle its warehouse inventories. The system costs $41,000 to purchase and install and $25,000 to operate each year. The system is estimated to be useful for 4 years. Management expects the new system to reduce the cost of managing inventories by $46,000 per year. The firm’s cost of capital (discount rate) is 11%. Required: 1. What is the net present value (NPV) of the proposed investment...