Solution – 1a:
Standard rate of micron = $0.30
Actual rate of micron = $0.29
Standard Qty of micron for 5000 Maze = 5000*8 = 40000
Actual Qty of Micron consumed = 78000 – 28000= 50000
Material Price Variance = (SR – AR) * AQ = (0.30 – 0.29) * 50000 = $500 (F)
Material Qty Variance = (SQ – AQ) * SR = (40000 – 50000) * 0.30 = $3,000 (U)
Solution – 1b:
Standard rate of direct labor = $6.50/hour
Standard hours for actual production = 5000 * 1.2 = 6000 Hrs
Actual Direct labor cost = $44850
Actual Direct labor hours = 6500
Actual rate of direct labor = 44,850/6500 = 6.90/Hr
Labor rate variance = (SR – AR) * AH = (6.50 – $6.90) * 6500 = $2,600 (U)
Labor efficiency variance = (SH – AH) * SR = (6000 – 6500) * 6.50 = $3,250 (U)
Exercise 10-8 Direct Materials and Direct Labor Variances [LO10-1, LO10-2] Dawson Toys, Ltd. produces a toy...
Exercise 10-8 Direct Materials and Direct Labor Variances (LO10-1, LO10-2) Dawson Toys, Ltd., produces a toy called the Maze. The company has recently established a standard cost system to help control costs and has established the following standards for the Maze toy: Direct materials: 8 microns per toy at $0.33 per micron Direct labor: 1.4 hours per toy at $6.60 per hour During July, the company produced 4,800 Maze toys. The toy's production data for the month are as follows:...
Exercise 10-8 Direct Materials and Direct Labor Variances (LO10-1, LO10-2] Dawson Toys, Ltd., produces a toy called the Maze. The company has recently established a standard cost system to help control costs and has established the following standards for the Maze toy: Direct materials: 7 microns per toy at $0.32 per micron Direct labor: 1.5 hours per toy at $7.10 per hour During July, the company produced 4,900 Maze toys. The toy's production data for the month are as follows:...
Exercise 10-8 Direct Materials and Direct Labor Variances [LO10-1, LO10-2] Dawson Toys, Ltd., produces a toy called the Maze. The company has recently established a standard cost system to help control costs and has established the following standards for the Maze toy: Direct materials: 8 microns per toy at $0.32 per micron Direct labor: 1.3 hours per toy at $6.80 per hour During July, the company produced 5,300 Maze toys. The toy's production data for the month are as follows:...
Exercise 10-8 Direct Materials and Direct Labor Variances (LO10-1, LO10-2) Dawson Toys, Ltd., produces a toy called the Maze. The company has recently established a standard cost system to help control costs and has established the following standards for the Maze toy: Direct materials: 7 microns per toy at $0.34 per micron Direct labor: 1.3 hours per toy at $6.60 per hour During July, the company produced 4,700 Maze toys. The toy's production data for the month are as follows:...
Exercise 10-8 Direct Materials and Direct Labor Variances [L010-1, LO10-2] Dawson Toys, Ltd., produces a toy called the Maze. The company has recently established a standard cost system to help control costs and has established the following standards for the Maze toy: Direct materials: 6 microns per toy at $0.35 per micron Direct labor: 1.3 hours per toy at $710 per hour During July, the company produced 5,000 Maze toys. The toy's production data for the month are as follows:...
Exercise 10-8 Direct Materials and Direct Labor Variances (LO10-1, LO10-2] Dawson Toys, Ltd., produces a toy called the Maze. The company has recently established a standard cost system to help control costs and has established the following standards for the Maze toy: Direct materials: 8 microns per toy at $0.32 per micron Direct labor: 1.2 hours per toy at $7.40 per hour During July, the company produced 4,900 Maze toys. The toy's production data for the month are as follows:...
Dawson Toys, Ltd., produces a toy called the Maze. The company has recently established a standard cost system to help control costs and has established the following standards for the Maze toy: Direct materials: 6 microns per toy at $1.50 per micron Direct labor: 1.3 hours per toy at $21 per hour During July, the company produced 3,000 Maze toys. The toy's production data for the month are as follows: Direct materials. 25,000 microns were purchased at a cost of...
Dawson Toys, Ltd.. produces a toy called the Maze. The company has recently established a standard cost system to help control costs and has established the following standards for the Maze toy Direct materials: 7 microns per toy at 50.33 per micron Direct labor 1.2 hours per toy at $7.20 per hour During July, the company produced 5,000 Maze toys. Production data for the month on the toy follow Direct materials: 74.000 microns were purchased at a cost of $0.20...
Dawson Toys, Ltd., produces a toy called the Maze. The company has recently established a standard cost system to help control costs and has established the following standards for the Maze toy: Direct materials: 6 microns per toy at $0.31 per micron Direct labor: 1.4 hours per toy at $7.20 per hour During July, the company produced 5,100 Maze toys. The toy's production data for the month are as follows: Direct materials. 75,000 microns were purchased at a cost of...
Dawson Toys, Ltd., produces a toy called the Maze. The company has recently established a standard cost system to help control costs and has established the following standards for the Maze toy Direct materials: 6 microns per toy at $0.34 per micron Direct labor: 12 hours per toy at $710 per hour During July, the company produced 4,800 Maze toys. The toy's production data for the month are as follows: Direct materials: 74,000 microns were purchased at a cost of...