Question

Exercise 11-8 a The following direct materials and direct labor data pertain to the operations of...

Exercise 11-8 a

The following direct materials and direct labor data pertain to the operations of Laurel Company for the month of August.

Costs

Actual labor rate $16 per hour
Actual materials price $110 per ton
Standard labor rate $15.50 per hour
Standard materials price $112 per ton

Quantities

Actual hours incurred and used 4,500 hours
Actual quantity of materials purchased and used 1,100 tons
Standard hours used 4,540 hours
Standard quantity of materials used 1,085 tons

(a)

Compute the total, price, and quantity variances for materials and labor.
Total materials variance $

FavorableUnfavorableNeither favorable nor unfavorable

Materials price variance $

Neither favorable nor unfavorableFavorableUnfavorable

Materials quantity variance $

FavorableNeither favorable nor unfavorableUnfavorable

Total labor variance $

Neither favorable nor unfavorableFavorableUnfavorable

Labor price variance $

UnfavorableFavorableNeither favorable nor unfavorable

Labor quantity variance $

Neither favorable nor unfavorableUnfavorableFavorable

Click if you would like to Show Work for this question:

Open Show Work

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Solution

Total Material Variance $               520.00 Favourable-F
Material Price Variance $           2,200.00 Favourable-F
Material quantity variance $           1,680.00 Unfavourable-U
Total Labor variance $           1,630.00 Unfavourable-U
Labor rate variance   $           2,250.00 Unfavourable-U
Labor Efficiency variance $               620.00 Favourable-F

Working

Actual DATA for
Quantity (AQ) Rate (AR) Actual Cost
Direct Material 1100 $ 110.00 $       121,000.00
Direct labor 4500 $     16.00 $          72,000.00

.

Material Price Variance
( Standard Rate - Actual Rate ) x Actual Quantity
( $               112.00 - $                 110.00 ) x 1100
2200
Variance $             2,200.00 Favourable-F
Material Quantity Variance
( Standard Quantity - Actual Quantity ) x Standard Rate
( 1085 - 1100 ) x $         112.00
-1680
Variance $             1,680.00 Unfavourable-U
Material Spending Variance
( Standard Cost - Actual Cost )
( $       121,520.00 - $        121,000.00 )
520
Variance $                 520.00 Favourable-F
Labor Rate Variance
( Standard Rate - Actual Rate ) x Actual Labor Hours
( $                  15.50 - $                   16.00 ) x 4500
-2250
Variance $             2,250.00 Unfavourable-U
Labour Efficiency Variance
( Standard Hours - Actual Hours ) x Standard Rate
( 4540 - 4500 ) x $           15.50
620
Variance $                 620.00 Favourable-F
Labor Spending Variance
( Standard Cost - Actual Cost )
( $         70,370.00 - $           72,000.00 )
-1630
Variance $             1,630.00 Unfavourable-U
Add a comment
Know the answer?
Add Answer to:
Exercise 11-8 a The following direct materials and direct labor data pertain to the operations of...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • The following direct materials and direct labor data pertain to the operations of Laurel Company for...

    The following direct materials and direct labor data pertain to the operations of Laurel Company for the month of August. Costs Actual labor rate $15 per hour Actual materials price $180 per ton Standard labor rate $14.50 per hour Standard materials price $182 per ton Quantities Actual hours incurred and used 4,700 hours Actual quantity of materials purchased and used 1,900 tons Standard hours used 4,760 hours Standard quantity of materials used 1,890 tons (a) Compute the total, price, and...

  • The following direct materials and direct labor data pertain to the operations of Laurel Company for...

    The following direct materials and direct labor data pertain to the operations of Laurel Company for the month of August. Costs Actual labor rate $13 per hour Actual materials price $290 per ton Standard labor rate $12.50 per hour Standard materials price $292 per ton Quantities Actual hours incurred and used 4,200 hours Actual quantity of materials purchased and used 1,000 tons Standard hours used 4,290 hours Standard quantity of materials used 990 tons (a) Compute the total, price, and...

  • The following direct materials and direct labor data pertain to the operations of Laurel Company for...

