(4 ) As cost accountant of Rackets Ltd, you estimate the standard cost of making one unit is as follows:

Direct material 4 kilos at £7 per kilo

Direct wages 5 hours at £10 per hour

The actual cost of a batch of 1000 units was:

Direct material £28960 (4328 kilos)

Direct wages £50200 (5370 hours)

Calculate the following:

(vi) The total labour cost variance

(vii) The total cost variance

1 0
Add a comment Improve this question Transcribed image text
Answer #1

Given data,

Estimated standard cost of making one unit

Direct material : 7 per kilo

Direct wages : 10 per hour

Actual cost of making 1000 unit:

Actual Direct Wages : 50200

Solution:

Standard Cost of making 1000 unit :

Standard Direct Material : 1000*4*7 = 28000

Standard Direct Wages : 1000*5*10 = 50000

(Vi) Total Labour Cost Variance = (Standard Hour * Standard Rate ) - (Actual Hour * Actual Rate)

= Standard Direct Wages - Actual Direct Wages

= 50000 - 50200 = 200 (Adverse)

(vii) Total Cost Variance = Total Material Cost Variance + Total Labour Cost Variance

(a) Total Material Cost Variance = (Standard Unit * Standard Rate) - (Actual Unit * Actual Rate)

= Standard Material Cost - Actual Material Cost

= 28000 - 28960 = 960 (Adverse)

(b) Total Labour Cost Variance (as per solution no. (vi) above = 200 (Adverce)

Total Cost Varialnce = Total Material Cost Variance + Total Labour Cost Variance

= 200+960 = 1160 (Adverse)

Add a comment
Know the answer?
Add Answer to:
ATTEMPT ALL THE QUESTIONS (4 ) As cost accountant of Rackets Ltd, you estimate the standard...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • CAT 1 AND 2 ATTEMPT ALL THE QUESTIONS (1 ) As cost accountant of Rackets Ltd,...

    CAT 1 AND 2 ATTEMPT ALL THE QUESTIONS (1 ) As cost accountant of Rackets Ltd, you estimate the standard cost of making one unit is as follows: Direct material 4 kilos at £7 per kilo Direct wages 5 hours at £10 per hour The actual cost of a batch of 1000 units was: Direct material £28960 (4328 kilos) Direct wages £50200 (5370 hours)   Calculate the following: (i) The material price variance (ii) The material usage variance (iii) The total...

  • You have recently been employed as a junior accountant at Thrones Ltd, a manufacturer of a...

    You have recently been employed as a junior accountant at Thrones Ltd, a manufacturer of a miniature statue based on a popular TV show character. Unfortunately, your supervisor, the main company accountant, has been injured in a recent horse riding accident and is away from work for some time. The company CEO, after hearing you have recently graduated from a prestigious university with great results in management d you to prepare a variance report for a management meeting later in...

  • QUESTION 1: IDE company manufactures and sales one product. There is no opening or closing inventories...

    QUESTION 1: IDE company manufactures and sales one product. There is no opening or closing inventories and work in progress is negligible. The company operates a standard costing system and analysis of variances and reports are prepared every month for management's planning control and decision making. The below product information is given; Standard selling price K32 Standard contribution K13.4 Variable overheads 2hrs@30ngwee/hr k0.60 Direct wages 2hrs@K8/hr K16 Direct Materials 0.5kgs @K4/kg K2 Further information is given as follows: Variable overheads...

  • The U.R. Good Company produces a product using standard costs as follows: a. Standard cost per unit Materials 7 kilos at ₱ 3.50 per kilo Labor 8 hours at ₱ 1.75 per kilo Fixed MOH ₱ 1.15 per hour or ₱ 9.20 per unit Variabl

    The U.R. Good Company produces a product using standard costs as follows:a.  Standard cost per unit     Materials   7 kilos at ₱ 3.50 per kilo     Labor   8 hours at ₱ 1.75 per kilo     Fixed  MOH   ₱ 1.15 per hour or ₱ 9.20 per unit     Variable MOH   ₱ 0.85 per hour or ₱ 6.80 per unitb.  Overhead is applied on direct labor hoursc.  Actual performance (1 month)     Volume produced   800     Labor hours    6,300     Overhead   ₱13,200     Material Cost ...

  • Question 5 (24 marks) You have recently been employed as a junior accountant at Thrones Ltd,...

    Question 5 (24 marks) You have recently been employed as a junior accountant at Thrones Ltd, a manufacturer of a miniature statue based on a popular TV show character. Unfortunately, your supervisor, the main company accountant, has been injured in a recent horse riding accident and is away from work for some time. The company CEO, after hearing you have recently graduated from a prestigious university with great results in management accounting, has asked you to prepare a variance report...

  • Nyundo Ltd manufactures a product whose standard variable cost is given below: Direct materials (2 kg...

    Nyundo Ltd manufactures a product whose standard variable cost is given below: Direct materials (2 kg @ Sh 3) Direct labour (0.75 hours @ Sh 4) Variable overheads The company treats fixed costs as period costs and therefore they are not charged to products. The following information relates to the month of March 2001. 1/10/2019 31/10/2019 Sh Sh Stocks (all at standard cost) Raw materials 12,000 6,000 Finished goods 36,000 42,500 The following information is available for the month of...

  • Agro Business operates several production processes including the production of bulk animal feed for cattle. One...

    Agro Business operates several production processes including the production of bulk animal feed for cattle. One such product is produced in three separate process operations – Testing, Mixing & Packaging. The information below is of the costs incurred in, and output from the Mixing Process during the period just completed. (i) Input from Testing: 120,000 kilos valued at an average cost of $24.05 per kilo (ii) Other manufacturing costs incurred during the period: Direct material added $790,500 Direct labour $380,400...

  • Agro Business operates several production processes including the production of bulk animal feed for cattle. One such pr...

    Agro Business operates several production processes including the production of bulk animal feed for cattle. One such product is produced in three separate process operations – Testing, Mixing & Packaging. The information below is of the costs incurred in, and output from the Mixing Process during the period just completed. (i) Input from Testing: 120,000 kilos valued at an average cost of $24.05 per kilo (ii) Other manufacturing costs incurred during the period: Direct material added Direct labour Manufacturing overhead...

  • Problem 9-21 Multiple Products, Materials, and Processes (LO9-4, LO9-5] Mickley Corporation produces two products, Alph...

    Problem 9-21 Multiple Products, Materials, and Processes (LO9-4, LO9-5] Mickley Corporation produces two products, Alphabs and Zeta7s, which pass through two operations, Sintering and Finishing. Each of the products uses two raw materials-X442 and Y661. The company uses a standard cost system, with the following standards for each product (on a per unit basis): Product Alpha 6 Zeta 7 Raw Material X442 7661 3.0 kilos 2.0 liters 5.0 kilos 4.0 liters Standard Labor Time Sintering Finishing 0.30 hours 1.20 hours...

  • QUESTION 2 Dasebre Ltd produces and sells one product with the brand name Sobolo. The standard...

    QUESTION 2 Dasebre Ltd produces and sells one product with the brand name Sobolo. The standard cost for one unit being as follows: GHS 200 30 30 Direct material A-10 kilograms at GHS20 per kg Direct material B - 5 litres at GHS per litre Direct wages - 5 hours at GHS6 per hour Variable production overhead Total standard cost 50 310 The variable production Overheads is incurred in direct proportion to the direct labour hours worked. The budgeted sales...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT