Wonder Mountain Company operates a snow sports resort for skiers and snowboarders. The company has recently decided to replace an existing old chair lift with a new high-speed quad chair and expand the hill to allow for increased capacity. The old chair lift was a $822,000 asset on the books, 90% depreciated. The work was completed from April to November. Wonder Mountain incurred the following costs for the expansion:
| Invoice price high-speed quad chair lift | $ | 1,694,000 |
| Costs to dismantle old chair lift | 32,200 | |
| Cash received for sale used chair lift | 169,400 | |
| Shipping costs for delivery | 20,740 | |
| Landscape architect fees, grading expansion hill | 8,340 | |
| Permit costs | 5,620 | |
| Clearing trees/grading land for expansion | 48,500 | |
| Installation of concrete bases for chair lift | 105,000 | |
| Helicopter rental to install towers for chair lift | 92,000 | |
| Labour installation ski lift | 310,000 | |
| Training employees on maintenance and operation | 9,600 | |
| Testing of chair lift | 30,400 | |
| Interest costs on loan for construction | 69,000 | |
| General overhead costs | 34,200 | |
| Annual routine maintenance | 49,800 | |
| Purchase tools required for annual maintenance | 85,200 | |
Required:
Calculate the total cost for each asset:
land
tools
ski lift

Wonder Mountain Company operates a snow sports resort for skiers and snowboarders. The company has recently...