    The following direct materials and direct labor data pertain to the operations of Laurel Company for the month of August. Costs Actual labor rate $15 per hour Actual materials price $140 per ton Standard labor rate $14.50 per hour Standard materials price $142 per ton Quantities Actual hours incurred and used 3,800 hours Actual quantity of materials purchased and used 1,500 tons Standard hours used 3,850 hours Standard quantity of materials used 1,490 tons (a) Compute the total, price, and...

  • The following direct materials and direct labor data pertain to the operations of Laurel Company for...

    The following direct materials and direct labor data pertain to the operations of Laurel Company for the month of August. Costs Actual labor rate $15 per hour Actual materials price $140 per ton Standard labor rate $14.50 per hour Standard materials price $142 per ton Quantities Actual hours incurred and used 3,800 hours Actual quantity of materials purchased and used 1,500 tons Standard hours used 3,850 hours Standard quantity of materials used 1,490 tons (a) Compute the total, price, and...

  • The standard cost of Product B manufactured by Flint Company includes 3.90 units of direct materials...

    The standard cost of Product B manufactured by Flint Company includes 3.90 units of direct materials at $5.60 per unit. During June, 26,700 units of direct materials are purchased at a cost of $5.45 per unit, and 26,700 units of direct materials are used to produce 6,800 units of Product B. Compute the total materials variance and the price and quantity variances. Total materials variance $ Neither favorable nor unfavorableUnfavorableFavorable Materials price variance $ UnfavorableFavorableNeither favorable nor unfavorable Materials quantity...

  • 1) Stefani Company has gathered the following information about its product. Direct materials: Each unit of...

    1) Stefani Company has gathered the following information about its product. Direct materials: Each unit of product contains 4.50 pounds of materials. The average waste and spoilage per unit produced under normal conditions is 1.50 pounds. Materials cost $3 per pound, but Stefani always takes the 5.00% cash discount all of its suppliers offer. Freight costs average $0.30 per pound. Direct labor. Each unit requires 1.70 hours of labor. Setup, cleanup, and downtime average 0.20 hours per unit. The average...

  • Levine Inc., which produces a single product, has prepared the following standard cost sheet for one...

    Levine Inc., which produces a single product, has prepared the following standard cost sheet for one unit of the product. Direct materials (9 pounds at $1.90 per pound) $17.10 Direct labor (4 hours at $10.00 per hour) $40.00 During the month of April, the company manufactures 160 units and incurs the following actual costs. Direct materials purchased and used (2,100 pounds) $4,410 Direct labor (680 hours) $6,664 Compute the total, price, and quantity variances for materials and labor. Total materials...

  • View Policies Current Attempt in Progress The following direct materials and direct labor data pertain to...

    View Policies Current Attempt in Progress The following direct materials and direct labor data pertain to the operations of Laurel Company for the month of August. Costs $16 per hour $110 per ton Actual labor rate Actual materials price Standard labor rate Standard materials price $15.50 per hour $112 perton Quantities Actual hours incurred and used 4,500 hours Actual quantity of materials purchased and used 1.100 tons Standard hours used 4.540 hours Standard quantity of materials used 1,085 tons Compute...

  • The standard cost of Product B manufactured by Pharrell Company includes 2.7 units of direct materials...

    The standard cost of Product B manufactured by Pharrell Company includes 2.7 units of direct materials at $6.20 per unit. During June, 26,700 units of direct materials are purchased at a cost of $6.05 per unit, and 26,700 units of direct materials are used to produce 9,800 units of Product B. (a) Compute the total materials variance and the price and quantity variances. Total materials variance $enter a dollar amount select an option Neither favorable nor unfavorableUnfavorableFavorable Materials price variance...

  • Lewis Company’s standard labor cost of producing one unit of Product DD is 3.8 hours at...

    Lewis Company’s standard labor cost of producing one unit of Product DD is 3.8 hours at the rate of $10.3 per hour. During August, 40,200 hours of labor are incurred at a cost of $10.50 per hour to produce 10,500 units of Product DD. (a) Compute the total labor variance. Total labor variance $enter a dollar amount of the total labor variance select a type of the total variance UnfavorableFavorableNeither favorable nor unfavorable (b) Compute the labor price and quantity...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT