Direct material Quantity variance = (Standard Quantity – Actual Quantity used)*Standard Price
= (132*5 – 680)*2
= $40 Unfavorable
Question 15 A company developed the following per-unit standards for its product: 5 kilograms of direct...
Question 15 A company developed the following per-unit standards for its product: 5 kilograms of direct materials at $3.10 per kilogram. Last month, 1000 kilograms of direct materials were purchased for $2990. Also last month, 750 kilograms of direct materials were used to produce 130 units. What was the direct materials price variance for last month? $12820 favourable O $110 favourable 0 $12820 unfavourable $110 unfavourable
A company developed the following per-unit standards for its
product: 5 kilograms of direct materials at $3.20 per kilogram.
Last month, 1000 kilograms of direct materials were purchased for
$2880. Also last month, 650 kilograms of direct materials were used
to produce 133 units. What was the direct materials price variance
for last month?
$13760 favourable
$320 favourable
$13760 unfavourable
$320 unfavourable
A company developed the following per-unit standards for its product: 5 kilograms of direct materials at $3.20 per kilogram. Last month, 1000 kilograms of direct materials were purchased for $2820. Also last month, 700 kilograms of direct materials were used to produce 139 units. What O $13820 favourable $380 favourable O $13820 unfavourable O $380 unfavourable
A company developed the following per - unit standards for its product: 2 pounds of direct materials at $4 per pound. Last month, 1,500 pounds of direct materials were purchased for $5,700. The direct materials price variance for last month was a. 5,700 Favorable b. $300 Favorable c. $150 Favorable d. $300 unfavorable
A company developed the following per unit materials standards for its product: 3 gallons of direct materials at $5 per gallon. If 2,000 units of product were produced last month and 5,750 gallons of direct materials were used, the direct materials quantity variance was: a. $750 favorable b. $1,250 favorable c. $7,500 favorable d. $11,250 favorable.
The per-unit standards for direct labour are 3 direct labour hours at $15 per hour. If in producing 710 units, the actual direct labour cost was $31000 for 2377 direct labour hours worked, the total direct labour variance is $247 unfavourable. $950 favourable. $247 favourable. $950 unfavourable.
Multiple Choice Question 115 The per-unit standards for direct materials are 2 pounds at $5 per pound. Last month, 9800 pounds of direct materials that actually cost $47200 were used to produce 5400 units of product. The direct materials quantity variance for last month was $6800 unfavorable. $5000 favorable. $2700 favorable. $5000 unfavorable. NOISEA H BACK NE Multiple Choice Question 116 The per-unit standards for direct labor are 1.5 direct labor hours at $15 per hour. If in producing 3000...
If the actual labour hours worked exceed the standard labour hours allowed, what type of variance will occur? Multiple Choice Favourable labour efficiency variance. ) Favourable labour rate variance. 0 Unfavourable labour efficiency variance. 0 Unfavourable labour rate variance. The standards for direct labour for a product are 2.5 hours at $8 per hour. Last month, 9,000 units of the product were made, and the labour efficiency variance was $8,000 favourable. What was the actual number of hours worked during...
The following data for a pottery company pertain to the production of 2,000 clay pots during July. Direct Materials (all materials purchased were used): Standard cost: $2.00 per kilogram of clay Total actual cost: $10,640 Standard cost allowed for units produced was $12,000 Materials quantity variance was $800 favourable Direct Manufacturing Labour: Standard cost is 2 pots per hour at $24.00 per hour Actual cost per hour was $24.50 Actual labour was 1028 hours show all steps! a. What is...
Jay Levitt Company budgeted the following cost standards for
the current year:
Direct materials (2 kg of
plastic at $6 per kilogram)
$12.00
Direct labour (2 hours at $12
per hour)
24.00
Variable manufacturing
overhead
11.90
Fixed manufacturing
overhead
6.25
Total standard cost per
unit
$54.15
Actual costs for producing 2,740 units were as follows:
Direct materials used
5,560
kg
Direct materials purchased
(6,780 kg)
$40,002
Direct labour (6,880 hours)
$67,424
Variable manufacturing
costs
$32,600
Fixed manufacturing costs
$17,600
Your...