McNeil uses the high-low method of estimating costs. McNeil had total costs of $51,000 at its lowest level of activity, when

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Correct answer---------$67,800

Working

Cost No. of activities
A High Level $          79,000.00 10500
B Low Level $          51,000.00 5500
C=A-B Difference $          28,000.00                        5,000
A Cost difference $          28,000.00
B No. of activities difference 5000
C=A/B Variable cost per unit $                     5.60
High Level Low Level
A No. of activities 10500 5500
B Variable cost per unit $                5.6000 $                  5.6000
C=AxB Total Variable cost $          58,800.00 $            30,800.00
D Total cost $          79,000.00 $            51,000.00
E=D-C Total fixed cost $          20,200.00 $            20,200.00

.

No of units $            8,500.00
Variable cost (5.60 x 8500) $          47,600.00
Fixed cost $          20,200.00
Total cost $          67,800.00
Add a comment
Know the answer?
Add Answer to:
McNeil uses the high-low method of estimating costs. McNeil had total costs of $51,000 at its...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT