Answer #1

Variable cost per unit=[Total cost at highest level-Total cost at lowest level]/(Highest level-Lowest level)

=(12800-10180)/(16100-12100)

=$0.655 per machine hour

Total fixed cost=12800-(0.655*16100)

=2254.5

Hence total cost would be=Total variable cost+Total fixed cost

=(0.655*14600)+2254.5

=$11817.5

Add a comment
Know the answer?
Add Answer to:
Hagler's Toupees has the following machine hours and production costs for the last six months of...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Fromme's Frocks has the following machine hours and production costs for the last six months of...

    Fromme's Frocks has the following machine hours and production costs for the last six months of last year: Month July August September October November December Machine Production Hours Cost 16,900 $12, 170 15,400 12,700 13,400 9,650 17,400 12,270 16,700 11,787 14,000 9,979 If Fromme expects to incur 12,500 machine hours in January, what will be the estimated total production cost using the high-low method? If Fromme expects to incur 12,500 machine hours in January, what will be the estimated total...

  • fromme’ Fromme's Frocks has the following machine hours and production costs for the last six months...

    fromme’ Fromme's Frocks has the following machine hours and production costs for the last six months of last year: Production Cost Month July August September October November December Machine Hours 15,400 13,900 11,900 15,900 15,200 12,500 12,095 11,200 9,620 12,120 11,712 9,934 If Fromme expects to incur 11,000 machine hours in January, what will be the estimated total production cost using the high-low method? O $6,875.00 $9,057.50 $18,995.00 O $8,384.91.

  • Fromme's Frocks has the following machine hours and production costs for the last six months of...

    Fromme's Frocks has the following machine hours and production costs for the last six months of last year: Month Machine Hours Production Cost July 16,500 $ 12,150 August 15,000 12,300 September 13,000 9,650 October 17,000 12,230 November 16,300 11,767 December 13,600 9,967 If Fromme expects to incur 12,100 machine hours in January, what will be the estimated total production cost using the high-low method?

  • The following six months of data were collected on electricity cost and the number of machine...

    The following six months of data were collected on electricity cost and the number of machine hours in a factory. Month Electricity cost Machine hours June $25,160   4,500 July 26,170 4,810 August 27,250 5,120 September 26,680 5,010 October 27,950 5,430 November 27,500 5,190 Refer to Figure 3-13. An independent variable value used in calculating the cost line using the high-low method is: a.$27,950 b.4,000 c.5,430 d.$25,160

  • Based on the following for the first six months: Direct Labor Hours Manufacturing Overhead July 45,000...

    Based on the following for the first six months: Direct Labor Hours Manufacturing Overhead July 45,000 $295,000 August 60,000 $320,000 September 57,000 $323,000 October 52,000 $247,250 November 34,000 $178,200 December 25,000 $162,500 Required: Use the high-low method to estimate the cost formula Estimate the total overhead cost at an activity level of 48,000 machine hours, using the separate estimates you obtained for its components.

  • Machine hours and electricity costs for Wells Industries for last year were as follows: Machine Electricity...

    Machine hours and electricity costs for Wells Industries for last year were as follows: Machine Electricity Month Hours Costs January 2,000 $ 9,200 February 2,320 10,500 March 1,520 6,750 April 2,480 11,500 May 3,040 14,125 June 2,640 11,000 July 3,280 12,375 August 2,800 11,375 September 1,600 7,750 October 2,960 13,000 November 3,760 15,500 December 3,360 13,875 Required: Show your Calculations! A. Using the high-low method, develop an estimate of variable electricity costs per machine hour. B. Using the high-low method,...

  • Westerville Corp. has collected the following data concerning its maintenance costs for the past six months:...

    Westerville Corp. has collected the following data concerning its maintenance costs for the past six months: Units Produced Total Cost July 17,300 $31,620 August 32,900 48,000 September 36,100 55,100 October 22,400 39,000 November 40,300 65,200 December 38,200 62,300 (a1) Calculate the variable cost per unit using the high-low method. (Round variable cost per unit to 2 decimal places, e.g. 12.25.) Variable cost $ per unit

  • Create two tuples named months1 and months2, including first six months and last six months, respectively....

    Create two tuples named months1 and months2, including first six months and last six months, respectively. Create a new tuple from concatenation of the two tuples created previously. Print the tuple including all months. Print the name of the 6th month using tuple index. Query the index of the one of months. (ex.‘November’) python IDL #WORKLAB4.3 month1=('January','February','March','April','May','June') month2=('July','August','September','October','November','December') allMonths = 'months1'+ 'months2' print('allMonths') print(allMonths[6]) print(allMonths.index('November'))

  • Fiscal Company has the following sales budget for the last six months of 2020: July                   $100,000        &

    Fiscal Company has the following sales budget for the last six months of 2020: July                   $100,000                          August                 80,000                           September       110,000                           October               90,000 November        100,000 December           94,000 Historically, the cash collection of sales has been as follows: 65 percent of sales collected in month of sale, 25 percent of sales collected in month following sale, 8 percent of sales collected in second month following sale, and 2 percent of sales are uncollectible. Prepare a schedule of cash collections for October, November, and December of 2020. Make sure...

  • The following information is available for a company’s maintenance cost over the last seven months. Month...

    The following information is available for a company’s maintenance cost over the last seven months. Month Maintenance Hours Maintenance Cost June 9 $ 3,950 July 18 5,750 August 12 4,550 September 15 5,150 October 21 6,350 November 24 6,950 December 6 3,350 Using the high-low method, estimate both the fixed and variable components of its maintenance cost.    High- Low method- Calculation of variable cost per maintenance hour

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT